Economic Purchase Quantity—Supplies.
View on acquisition.gov · View on eCFR.gov
Effective Date
AUG 1987
Active Deviations
Versions
1 (since 2017-01-01)
RFO
RFO Version Available

The Revolutionary FAR Overhaul has published a revised version of this clause. The RFO version supersedes the eCFR text below for contracts using the RFO model; see the RFO deviation for applicability.

View RFO version
52.207-4 Economic Purchase Quantity—Supplies.

As prescribed in 7.203, insert the following provision:

Economic Purchase Quantity—Supplies (AUG 1987)

(a) Offerors are invited to state an opinion on whether the quantity(ies) of supplies on which bids, proposals or quotes are requested in this solicitation is (are) economically advantageous to the Government.

(b) Each offeror who believes that acquisitions in different quantities would be more advantageous is invited to recommend an economic purchase quantity. If different quantities are recommended, a total and a unit price must be quoted for applicable items. An economic purchase quantity is that quantity at which a significant price break occurs. If there are significant price breaks at different quantity points, this information is desired as well.

Offeror Recommendations

Item

Quantity

Price quotation

Total

(c) The information requested in this provision is being solicited to avoid acquisitions in disadvantageous quantities and to assist the Government in developing a data base for future acquisitions of these items. However, the Government reserves the right to amend or cancel the solicitation and resolicit with respect to any individual item in the event quotations received and the Government's requirements indicate that different quantities should be acquired.

(End of provision)

[50 FR 35479, Aug. 30, 1985, as amended at 52 FR 30078, Aug. 12, 1987]
7.203
Contracting officers shall insert the provision at 52.207-4, Economic Purchase Quantity-Supplies, in solicitations for supplies. The provision need not be inserted if the solicitation is for a contract under the General Services Administration's multiple award schedule contract program, or if the contracting officer determines that-

(a) The Government already has the data;

(b) The data is otherwise readily available; or

(c) It is impracticable for the Government to vary its future requirements.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC. Cross-references within the prescription are not resolved automatically.

Regulatory Stack

The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.

RFO RFO Version Overhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.

Search on acquisition.gov

FAR FAR Prescription 7.203
Contracting officers shall insert the provision at 52.207-4, Economic Purchase Quantity-Supplies, in solicitations for supplies. The provision need not be inserted if the solicitation is for a contract under the General Services Administration's multiple award schedule contract program, or if the contracting officer determines that-

(a) The Government already has the data;

(b) The data is otherwise readily available; or

(c) It is impracticable for the Government to vary its future requirements.

View on acquisition.gov · View on eCFR.gov

Version History

Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.

No version history available from eCFR.

RFO Version

Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).

Clause Text

Substantive changes. The RFO version differs materially from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.207-4 Economic Purchase Quantity-Supplies.
eCFR (codified)
RFO (implemented)
1 added
_________________________________________________________________________________
1 added
_________________________________________________________________________________
1 added
____________
1 added
____________
1 added
____________
1 added
____________
15 removed
[50 FR 35479, Aug. 30, 1985, as amended at 52 FR 30078, Aug. 12, 1987]

Prescription

Substantive changes. The RFO prescription differs materially from the eCFR prescription.
eCFR (codified)
RFO (implemented)
Unchanged
52.207-4 Economic Purchase Quantity-Supplies.: Prescription
eCFR (codified)
RFO (implemented)
4 added, 7 removed
Contracting officers shall insert the provision at 52.207-4, Economic Purchase Quantity-Supplies, in solicitations for supplies. The provision need not be inserted if the solicitation is for a contract under the General Services Administration's multiple award schedule contract program, or if the contracting officer determines that-
Insert the provision at 52.207-4, Economic Purchase Quantity—Supplies, in solicitations for supplies. The provision may not be necessary if the solicitation is for a contract under the General Services Administration's multiple award schedule contract program, or if the contracting officer determines that—
7 removed
(a)
(a) The Government already has the data;
(a)
8 removed
(b)
(b) The data is otherwise readily available; or
(b)
12 removed
(c)
(c) It is impracticable for the Government to vary its future requirements.
(c)

Source: acquisition.gov RFO Part 52 · Prescribing Part 7