FAR Clause

52.216-20

Definite Quantity.
View on acquisition.gov · View on eCFR.gov
Effective Date
OCT 1995
Active Deviations
Versions
1 (since 2017-01-01)
RFO
RFO Version Available

The Revolutionary FAR Overhaul has published a revised version of this clause. The RFO version supersedes the eCFR text below for contracts using the RFO model; see the RFO deviation for applicability.

View RFO version
52.216-20 Definite Quantity.

As prescribed in 16.506(c), insert the following clause:

Definite Quantity (OCT 1995)

(a) This is a definite-quantity, indefinite-delivery contract for the supplies or services specified, and effective for the period stated, in the Schedule.

(b) The Government shall order the quantity of supplies or services specified in the Schedule, and the Contractor shall furnish them when ordered. Delivery or performance shall be at locations designated in orders issued in accordance with the Ordering clause and the Schedule.

(c) Except for any limitations on quantities in the Order Limitations clause or in the Schedule, there is no limit on the number of orders that may be issued. The Government may issue orders requiring delivery to multiple destinations or performance at multiple locations.

(d) Any order issued during the effective period of this contract and not completed within that time shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor's and Government's rights and obligations with respect to that order to the same extent as if the order were completed during the contract's effective period;
provided,
that the Contractor shall not be required to make any deliveries under this contract after __ [
insert date
].

(End of clause)

[48 FR 42478, Sept. 19, 1983, as amended at 60 FR 49727, Sept. 26, 1995]
16.506(c)
(c) Insert the clause at 52.216-20, Definite Quantity, in solicitations and contracts when a definite-quantity contract is contemplated.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC. Cross-references within the prescription are not resolved automatically.

Regulatory Stack

The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.

RFO RFO Version Overhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.

Search on acquisition.gov

FAR FAR Prescription 16.506(c)
(c) Insert the clause at 52.216-20, Definite Quantity, in solicitations and contracts when a definite-quantity contract is contemplated.

View on acquisition.gov · View on eCFR.gov

Version History

Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.

No version history available from eCFR.

RFO Version

Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).

Clause Text

Substantive changes. The RFO version differs materially from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.216-20 Definite Quantity.
eCFR (codified)
RFO (implemented)
1 added, 1 removed
As prescribed in 16.506(c), insert the following clause:
As prescribed in 16.505(c), insert the following clause:
5 added, 5 removed
(d)
(d) Any order issued during the effective period of this contract and not completed within that time shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor's and Government's rights and obligations with respect to that order to the same extent as if the order were completed during the contract's effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after __ [insert date].
(d)
(d) Any order issued during the ordering period of this contract and not completed within that time shall be completed by the Contractor within the time specified in the order. The contract shall govern the Contractor’s and Government’s rights and obligations with respect to that order to the same extent as if the order were completed during the contract’s effective period; provided, that the Contractor shall not be required to make any deliveries under this contract after ________________ [insert date].
15 removed
[48 FR 42478, Sept. 19, 1983, as amended at 60 FR 49727, Sept. 26, 1995]

Prescription

No substantive changes. The RFO prescription is identical to the eCFR prescription.

Source: acquisition.gov RFO Part 52 · Prescribing Part 16

Use with AI assistant
Copy a link and prompt for use with Gemini or another AI assistant.