A community resource for the acquisition workforce
—not a .gov website
Community-maintained
part52.dev is built and maintained by members of the federal acquisition community to help with navigating DoD acquisition regulation.
Not affiliated with the U.S. Government
This site is not operated, endorsed or sanctioned by the U.S. Government. Data is sourced from public regulatory sources including eCFR.gov and acquisition.gov. Always verify against official sources.
The Revolutionary FAR Overhaul has published a revised version of this clause. The RFO version supersedes the eCFR text below for contracts using the RFO model; see the RFO deviation for applicability.
52.214-18 Preparation of Bids—Construction.
As prescribed in 14.201-6(l), insert the following provision:
Preparation of Bids—Construction (APR 1984)
(a) Bids must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including—
(1) Lump sum bidding;
(2) Alternate prices;
(3) Units of construction; or
(4) Any combination of subparagraphs (1) through (3) above.
(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words
no bid
in the space provided for any item on which no price is submitted.
(d) Alternate bids will not be considered unless this solicitation authorizes their submission.
(End of provision)
[48 FR 42478, Sept. 19, 1983, as amended at 55 FR 25531, June 21, 1990]
14.201-6(l)
(l) Insert the provision at 52.214-18, Preparation of Bids-Construction, in invitations for bids for construction work.
DFARS Supplementary Guidance
214.201-6
(2) Use the provisions at 252.215-7007, Notice of Intent to Resolicit, and 252.215-7008, Only One Offer, as prescribed at 215.371-6 and 215.408(3), respectively.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC.
Cross-references within the prescription are not resolved automatically.
Regulatory Stack
The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.
RFORFO VersionOverhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.
(2) Use the provisions at 252.215-7007, Notice of Intent to Resolicit, and 252.215-7008, Only One Offer, as prescribed at 215.371-6 and 215.408(3), respectively.
Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.
No version history available from eCFR.
RFO Version
Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).
Clause Text
Substantive changes. The RFO version differs materially from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.214-18 Preparation of Bids-Construction.
eCFR (codified)
RFO (implemented)
1 added, 1 removed
As prescribed in 14.201-6(l), insert the following provision:
As prescribed in 14.207(h), insert the following provision:
Preparation of Bids—Construction (APR 1984)
Preparation of Bids-Construction (Apr 1984)
1 added, 36 removed
(a)
(a) Bids must be (1) submitted on the forms furnished by the Government or on copies of those forms, and (2) manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(a)
(a) Bids must be-
16 added
(1)
(1)
(1) Submitted on the forms furnished by the Government or on copies of those forms, and
19 added
(2)
(2)
(2) Manually signed. The person signing a bid must initial each erasure or change appearing on any bid form.
(b)
(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including—
(b)
(b) The bid form may require bidders to submit bid prices for one or more items on various bases, including-
(1)
(1) Lump sum bidding;
(1)
(1) Lump sum bidding;
(2)
(2) Alternate prices;
(2)
(2) Alternate prices;
(3)
(3) Units of construction; or
(3)
(3) Units of construction; or
6 added, 4 removed
(4)
(4) Any combination of subparagraphs (1) through (3) above.
(4)
(4) Any combination of paragraphs (b)(1) through (b)(3) of this provision.
2 added, 2 removed
(c)
(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words no bid in the space provided for any item on which no price is submitted.
(c)
(c) If the solicitation requires bidding on all items, failure to do so will disqualify the bid. If bidding on all items is not required, bidders should insert the words "no bid" in the space provided for any item on which no price is submitted.
(d)
(d) Alternate bids will not be considered unless this solicitation authorizes their submission.
(d)
(d) Alternate bids will not be considered unless this solicitation authorizes their submission.
(End of provision)
(End of provision)
15 removed
[48 FR 42478, Sept. 19, 1983, as amended at 55 FR 25531, June 21, 1990]
Prescription
Substantive changes. The RFO prescription differs materially from the eCFR prescription.
eCFR (codified)
RFO (implemented)
Unchanged
52.214-18 Preparation of Bids-Construction.: Prescription
eCFR (codified)
RFO (implemented)
2 added, 2 removed
(l)
(l) Insert the provision at 52.214-18, Preparation of Bids-Construction, in invitations for bids for construction work.
(l)
(h) Insert the provision at 52.214-18, Preparation of Bids—Construction, in invitations for bids for construction work.