FAR Clause ACTIVE

52.215-1

Instructions to Offerors—Competitive Acquisition.
View on acquisition.gov · View on eCFR.gov
Effective Date
NOV 2021
Active Deviations
1
Versions
3 (since 2017-01-01)
RFO
RFO Version Available

The Revolutionary FAR Overhaul has published a revised version of this clause. The RFO version supersedes the eCFR text below for contracts using the RFO model; see the RFO deviation for applicability.

View RFO version
DEV
This clause is modified by 1 active class deviation
  • 2026-O0048 — DFARS RFO Implementation (Part 15)
    Add clause 52.215-1
View per-deviation details →
52.215-1 Instructions to Offerors—Competitive Acquisition.

As prescribed in 15.209(a), insert the following provision:

Instructions to Offerors—Competitive Acquisition (NOV 2021)

(a)
Definitions.
As used in this provision—

Discussions
are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer's discretion, result in the offeror being allowed to revise its proposal.

In writing, writing,
or
written
means any worded or numbered expression that can be read, reproduced, and later communicated, and includes electronically transmitted and stored information.

Proposal modification
is a change made to a proposal before the solicitation's closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.

Proposal revision
is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.

Time,
if stated as a number of days, is calculated using calendar days, unless otherwise specified, and will include Saturdays, Sundays, and legal holidays. However, if the last day falls on a Saturday, Sunday, or legal holiday, then the period shall include the next working day.

(b)
Amendments to solicitations.
If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).

(c)
Submission, modification, revision, and withdrawal of proposals.
(1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.

(2) The first page of the proposal must show—

(i) The solicitation number;

(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);

(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;

(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror's behalf with the Government in connection with this solicitation; and

(v) Name, title, and signature of person authorized to sign the proposal. Proposals signed by an agent shall be accompanied by evidence of that agent's authority, unless that evidence has been previously furnished to the issuing office.

(3)
Submission, modification, revision, and withdrawal of proposals.
(i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.

(ii)(A) Any proposal, modification, or revision, received at the Government office designated in the solicitation after the exact time specified for receipt of offers is "late" and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and—

(
1
) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or

(
2
) There is acceptable evidence to establish that it was received at the Government installation designated for receipt of offers and was under the Government's control prior to the time set for receipt of offers; or

(
3
) It is the only proposal received.

(B) However, a late modification of an otherwise successful proposal that makes its terms more favorable to the Government, will be considered at any time it is received and may be accepted.

(iii) Acceptable evidence to establish the time of receipt at the Government installation includes the time/date stamp of that installation on the proposal wrapper, other documentary evidence of receipt maintained by the installation, or oral testimony or statements of Government personnel.

(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.

(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.

(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.

(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.

(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.

(7) Offerors may submit revised proposals only if requested or allowed by the Contracting Officer.

(8) Proposals may be withdrawn at any time before award. Withdrawals are effective upon receipt of notice by the Contracting Officer.

(d)
Offer expiration date.
Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).

(e)
Restriction on disclosure and use of data.
Offerors that include in their proposals data that they do not want disclosed to the public for any purpose, or used by the Government except for evaluation purposes, shall—

(1) Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed—in whole or in part—for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of—or in connection with—the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and

(2) Mark each sheet of data it wishes to restrict with the following legend: Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.

(f)
Contract award.
(1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.

(2) The Government may reject any or all proposals if such action is in the Government's interest.

(3) The Government may waive informalities and minor irregularities in proposals received.

(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.

(5) The Government reserves the right to make an award on any item for a quantity less than the quantity offered, at the unit cost or prices offered, unless the offeror specifies otherwise in the proposal.

(6) The Government reserves the right to make multiple awards if, after considering the additional administrative costs, it is in the Government's best interest to do so.

(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.

(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.

(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.

(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.

(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:

(i) The agency's evaluation of the significant weak or deficient factors in the debriefed offeror's offer.

(ii) The overall evaluated cost or price and technical rating of the successful and the debriefed offeror and past performance information on the debriefed offeror.

(iii) The overall ranking of all offerors, when any ranking was developed by the agency during source selection.

(iv) A summary of the rationale for award.

(v) For acquisitions of commercial products, the make and model of the product to be delivered by the successful offeror.

(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.

(End of provision)

Alternate I
(OCT 1997). As prescribed in 15.209(a)(1), substitute the following paragraph (f)(4) for paragraph (f)(4) of the basic provision:

(f)(4) The Government intends to evaluate proposals and award a contract after conducting discussions with offerors whose proposals have been determined to be within the competitive range. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals. Therefore, the offeror's initial proposal should contain the offeror's best terms from a price and technical standpoint.

Alternate II
(OCT 1997). As prescribed in 15.209(a)(2), add a paragraph (c)(9) substantially the same as the following to the basic clause:

(9) Offerors may submit proposals that depart from stated requirements. Such proposals shall clearly identify why the acceptance of the proposal would be advantageous to the Government. Any deviations from the terms and conditions of the solicitation, as well as the comparative advantage to the Government, shall be clearly identified and explicitly defined. The Government reserves the right to amend the solicitation to allow all offerors an opportunity to submit revised proposals based on the revised requirements.

[62 FR 51259, Sept. 30, 1997; 64 FR 51841, Sept. 24, 1999, as amended at 64 FR 72433, 72451, Dec. 27, 1999; 66 FR 2135, Jan. 10, 2001; 68 FR 69258, Dec. 11, 2003; 82 FR 4715, Jan. 13, 2017; 86 FR 61034, Nov. 4, 2021]
RFO
Prescription superseded under the RFO

The prescription shown below is from the codified eCFR. The Revolutionary FAR Overhaul relocates this clause's prescription as follows:

  • 14.503-215.105-2 (prescriptive text also revised)
  • 15.20915.110 (prescriptive text also revised)
  • Alternate I: 15.20915.110 (prescriptive text also revised)
  • Alternate II: 15.20915.110 (prescriptive text also revised)
  • 215.209215.110 (prescriptive text also revised)
  • Alternate I: 215.209215.110 (prescriptive text also revised)

See the deviation memorandum for the current prescription authority.

View deviation: 2026-O0048 →

R-DFARS Prescription Source

This clause is prescribed in the R-DFARS by the following deviation:

  • 2026-O0048 — DFARS RFO Implementation (Part 15) (DFARS Part 215)
    Add clause 52.215-1
15.209(a)
(a) The contracting officer shall insert the provision at 52.215-1, Instructions to Offerors-Competitive Acquisition, in all competitive solicitations where the Government intends to award a contract without discussions.

(1) If the Government intends to make award after discussions with offerors within the competitive range, the contracting officer shall use the basic provision with its Alternate I.

(2) If the Government would be willing to accept alternate proposals, the contracting officer shall alter the basic clause to add a new paragraph (c)(9) substantially the same as Alternate II.

DFARS Supplementary Guidance

215.209
(a) For source selections when the procurement is $100 million or more, contracting officers should use the provision at FAR 52.215-1, Instructions to Offerors--Competitive Acquisition, with its Alternate I.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC. Cross-references within the prescription are not resolved automatically.

Regulatory Stack

The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.

RFO RFO Version Overhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.

Search on acquisition.gov

R-DFARS R-DFARS Prescription Per Deviation 2026-O0048 (DFARS Part 215)
2026-O0048: DFARS RFO Implementation (Part 15) — DFARS Part 215

View Deviation 2026-O0048 →

FAR FAR Prescription ⚠ May be superseded by RFO 15.209(a)
(a) The contracting officer shall insert the provision at 52.215-1, Instructions to Offerors-Competitive Acquisition, in all competitive solicitations where the Government intends to award a contract without discussions.

(1) If the Government intends to make award after discussions with offerors within the competitive range, the contracting officer shall use the basic provision with its Alternate I.

(2) If the Government would be willing to accept alternate proposals, the contracting officer shall alter the basic clause to add a new paragraph (c)(9) substantially the same as Alternate II.

View on acquisition.gov · View on eCFR.gov

DFARS DFARS Supplement (eCFR) ⚠ May be superseded by RFO 215.209
(a) For source selections when the procurement is $100 million or more, contracting officers should use the provision at FAR 52.215-1, Instructions to Offerors--Competitive Acquisition, with its Alternate I.

Search on acquisition.gov · View on eCFR.gov

Version History

Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.

3 versions tracked from 2017-01-01 to 2021-12-06.
DEC 2021 December 6, 2021 CURRENT
Removed in this version
Added in this version
Unchanged
NOV 2021 (previous)
DEC 2021 (current)
2 added, 2 removed
(v)
(v) For acquisitions of commercial items, the make and model of the item to be delivered by the successful offeror.
(v)
(v) For acquisitions of commercial products, the make and model of the product to be delivered by the successful offeror.
4 added, 12 removed
(1)
(1) Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed - in whole or in part - for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of - or in connection with - the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction.
(1)
(1) Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed—in whole or in part—for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of—or in connection with—the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction.
NOV 2021 November 4, 2021 SUBSTANTIVE
Removed in this version
Added in this version
Unchanged
JAN 2017 (previous)
NOV 2021 (current)
1 removed
(8)
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more contract line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(8)
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
JAN 2017 January 1, 2017 SUBSTANTIVE
Earliest version available from the eCFR

RFO Version

Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).

Clause Text

Substantive changes. The RFO version differs materially from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.215-1 Instructions to Offerors-Competitive Acquisition.
eCFR (codified)
RFO (implemented)
1 added, 1 removed
As prescribed in 15.209(a), insert the following provision:
As prescribed in 15.110(a), insert the following provision:
3 added, 3 removed
Instructions to Offerors—Competitive Acquisition (NOV 2021)
Instructions to Offerors-Competitive Acquisition (Deviation Date)
28 removed
Discussions are negotiations that occur after establishment of the competitive range that may, at the Contracting Officer's discretion, result in the offeror being allowed to revise its proposal.
3 added, 1 removed
Proposal modification is a change made to a proposal before the solicitation's closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
Proposal modification is a change made to a proposal before the request for proposal closing date and time, or made in response to an amendment, or made to correct a mistake at any time before award.
7 added, 2 removed
Proposal revision is a change to a proposal made after the solicitation closing date, at the request of or as allowed by a Contracting Officer as the result of negotiations.
Proposal revision is a change to material elements of a proposal made after the request for proposal closing date, at the request of or as allowed by a Contracting Officer, as the result of negotiations.
8 added, 3 removed
(b)
(b) Amendments to solicitations. If this solicitation is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this solicitation by the date and time specified in the amendment(s).
(b)
(b) Amendments to requests for proposals. If this request for proposal (RFP) is amended, all terms and conditions that are not amended remain unchanged. Offerors shall acknowledge receipt of any amendment to this RFP by the date and time specified in the amendment(s).
86 removed
(c)
(c) Submission, modification, revision, and withdrawal of proposals. (1) Unless other methods (e.g., electronic commerce or facsimile) are permitted in the solicitation, proposals and modifications to proposals shall be submitted in paper media in sealed envelopes or packages (i) addressed to the office specified in the solicitation, and (ii) showing the time and date specified for receipt, the solicitation number, and the name and address of the offeror. Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i) and (c)(1)(ii) of this provision.
(c)
(c) Submission, modification, revision, and withdrawal of proposals.
1 added
(1)
(1)
(1)
8 added
(i)
(i)
(i) Proposals and modifications to proposals shall be—
12 added
(A)
(A)
(A) Submitted using the method and the format specified in the RFP;
10 added
(B)
(B)
(B) Addressed to the office specified in the RFP; and
20 added
(C)
(C)
(C) Showing the time and date specified for receipt, the RFP number, and the name and address of the offeror.
27 added
(ii)
(ii)
(ii) Offerors using commercial carriers should ensure that the proposal is marked on the outermost wrapper with the information in paragraphs (c)(1)(i)(B) and (C) of this provision.
1 added, 1 removed
(i)
(i) The solicitation number;
(i)
(i) The RFP number;
1 added, 3 removed
(ii)
(ii) The name, address, and telephone and facsimile numbers of the offeror (and electronic address if available);
(ii)
(ii) The name, address, and telephone number of the offeror (and electronic address if available);
1 added, 1 removed
(iii)
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the solicitation and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
(iii)
(iii) A statement specifying the extent of agreement with all terms, conditions, and provisions included in the RFP and agreement to furnish any or all items upon which prices are offered at the price set opposite each item;
3 added, 5 removed
(iv)
(iv) Names, titles, and telephone and facsimile numbers (and electronic addresses if available) of persons authorized to negotiate on the offeror's behalf with the Government in connection with this solicitation; and
(iv)
(iv) Names, titles, and telephone number (and electronic addresses if available) of persons authorized to negotiate on the offeror’s behalf with the Government in connection with this RFP; and
68 removed
(3)
(3) Submission, modification, revision, and withdrawal of proposals. (i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the solicitation by the time specified in the solicitation. If no time is specified in the solicitation, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
(3)
(3)
46 added, 40 removed
(ii)(A)
(ii)(A) Any proposal, modification, or revision, received at the Government office designated in the solicitation after the exact time specified for receipt of offers is "late" and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and—
(ii)(A)
(i) Offerors are responsible for submitting proposals, and any modifications or revisions, so as to reach the Government office designated in the RFP by the time specified in the RFP. If no time is specified in the RFP, the time for receipt is 4:30 p.m., local time, for the designated Government office on the date that proposal or revision is due.
1 added, 45 removed
(ii)
(1) If it was transmitted through an electronic commerce method authorized by the solicitation, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
(ii)
(ii)
55 added
(A)
(A)
(A) Any proposal, modification, or revision received at the Government office designated in the RFP after the exact time specified for receipt of offers is "late" and will not be considered unless it is received before award is made, the Contracting Officer determines that accepting the late offer would not unduly delay the acquisition; and-
45 added
(1)
(1)
(1) If it was transmitted through an electronic commerce method authorized by the RFP, it was received at the initial point of entry to the Government infrastructure not later than 5:00 p.m. one working day prior to the date specified for receipt of proposals; or
3 added, 3 removed
(iv)
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the solicitation, and urgent Government requirements preclude amendment of the solicitation, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the solicitation on the first work day on which normal Government processes resume.
(iv)
(iv) If an emergency or unanticipated event interrupts normal Government processes so that proposals cannot be received at the office designated for receipt of proposals by the exact time specified in the RFP, and urgent Government requirements preclude amendment of the RFP, the time specified for receipt of proposals will be deemed to be extended to the same time of day specified in the RFP on the first work day on which normal Government processes resume.
1 added, 31 removed
(v)
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral solicitations may be withdrawn orally. If the solicitation authorizes facsimile proposals, proposals may be withdrawn via facsimile received at any time before award, subject to the conditions specified in the provision at 52.215-5, Facsimile Proposals. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
(v)
(v) Proposals may be withdrawn by written notice received at any time before award. Oral proposals in response to oral RFPs may be withdrawn orally. Proposals may be withdrawn in person by an offeror or an authorized representative, if the identity of the person requesting withdrawal is established and the person signs a receipt for the proposal before award.
1 added, 1 removed
(4)
(4) Unless otherwise specified in the solicitation, the offeror may propose to provide any item or combination of items.
(4)
(4) Unless otherwise specified in the RFP, the offeror may propose to provide any item or combination of items.
3 added, 3 removed
(5)
(5) Offerors shall submit proposals in response to this solicitation in English, unless otherwise permitted by the solicitation, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the solicitation.
(5)
(5) Offerors shall submit proposals in response to this RFP in English, unless otherwise permitted by the RFP, and in U.S. dollars, unless the provision at FAR 52.225-17, Evaluation of Foreign Currency Offers, is included in the RFP.
1 added, 1 removed
(6)
(6) Offerors may submit modifications to their proposals at any time before the solicitation closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
(6)
(6) Offerors may submit modifications to their proposals at any time before the RFP closing date and time, and may submit modifications in response to an amendment, or to correct a mistake at any time before award.
2 added, 2 removed
(d)
(d) Offer expiration date. Proposals in response to this solicitation will be valid for the number of days specified on the solicitation cover sheet (unless a different period is proposed by the offeror).
(d)
(d) Offer expiration date. Proposals in response to this RFP will be valid for the number of days specified on the RFP cover sheet (unless a different period is proposed by the offeror).
115 removed
(1)
(1) Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed—in whole or in part—for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of—or in connection with—the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
(1)
(1) Mark the title page with the following legend:
113 added, 23 removed
(2)
(2) Mark each sheet of data it wishes to restrict with the following legend: Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
(2)
Mark the title page with the following legend: This proposal includes data that shall not be disclosed outside the Government and shall not be duplicated, used, or disclosed—in whole or in part—for any purpose other than to evaluate this proposal. If, however, a contract is awarded to this offeror as a result of, or in connection with, the submission of this data, the Government shall have the right to duplicate, use, or disclose the data to the extent provided in the resulting contract. This restriction does not limit the Government's right to use information contained in this data if it is obtained from another source without restriction. The data subject to this restriction are contained in sheets [insert numbers or other identification of sheets]; and
11 added, 36 removed
(f)
(f) Contract award. (1) The Government intends to award a contract or contracts resulting from this solicitation to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the solicitation.
(f)
(2) Mark each sheet of data it wishes to restrict with the following legend:
21 added
Use or disclosure of data contained on this sheet is subject to the restriction on the title page of this proposal.
3 added
(f)
(f)
(f) Contract award.
36 added
(1)
(1)
(1) The Government intends to award a contract or contracts resulting from this RFP to the responsible offeror(s) whose proposal(s) represents the best value after evaluation in accordance with the factors and subfactors in the RFP.
4 added, 4 removed
(4)
(4) The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint. The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
(4)
(4) The Government intends to evaluate proposals and award a contract without negotiations with offerors (except clarifications as described in FAR 15.202(b)). Therefore, the offeror's initial proposal should contain the offeror's best terms from a cost or price and technical standpoint. The Government reserves the right to conduct negotiations if the Contracting Officer later determines them to be necessary. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly evaluated proposals.
72 added, 12 removed
(7)
(7) Exchanges with offerors after receipt of a proposal do not constitute a rejection or counteroffer by the Government.
(7)
(7) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
19 added, 74 removed
(8)
(8) The Government may determine that a proposal is unacceptable if the prices proposed are materially unbalanced between line items or subline items. Unbalanced pricing exists when, despite an acceptable total evaluated price, the price of one or more line items is significantly overstated or understated as indicated by the application of cost or price analysis techniques. A proposal may be rejected if the Contracting Officer determines that the lack of balance poses an unacceptable risk to the Government.
(8)
(8) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
32 added, 21 removed
(9)
(9) If a cost realism analysis is performed, cost realism may be considered by the source selection authority in evaluating performance or schedule risk.
(9)
(9) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
14 added, 30 removed
(10)
(10) A written award or acceptance of proposal mailed or otherwise furnished to the successful offeror within the time specified in the proposal shall result in a binding contract without further action by either party.
(10)
(10) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
13 added, 17 removed
(11)
(11) If a post-award debriefing is given to requesting offerors, the Government shall disclose the following information, if applicable:
(11)
(i) The agency's evaluation of the significant weaknesses or deficiencies in the debriefed offeror's offer.
16 removed
(i)
(i) The agency's evaluation of the significant weak or deficient factors in the debriefed offeror's offer.
(i)
1 added, 1 removed
(vi)
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the solicitation, applicable regulations, and other applicable authorities were followed by the agency.
(vi)
(vi) Reasonable responses to relevant questions posed by the debriefed offeror as to whether source-selection procedures set forth in the RFP, applicable regulations, and other applicable authorities were followed by the agency.
58 added
(vii)
(vii)
(vii) For DoD contracts in excess of $10 million but not in excess of $100 million with a small business or nontraditional defense contractor (10 U.S.C. 3014), an option for the contractor to request disclosure of the agency's written source selection decision document, redacted to protect the confidential and proprietary information of other offerors for the contract award.
36 added
(viii)
(viii)
(viii) For award of a DoD contract in excess of $100 million, disclosure of the agency's written source selection decision document, redacted to protect the confidential and proprietary information of other offerors for the contract award.
3 added, 5 removed
Alternate I (OCT 1997). As prescribed in 15.209(a)(1), substitute the following paragraph (f)(4) for paragraph (f)(4) of the basic provision:
Alternate I–DEVIATION (Date). As prescribed in 15.110(a)(1), substitute the following paragraph (f)(4) for paragraph (f)(4) of the provision:
1 added, 1 removed
(f)(4)
(f)(4) The Government intends to evaluate proposals and award a contract after conducting discussions with offerors whose proposals have been determined to be within the competitive range. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals. Therefore, the offeror's initial proposal should contain the offeror's best terms from a price and technical standpoint.
(f)(4)
(f)(4) The Government intends to evaluate proposals and award a contract after conducting negotiations with offerors whose proposals have been determined to be within the competitive range. If the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals. Therefore, the offeror's initial proposal should contain the offeror's best terms from a price and technical standpoint.
3 added, 4 removed
Alternate II (OCT 1997). As prescribed in 15.209(a)(2), add a paragraph (c)(9) substantially the same as the following to the basic clause:
Alternate II–DEVIATION (Date). As prescribed in 15.110(a)(2), add a paragraph (c)(9) substantially the same as the following to the basic clause:
3 added, 3 removed
(9)
(9) Offerors may submit proposals that depart from stated requirements. Such proposals shall clearly identify why the acceptance of the proposal would be advantageous to the Government. Any deviations from the terms and conditions of the solicitation, as well as the comparative advantage to the Government, shall be clearly identified and explicitly defined. The Government reserves the right to amend the solicitation to allow all offerors an opportunity to submit revised proposals based on the revised requirements.
(9)
(c)(9) Offerors may submit proposals that depart from stated requirements. Such proposals shall clearly identify why the acceptance of the proposal would be advantageous to the Government. Any deviations from the terms and conditions of the RFP, as well as the comparative advantage to the Government, shall be clearly identified and explicitly defined. The Government reserves the right to amend the RFP to allow all offerors an opportunity to submit revised proposals based on the revised requirements.
46 removed
[62 FR 51259, Sept. 30, 1997; 64 FR 51841, Sept. 24, 1999, as amended at 64 FR 72433, 72451, Dec. 27, 1999; 66 FR 2135, Jan. 10, 2001; 68 FR 69258, Dec. 11, 2003; 82 FR 4715, Jan. 13, 2017; 86 FR 61034, Nov. 4, 2021]
Applied to DoD contracts via Class Deviation 2026-O0048 (effective 2026-03-16) .

Prescription

Substantive changes. The RFO prescription differs materially from the eCFR prescription.
eCFR (codified)
RFO (implemented)
Unchanged
52.215-1 Instructions to Offerors-Competitive Acquisition.: Prescription
eCFR (codified)
RFO (implemented)
40 added, 20 removed
(a)
(a) The contracting officer shall insert the provision at 52.215-1, Instructions to Offerors-Competitive Acquisition, in all competitive solicitations where the Government intends to award a contract without discussions.
(a)
Competitive RFPs must advise offerors whether the Government intends to evaluate proposals and award a contract with or without conducting negotiations with offerors whose proposals have been determined to be within the competitive range. FAR provision 52.215-1, Instructions to Offerors-Competitive Acquisition, and its Alternate I, contain this disclosure.
28 removed
(1)
(1) If the Government intends to make award after discussions with offerors within the competitive range, the contracting officer shall use the basic provision with its Alternate I.
(1)
31 removed
(2)
(2) If the Government would be willing to accept alternate proposals, the contracting officer shall alter the basic clause to add a new paragraph (c)(9) substantially the same as Alternate II.
(2)

Source: acquisition.gov RFO Part 52 · Prescribing Part 15

Active Class Deviations

DFARS RFO Implementation (Part 15) Add clause 52.215-1
MODIFIED

Related Clauses

References

52.215-5 52.225-17
Use with AI assistant
Copy a link and prompt for use with Gemini or another AI assistant.