# 52.247-4 Inspection of Shipping and Receiving Facilities.
Type: Provision
Prescribed in: 47.207-1(c)
Current version date: APR 1984

## Prescription and Applicability

### FAR Prescription, 47.207-1(c)

(c) Inspection of shipping and receiving facilities. The contracting officer shall insert the provision at 52.247-4, Inspection of Shipping and Receiving Facilities, when it is desired for offerors to inspect the shipping, receiving, or other sites to ensure realistic bids.

## Current Text

52.247-4 Inspection of Shipping and Receiving Facilities.

As prescribed in 47.207-1(c), insert the following provision in solicitations for transportation or for transportation-related services when it is desired for offerors to inspect the shipping, receiving, or other sites to ensure realistic bids:

Inspection of Shipping and Receiving Facilities (APR 1984)

(a) Offerors are urged to inspect the shipping and receiving facilities where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance.

(b) Site visits have been scheduled as follows:

(locations)

(dates)

(times)

(c) For further information offerors may contact:

(name)

(telephone)

(End of provision)

## Suggested Questions

You can ask your AI assistant:
- Should I include this provision in my solicitation?
- Does this clause apply to commercial acquisitions?
- Does this clause apply to R&D contracts under Part 35?
- Which alternate should I use for a multiple-award contract?
- Are there any active Class Deviations that modify this clause?
- What changed in the most recent amendment?

---
Source: https://part52.dev
Generated: 2026-04-21 17:40 UTC
Reference: https://www.ecfr.gov/current/title-48/section-52.247-4