52.209-3 First Article Approval—Contractor Testing.

As prescribed in 9.308-1 (a) and (b), insert the following clause:

First Article Approval—Contractor Testing (SEP 1989)

[
Contracting Officer shall insert details
]

(a) The Contractor shall test __ unit(s) of Lot/Item __ as specified in this contract. At least __ calendar days before the beginning of first article tests, the Contractor shall notify the Contracting Officer, in writing, of the time and location of the testing so that the Government may witness the tests.

(b) The Contractor shall submit the first article test report within __ calendar days from the date of this contract to __ [
insert address of the Government activity to receive the report
] marked "FIRST ARTICLE TEST REPORT: Contract No. __, Lot/Item No. __." Within __ calendar days after the Government receives the test report, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval shall state any further action required of the Contractor. A notice of disapproval shall cite reasons for the disapproval.

(c) If the first article is disapproved, the Contractor, upon Government request, shall repeat any or all first article tests. After each request for additional tests, the Contractor shall make any necessary changes, modifications, or repairs to the first article or select another first article for testing. All costs related to these tests are to be borne by the Contractor, including any and all costs for additional tests following a disapproval. The Contractor shall then conduct the tests and deliver another report to the Government under the terms and conditions and within the time specified by the Government. The Government shall take action on this report within the time specified in paragraph (b) above. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule, or for any additional costs to the Government related to these tests.

(d) If the Contractor fails to deliver any first article report on time, or the Contracting Officer disapproves any first article, the Contractor shall be deemed to have failed to make delivery within the meaning of the Default clause of this contract.

(e) Unless otherwise provided in the contract, and if the approved first article is not consumed or destroyed in testing, the Contractor may deliver the approved first article as part of the contract quantity if it meets all contract requirements for acceptance.

(f) If the Government does not act within the time specified in paragraph (b) or (c) above, the Contracting Officer shall, upon timely written request from the Contractor, equitably adjust under the Changes clause of this contract the delivery or performance dates and/or the contract price, and any other contractual term affected by the delay.

(g) Before first article approval, the acquisition of materials or components for, or the commencement of production of, the balance of the contract quantity is at the sole risk of the Contractor. Before first article approval, the costs thereof shall not be allocable to this contract for (1) progress payments, or (2) termination settlements if the contract is terminated for the convenience of the Government.

(h) The Government may waive the requirement for first article approval test where supplies identical or similar to those called for in the schedule have been previously furnished by the offeror/contractor and have been accepted by the Government. The offeror/contractor may request a waiver.

(End of clause)

Alternate I
(JAN 1997). As prescribed in 9.308-1 (a)(2) and (b)(2), add the following paragraph (i) to the basic clause:

(i) The Contractor shall produce both the first article and the production quantity at the same facility.

Alternate II
(SEP 1989). As prescribed in 9.308-1 (a)(3) and (b)(3), substitute the following paragraph (g) for paragraph (g) of the basic clause:

(g) Before first article approval, the Contracting Officer may, by written authorization, authorize the Contractor to acquire specific materials or components or to commence production to the extent essential to meet the delivery schedules. Until first article approval is granted, only costs for the first article and costs incurred under this authorization are allocable to this contract for (1) progress payments, or (2) termination settlements if the contract is terminated for the convenience of the Government. If first article tests reveal deviations from contract requirements, the Contractor shall, at the location designated by the Government, make the required changes or replace all items produced under this contract at no change in the contract price.

[48 FR 42478, Sept. 19, 1983, as amended at 54 FR 34757, Aug. 21, 1989; 55 FR 25531, June 21, 1990; 62 FR 238, Jan. 2, 1997]
9.308-1
(a)
(1) The contracting officer shall insert the clause at 52.209-3, First Article Approval-Contractor Testing, in solicitations and contracts when a fixed-price contract is contemplated and it is intended that the contract require-

(i) First article approval; and

(ii) That the contractor be required to conduct the first article testing.

(2) If it is intended that the contractor be required to produce the first article and the production quantity at the same facility, the contracting officer shall use the clause with its Alternate I.

(3) If it is necessary to authorize the contractor to purchase material or to commence production before first article approval, the contracting officer shall use the clause with its Alternate II.

(b)
(1) The contracting officer shall insert a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, in solicitations and contracts when a cost-reimbursement contract is contemplated and it is intended that the contract require

(i) First article approval and

(ii) That the contractor be required to conduct the first article test.

(2) If it is intended that the contractor be required to produce the first article and the production quantity at the same facility, the contracting officer shall use a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, with its Alternate I.

(3) If it is necessary to authorize the contractor to purchase material or to commence production before first article approval, the contracting officer shall use a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, with its Alternate II.

Alternate I

9.308-1
(a)
(1) The contracting officer shall insert the clause at 52.209-3, First Article Approval-Contractor Testing, in solicitations and contracts when a fixed-price contract is contemplated and it is intended that the contract require-

(i) First article approval; and

(ii) That the contractor be required to conduct the first article testing.

(2) If it is intended that the contractor be required to produce the first article and the production quantity at the same facility, the contracting officer shall use the clause with its Alternate I.

(3) If it is necessary to authorize the contractor to purchase material or to commence production before first article approval, the contracting officer shall use the clause with its Alternate II.

(b)
(1) The contracting officer shall insert a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, in solicitations and contracts when a cost-reimbursement contract is contemplated and it is intended that the contract require

(i) First article approval and

(ii) That the contractor be required to conduct the first article test.

(2) If it is intended that the contractor be required to produce the first article and the production quantity at the same facility, the contracting officer shall use a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, with its Alternate I.

(3) If it is necessary to authorize the contractor to purchase material or to commence production before first article approval, the contracting officer shall use a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, with its Alternate II.

Alternate II

9.308-1
(a)
(1) The contracting officer shall insert the clause at 52.209-3, First Article Approval-Contractor Testing, in solicitations and contracts when a fixed-price contract is contemplated and it is intended that the contract require-

(i) First article approval; and

(ii) That the contractor be required to conduct the first article testing.

(2) If it is intended that the contractor be required to produce the first article and the production quantity at the same facility, the contracting officer shall use the clause with its Alternate I.

(3) If it is necessary to authorize the contractor to purchase material or to commence production before first article approval, the contracting officer shall use the clause with its Alternate II.

(b)
(1) The contracting officer shall insert a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, in solicitations and contracts when a cost-reimbursement contract is contemplated and it is intended that the contract require

(i) First article approval and

(ii) That the contractor be required to conduct the first article test.

(2) If it is intended that the contractor be required to produce the first article and the production quantity at the same facility, the contracting officer shall use a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, with its Alternate I.

(3) If it is necessary to authorize the contractor to purchase material or to commence production before first article approval, the contracting officer shall use a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, with its Alternate II.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC. Cross-references within the prescription are not resolved automatically.

Regulatory Stack

The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.

RFO RFO Version Overhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.

Search on acquisition.gov

FAR FAR Prescription 9.308-1
(a)
(1) The contracting officer shall insert the clause at 52.209-3, First Article Approval-Contractor Testing, in solicitations and contracts when a fixed-price contract is contemplated and it is intended that the contract require-

(i) First article approval; and

(ii) That the contractor be required to conduct the first article testing.

(2) If it is intended that the contractor be required to produce the first article and the production quantity at the same facility, the contracting officer shall use the clause with its Alternate I.

(3) If it is necessary to authorize the contractor to purchase material or to commence production before first article approval, the contracting officer shall use the clause with its Alternate II.

(b)
(1) The contracting officer shall insert a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, in solicitations and contracts when a cost-reimbursement contract is contemplated and it is intended that the contract require

(i) First article approval and

(ii) That the contractor be required to conduct the first article test.

(2) If it is intended that the contractor be required to produce the first article and the production quantity at the same facility, the contracting officer shall use a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, with its Alternate I.

(3) If it is necessary to authorize the contractor to purchase material or to commence production before first article approval, the contracting officer shall use a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, with its Alternate II.

View on acquisition.gov · View on eCFR.gov

Version History

Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.

2 versions tracked from 2017-01-01 to 2018-01-24.
JAN 2018 January 24, 2018 CURRENT
Removed in this version
Added in this version
Unchanged
JAN 2017 (previous)
JAN 2018 (current)
3 added, 3 removed
(a)
(a) The Contractor shall test _ unit(s) of Lot/Item _ as specified in this contract. At least _ calendar days before the beginning of first article tests, the Contractor shall notify the Contracting Officer, in writing, of the time and location of the testing so that the Government may witness the tests.
(a)
(a) The Contractor shall test __ unit(s) of Lot/Item __ as specified in this contract. At least __ calendar days before the beginning of first article tests, the Contractor shall notify the Contracting Officer, in writing, of the time and location of the testing so that the Government may witness the tests.
3 added, 3 removed
(b)
(b) The Contractor shall submit the first article test report within _ calendar days from the date of this contract to _ [insert address of the Government activity to receive the report] marked "FIRST ARTICLE TEST REPORT: Contract No. __, Lot/Item No. __." Within _ calendar days after the Government receives the test report, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract.
(b)
(b) The Contractor shall submit the first article test report within __ calendar days from the date of this contract to __ [insert address of the Government activity to receive the report] marked "FIRST ARTICLE TEST REPORT: Contract No. __, Lot/Item No. __." Within __ calendar days after the Government receives the test report, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract.
JAN 2017 January 1, 2017 SUBSTANTIVE
Earliest version available from the eCFR

RFO Version

Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).

Clause Text

Minor revisions. The RFO version has formatting or editorial changes from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.209-3 First Article Approval-Contractor Testing.
eCFR (codified)
RFO (implemented)
1 added, 2 removed
As prescribed in 9.308-1 (a) and (b), insert the following clause:
As prescribed in 9.308-1(a) and (b), insert the following clause:
3 added, 3 removed
First Article Approval—Contractor Testing (SEP 1989)
First Article Approval-Contractor Testing (Deviation Date)
1 added, 2 removed
[Contracting Officer shall insert details]
[Contracting Officer inserts details]
3 added, 3 removed
(a)
(a) The Contractor shall test __ unit(s) of Lot/Item __ as specified in this contract. At least __ calendar days before the beginning of first article tests, the Contractor shall notify the Contracting Officer, in writing, of the time and location of the testing so that the Government may witness the tests.
(a)
(a) The Contractor shall test _____ unit(s) of Lot/Item _____ as specified in this contract. At least _____ calendar days before the beginning of first article tests, the Contractor shall notify the Contracting Officer, in writing, of the time and location of the testing so that the Government may witness the tests.
9 added, 9 removed
(b)
(b) The Contractor shall submit the first article test report within __ calendar days from the date of this contract to __ [insert address of the Government activity to receive the report] marked "FIRST ARTICLE TEST REPORT: Contract No. __, Lot/Item No. __." Within __ calendar days after the Government receives the test report, the Contracting Officer shall notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval shall state any further action required of the Contractor. A notice of disapproval shall cite reasons for the disapproval.
(b)
(b) The Contractor shall submit the first article test report within _____ calendar days from the date of this contract to _____ [insert address of the Government activity to receive the report] marked “FIRST ARTICLE TEST REPORT: Contract No. _______, Lot/Item No. _______." Within _____ calendar days after the Government receives the test report, the Contracting Officer will notify the Contractor, in writing, of the conditional approval, approval, or disapproval of the first article. The notice of conditional approval or approval shall not relieve the Contractor from complying with all requirements of the specifications and all other terms and conditions of this contract. A notice of conditional approval will state any further action required of the Contractor. A notice of disapproval will cite reasons for the disapproval.
1 added, 1 removed
(c)
The Contractor shall then conduct the tests and deliver another report to the Government under the terms and conditions and within the time specified by the Government. The Government shall take action on this report within the time specified in paragraph (b) above. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule, or for any additional costs to the Government related to these tests.
(c)
The Contractor shall then conduct the tests and deliver another report to the Government under the terms and conditions and within the time specified by the Government. The Government will take action on this report within the time specified in paragraph (b) above. The Government reserves the right to require an equitable adjustment of the contract price for any extension of the delivery schedule, or for any additional costs to the Government related to these tests.
1 added, 1 removed
(f)
(f) If the Government does not act within the time specified in paragraph (b) or (c) above, the Contracting Officer shall, upon timely written request from the Contractor, equitably adjust under the Changes clause of this contract the delivery or performance dates and/or the contract price, and any other contractual term affected by the delay.
(f)
(f) If the Government does not act within the time specified in paragraph (b) or (c) above, the Contracting Officer will, upon timely written request from the Contractor, equitably adjust under the Changes clause of this contract the delivery or performance dates and/or the contract price, and any other contractual term affected by the delay.
1 added, 2 removed
Alternate I (JAN 1997). As prescribed in 9.308-1 (a)(2) and (b)(2), add the following paragraph (i) to the basic clause:
Alternate I (Jan 1997). As prescribed in 9.308-1(a)(2) and (b)(2), add the following paragraph (i) to the basic clause:
2 added, 4 removed
Alternate II (SEP 1989). As prescribed in 9.308-1 (a)(3) and (b)(3), substitute the following paragraph (g) for paragraph (g) of the basic clause:
Alternate II (Sept1989). As prescribed in 9.308-1(a)(3) and (b)(3), substitute the following paragraph (g) for paragraph (g) of the basic clause:
27 removed
[48 FR 42478, Sept. 19, 1983, as amended at 54 FR 34757, Aug. 21, 1989; 55 FR 25531, June 21, 1990; 62 FR 238, Jan. 2, 1997]

Prescription

Substantive changes. The RFO prescription differs materially from the eCFR prescription.
eCFR (codified)
RFO (implemented)
Unchanged
52.209-3 First Article Approval-Contractor Testing.: Prescription
eCFR (codified)
RFO (implemented)
58 added, 20 removed
(a)
(a) (1) The contracting officer shall insert the clause at 52.209-3, First Article Approval-Contractor Testing, in solicitations and contracts when a fixed-price contract is contemplated and it is intended that the contract require-
(a)
(b) Notwithstanding paragraph (a), the contracting officer may, before approval of the first article, authorize the contractor to acquire specific materials or components or commence production to the extent necessary to meet the delivery schedule (see Alternate II of the clause at 52.209-3, First Article Approval—Contractor Testing, and Alternate II of the clause at 52.209-4, First Article Approval—Government Testing. Costs incurred based on this authorization are allocable to the contract for—
5 removed
(i)
(i) First article approval; and
(i)
12 removed
(ii)
(ii) That the contractor be required to conduct the first article testing.
(ii)
34 removed
(2)
(2) If it is intended that the contractor be required to produce the first article and the production quantity at the same facility, the contracting officer shall use the clause with its Alternate I.
(2)
31 removed
(3)
(3) If it is necessary to authorize the contractor to purchase material or to commence production before first article approval, the contracting officer shall use the clause with its Alternate II.
(3)
39 removed
(b)
(b) (1) The contracting officer shall insert a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, in solicitations and contracts when a cost-reimbursement contract is contemplated and it is intended that the contract require
(b)
5 removed
(i)
(i) First article approval and
(i)
12 removed
(ii)
(ii) That the contractor be required to conduct the first article test.
(ii)
46 removed
(2)
(2) If it is intended that the contractor be required to produce the first article and the production quantity at the same facility, the contracting officer shall use a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, with its Alternate I.
(2)
43 removed
(3)
(3) If it is necessary to authorize the contractor to purchase material or to commence production before first article approval, the contracting officer shall use a clause substantially the same as the clause at 52.209-3, First Article Approval--Contractor Testing, with its Alternate II.
(3)

Source: acquisition.gov RFO Part 52 · Prescribing Part 9