252.217-7010

Performance.
Search on acquisition.gov · View on eCFR.gov
Effective Date
JUL 2009
Active Deviations
1
Versions
1 (since 2016-12-22)
DEV
This clause is modified by 1 active class deviation
  • 2026-O0027 — DFARS RFO Implementation (Part 17)
    Add clause 252.217-7010
View per-deviation details →
252.217-7010 Performance.

As prescribed in 217.7104(a), use the following clause:

Performance (JUL 2009)

(a) Upon the award of a job order, the Contractor shall promptly start the work specified and shall diligently prosecute the work to completion. The Contractor shall not start work until the job order has been awarded except in the case of emergency work ordered by the Contracting Officer under the Job Orders and Compensation clause of the Master Agreement.

(b) The Government shall deliver the vessel described in the job order at the time and location specified in the job order. Upon completion of the work, the Government shall accept delivery of the vessel at the time and location specified in the job order.

(c) The Contractor shall, without charge and without specific requirement in a job order,—

(1) Make available at the plant to personnel of the vessel while in dry dock or on a marine railway, sanitary lavatory and similar facilities acceptable to the Contracting Officer;

(2) Supply and maintain suitable brows and gangways from the pier, dry dock, or marine railway to the vessel;

(3) Treat salvage, scrap or other ship's material of the Government resulting from performance of the work as items of Government-furnished property, in accordance with the Government Property clause;

(4) Perform, or pay the cost of, any repair, reconditioning or replacement made necessary as the result of the use by the Contractor of any of the vessel's machinery, equipment or fittings, including, but not limited to, winches, pumps, rigging, or pipe lines; and

(5) Furnish suitable offices, office equipment and telephones at or near the site of the work for the Government's use.

(d) The job order will state whether dock and sea trials are required to determine whether or not the Contractor has satisfactorily performed the work.

(1) If dock and sea trials are required, the vessel shall be under the control of the vessel's commander and crew.

(2) The Contractor shall not conduct dock and sea trials not specified in the job order without advance approval of the Contracting Officer. Dock and sea trials not specified in the job order shall be at the Contractor's expense and risk.

(3) The Contractor shall provide and install all fittings and appliances necessary for dock and sea trials. The Contractor shall be responsible for care, installation, and removal of instruments and apparatus furnished by the Government for use in the trials.

(End of clause)

[56 FR 36479, July 31, 1991, as amended at 74 FR 37648, July 29, 2009]
RFO
Prescription superseded under the RFO

The prescription shown below is from the codified eCFR. Under the RFO, the prescribing section may have been revised, relocated or reserved. See the deviation memorandum for the current prescription authority.

View deviation: 2026-O0027 →

R-DFARS Prescription Source

This clause is prescribed in the R-DFARS by the following deviation:

  • 2026-O0027 — DFARS RFO Implementation (Part 17) (DFARS Part 217)
    Add clause 252.217-7010
217.7104(a)
(a) Use the following clauses in solicitations for, and in, master agreements for repair and alteration of vessels:
(1) 252.217-7003, Changes.
(2) 252.217-7004, Job Orders and Compensation.
(3) 252.217-7005, Inspection and Manner of Doing Work.
(4) 252.217-7006, Title.
(5) 252.217-7007, Payments.
(6) 252.217-7008, Bonds.
(7) 252.217-7009, Default.
(8) 252.217-7010, Performance.
(9) 252.217-7011, Access to Vessel.
(10) 252.217-7012, Liability and Insurance.
(11) 252.217-7013, Guarantees.
(12) 252.217-7014, Discharge of Liens.
(13) 252.217-7015, Safety and Health.
(14) 252.217-7016, Plant Protection, as applicable. (b)(1) Incorporate in solicitations for, and in, job orders, the clauses in the master agreement, and any other clauses on subjects not covered by the master agreement, but applicable to the job order to be awarded.
(2) Use the clause at 252.217-7016, Plant Protection, in job orders where performance is to occur at the contractor's facility.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC. Cross-references within the prescription are not resolved automatically.

Regulatory Stack

The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.

R-DFARS R-DFARS Prescription Per Deviation 2026-O0027 (DFARS Part 217)
2026-O0027: DFARS RFO Implementation (Part 17) — DFARS Part 217

View Deviation 2026-O0027 →

DFARS DFARS Supplement (eCFR) ⚠ May be superseded by RFO 217.7104(a)
(a) Use the following clauses in solicitations for, and in, master agreements for repair and alteration of vessels:
(1) 252.217-7003, Changes.
(2) 252.217-7004, Job Orders and Compensation.
(3) 252.217-7005, Inspection and Manner of Doing Work.
(4) 252.217-7006, Title.
(5) 252.217-7007, Payments.
(6) 252.217-7008, Bonds.
(7) 252.217-7009, Default.
(8) 252.217-7010, Performance.
(9) 252.217-7011, Access to Vessel.
(10) 252.217-7012, Liability and Insurance.
(11) 252.217-7013, Guarantees.
(12) 252.217-7014, Discharge of Liens.
(13) 252.217-7015, Safety and Health.
(14) 252.217-7016, Plant Protection, as applicable. (b)(1) Incorporate in solicitations for, and in, job orders, the clauses in the master agreement, and any other clauses on subjects not covered by the master agreement, but applicable to the job order to be awarded.
(2) Use the clause at 252.217-7016, Plant Protection, in job orders where performance is to occur at the contractor's facility.

Search on acquisition.gov · View on eCFR.gov

Version History

Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.

No version history available from eCFR.

Active Class Deviations

DFARS RFO Implementation (Part 17) Add clause 252.217-7010
MODIFIED