| Threshold | Value | Source | Adjustment | Notes |
|---|---|---|---|---|
| Micro-Purchase Threshold MPT | $10,000 | FAR 2.101 |
Inflation (41 U.S.C. 1908) | Higher thresholds apply for construction ($2,000), services subject to Service Contract Labor Standards ($2,500) and acquisitions at contingency operations ($35,000) |
| Simplified Acquisition Threshold SAT | $250,000 | FAR 2.101 |
Inflation (41 U.S.C. 1908) | Determines applicability of simplified acquisition procedures (FAR Part 13) and numerous clause prescriptions |
| Certified Cost or Pricing Data Threshold TINA Threshold | $2,000,000 | FAR 15.403-4 |
Statutory (10 U.S.C. 3702) | Threshold for requiring certified cost or pricing data. Set at $2M by NDAA FY2018 Sec 811 |
| Commercial Item Test Threshold | $10,000,000 | FAR 13.500(a) |
Statutory (41 U.S.C. 1903) | Maximum for use of simplified procedures for certain commercial products and services |
| Service Contract Labor Standards Threshold SCLS | $2,500 | FAR 22.1003-1 |
Statutory (41 U.S.C. 6707) | Contracts for services subject to the McNamara-O'Hara Service Contract Act |
| Construction Wage Rate Requirements Threshold Davis-Bacon | $2,000 | FAR 22.403-1 |
Statutory (40 U.S.C. 3142) | Contracts for construction subject to the Davis-Bacon Act |
| Performance Bond Threshold | $150,000 | FAR 28.102-1 |
Inflation (41 U.S.C. 1908) | Construction contracts exceeding this amount require performance and payment bonds |
| Payment Bond Threshold | $40,000 | FAR 28.102-1 |
Statutory (40 U.S.C. 3131) | Construction contracts exceeding $40,000 but not exceeding $150,000 require payment protection |
| Small Purchase Threshold for Commercial Items | $35,000 | FAR 13.302-5(a) |
Inflation (41 U.S.C. 1908) | Below this amount, contracting officers need not include terms and conditions required by FAR Part 12 |
| Substantial Bundling Threshold | $8,000,000 | FAR 2.101 |
Inflation (41 U.S.C. 1908) | DoD: $8M for R&D, $65.5M for production; Other agencies: $2M. Multiple-award contracts or orders above these amounts |
Thresholds are adjusted periodically per 41 U.S.C. 1908 or set by statute.
Values shown reflect the most recent FAR update. Verify against FAR 1.109
and the current Federal Acquisition Circular.
Use with AI assistant
Copy a link and prompt for use with Gemini or another AI assistant.