The Revolutionary FAR Overhaul has published a revised version of this clause. The RFO version supersedes the eCFR text below for contracts using the RFO model; see the RFO deviation for applicability.
52.216-25 Contract Definitization.
As prescribed in 16.603-4(b)(3), insert the following clause:
Contract Definitization (OCT 2010)
(a) A ____
[insert specific type of contract]
definitive contract is contemplated. The Contractor agrees to begin promptly negotiating with the Contracting Officer the terms of a definitive contract that will include (1) all clauses required by the Federal Acquisition Regulation (FAR) on the date of execution of the letter contract, (2) all clauses required by law on the date of execution of the definitive contract, and (3) any other mutually agreeable clauses, terms, and conditions. The Contractor agrees to submit a ____
[insert specific type of proposal (e.g., fixed-price or cost-and-fee)]
proposal, including data other than certified cost or pricing data, and certified cost or pricing data, in accordance with FAR 15.408, Table 15-2, supporting its proposal.
(b) The schedule for definitizing this contract is [
insert target date for definitization of the contract and dates for submission of proposal, beginning of negotiations, and, if appropriate, submission of make-or-buy and subcontracting plans and certified cost or pricing data
]:
(c) If agreement on a definitive contract to supersede this letter contract is not reached by the target date in paragraph (b) above, or within any extension of it granted by the Contracting Officer, the Contracting Officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with subpart 15.4 and part 31 of the FAR, subject to Contractor appeal as provided in the Disputes clause. In any event, the Contractor shall proceed with completion of the contract, subject only to the Limitation of Government Liability clause.
(1) After the Contracting Officer's determination of price or fee, the contract shall be governed by—
(i) All clauses required by the FAR on the date of execution of this letter contract for either fixed-price or cost-reimbursement contracts, as determined by the Contracting Officer under this paragraph (c);
(ii) All clauses required by law as of the date of the Contracting Officer's determination; and
(iii) Any other clauses, terms, and conditions mutually agreed upon.
(2) To the extent consistent with subparagraph (c)(1) above, all clauses, terms, and conditions included in this letter contract shall continue in effect, except those that by their nature apply only to a letter contract.
(End of clause)
Alternate I
(APR 1984). In letter contracts awarded on the basis of price competition, add the following paragraph (d) to the basic clause:
(d) The definitive contract resulting from this letter contract will include a negotiated ___ [
insert price ceiling
or
firm fixed price
] in no event to exceed ___ [
insert the proposed price upon which the award was based
].
[48 FR 42478, Sept. 19, 1983, as amended at 60 FR 48221, Sept. 18, 1995; 62 FR 51271, Sept. 30, 1997; 75 FR 53152, Aug. 30, 2010]
RFO
Prescription superseded under the RFO
The prescription shown below is from the codified eCFR. Under the RFO, the prescribing section may have been revised, relocated or reserved. See the deviation memorandum for the current prescription authority.
This clause is prescribed in the R-DFARS by the following deviation:
2026-O0045
— DFARS RFO Implementation (Part 16)
(DFARS Part 216)
Add clause 52.216-25
16.603-4(b)
(b) In addition, the contracting officer shall insert the following clauses in solicitations and contracts when a letter contract is contemplated:
(1) The clause at 52.216-23, Execution and Commencement of Work, except that this clause may be omitted from letter contracts awarded on SF 26;
(2) The clause at 52.216-24, Limitation of Government Liability, with dollar amounts completed in a manner consistent with 16.603-2(d); and
(3) The clause at 52.216-25, Contract Definitization, with its paragraph (b) completed in a manner consistent with 16.603-2(c). If at the time of entering into the letter contract, the contracting officer knows that the definitive contract will be based on adequate price competition or will otherwise meet the criteria of 15.403-1 for not requiring submission of certified cost or pricing data, the words "and certified cost or pricing data in accordance with FAR 15.408, Table 15-1 supporting its proposal" may be deleted from paragraph (a) of the clause. If the letter contract is being awarded on the basis of price competition, the contracting officer shall use the clause with its Alternate I.
DFARS Supplementary Guidance
216.603-4
(b)(2) See 217.7405 (a) for additional guidance regarding use of the clause at FAR 52.216-24, Limitation of Government Liability. (3) Use the clause at 252.217-7027, Contract Definitization, in accordance with its prescription 217.7406 (b), instead of the clause at FAR 52.216-25, Contract Definitization.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC.
Cross-references within the prescription are not resolved automatically.
Regulatory Stack
The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.
RFORFO VersionOverhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.
FARFAR Prescription⚠ May be superseded by RFO16.603-4(b)
(b) In addition, the contracting officer shall insert the following clauses in solicitations and contracts when a letter contract is contemplated:
(1) The clause at 52.216-23, Execution and Commencement of Work, except that this clause may be omitted from letter contracts awarded on SF 26;
(2) The clause at 52.216-24, Limitation of Government Liability, with dollar amounts completed in a manner consistent with 16.603-2(d); and
(3) The clause at 52.216-25, Contract Definitization, with its paragraph (b) completed in a manner consistent with 16.603-2(c). If at the time of entering into the letter contract, the contracting officer knows that the definitive contract will be based on adequate price competition or will otherwise meet the criteria of 15.403-1 for not requiring submission of certified cost or pricing data, the words "and certified cost or pricing data in accordance with FAR 15.408, Table 15-1 supporting its proposal" may be deleted from paragraph (a) of the clause. If the letter contract is being awarded on the basis of price competition, the contracting officer shall use the clause with its Alternate I.
DFARSDFARS Supplement (eCFR)⚠ May be superseded by RFO216.603-4
(b)(2) See 217.7405 (a) for additional guidance regarding use of the clause at FAR 52.216-24, Limitation of Government Liability. (3) Use the clause at 252.217-7027, Contract Definitization, in accordance with its prescription 217.7406 (b), instead of the clause at FAR 52.216-25, Contract Definitization.
Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.
2 versions tracked from 2017-01-01 to 2018-01-24.
JAN 2018January 24, 2018CURRENT
Removed in this version
Added in this version
Unchanged
JAN 2017 (previous)
JAN 2018 (current)
(a)
(a) A ____ [insert specific type of contract] definitive contract is contemplated. The Contractor agrees to begin promptly negotiating with the Contracting Officer the terms of a definitive contract that will include (1) all clauses required by the Federal Acquisition Regulation (FAR) on the date of execution of the letter contract, (2) all clauses required by law on the date of execution of the definitive contract, and (3) any other mutually agreeable clauses, terms, and conditions. The Contractor agrees to submit a ____ [insert specific type of proposal (e.g., fixed-price or cost-and-fee)] proposal, including data other than certified cost or pricing data, and certified cost or pricing data, in accordance with FAR 15.408, Table 15-2, supporting its proposal.
(a)
(a) A ____ [insert specific type of contract] definitive contract is contemplated. The Contractor agrees to begin promptly negotiating with the Contracting Officer the terms of a definitive contract that will include (1) all clauses required by the Federal Acquisition Regulation (FAR) on the date of execution of the letter contract, (2) all clauses required by law on the date of execution of the definitive contract, and (3) any other mutually agreeable clauses, terms, and conditions. The Contractor agrees to submit a ____ [insert specific type of proposal (e.g., fixed-price or cost-and-fee)] proposal, including data other than certified cost or pricing data, and certified cost or pricing data, in accordance with FAR 15.408, Table 15-2, supporting its proposal.
(b)
(b) The schedule for definitizing this contract is [insert target date for definitization of the contract and dates for submission of proposal, beginning of negotiations, and, if appropriate, submission of make-or-buy and subcontracting plans and certified cost or pricing data]:
(b)
(b) The schedule for definitizing this contract is [insert target date for definitization of the contract and dates for submission of proposal, beginning of negotiations, and, if appropriate, submission of make-or-buy and subcontracting plans and certified cost or pricing data]:
(c)
(c) If agreement on a definitive contract to supersede this letter contract is not reached by the target date in paragraph (b) above, or within any extension of it granted by the Contracting Officer, the Contracting Officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with subpart 15.4 and part 31 of the FAR, subject to Contractor appeal as provided in the Disputes clause. In any event, the Contractor shall proceed with completion of the contract, subject only to the Limitation of Government Liability clause.
(c)
(c) If agreement on a definitive contract to supersede this letter contract is not reached by the target date in paragraph (b) above, or within any extension of it granted by the Contracting Officer, the Contracting Officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with subpart 15.4 and part 31 of the FAR, subject to Contractor appeal as provided in the Disputes clause. In any event, the Contractor shall proceed with completion of the contract, subject only to the Limitation of Government Liability clause.
(1)
(1) After the Contracting Officer's determination of price or fee, the contract shall be governed by -
(1)
(1) After the Contracting Officer's determination of price or fee, the contract shall be governed by—
(i)
(i) All clauses required by the FAR on the date of execution of this letter contract for either fixed-price or cost-reimbursement contracts, as determined by the Contracting Officer under this paragraph (c);
(i)
(i) All clauses required by the FAR on the date of execution of this letter contract for either fixed-price or cost-reimbursement contracts, as determined by the Contracting Officer under this paragraph (c);
(ii)
(ii) All clauses required by law as of the date of the Contracting Officer's determination; and
(ii)
(ii) All clauses required by law as of the date of the Contracting Officer's determination; and
(iii)
(iii) Any other clauses, terms, and conditions mutually agreed upon.
(iii)
(iii) Any other clauses, terms, and conditions mutually agreed upon.
(2)
(2) To the extent consistent with subparagraph (c)(1) above, all clauses, terms, and conditions included in this letter contract shall continue in effect, except those that by their nature apply only to a letter contract.
(End of clause)
Alternate I (APR 1984). In letter contracts awarded on the basis of price competition, add the following paragraph (d) to the basic clause:
(2)
(2) To the extent consistent with subparagraph (c)(1) above, all clauses, terms, and conditions included in this letter contract shall continue in effect, except those that by their nature apply only to a letter contract.
(End of clause)
Alternate I (APR 1984). In letter contracts awarded on the basis of price competition, add the following paragraph (d) to the basic clause:
2 added, 2 removed
(d)
(d) The definitive contract resulting from this letter contract will include a negotiated __ [insert price ceiling or firm fixed price] in no event to exceed __ [insert the proposed price upon which the award was based].
(d)
(d) The definitive contract resulting from this letter contract will include a negotiated ___ [insert price ceiling or firm fixed price] in no event to exceed ___ [insert the proposed price upon which the award was based].
JAN 2017January 1, 2017SUBSTANTIVE
Earliest version available from the eCFR
RFO Version
Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).
Clause Text
Substantive changes. The RFO version differs materially from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.216-25 Contract Definitization.
eCFR (codified)
RFO (implemented)
As prescribed in 16.603-4(b)(3), insert the following clause:
As prescribed in 16.603-4(b)(3) , insert the following clause:
2 added, 2 removed
Contract Definitization (OCT 2010)
Contract Definitization (Deviation date)
3 added, 3 removed
(a)
(a) A ____ [insert specific type of contract] definitive contract is contemplated. The Contractor agrees to begin promptly negotiating with the Contracting Officer the terms of a definitive contract that will include (1) all clauses required by the Federal Acquisition Regulation (FAR) on the date of execution of the letter contract, (2) all clauses required by law on the date of execution of the definitive contract, and (3) any other mutually agreeable clauses, terms, and conditions. The Contractor agrees to submit a ____ [insert specific type of proposal (e.g., fixed-price or cost-and-fee)] proposal, including data other than certified cost or pricing data, and certified cost or pricing data, in accordance with FAR 15.408, Table 15-2, supporting its proposal.
(a)
(a) A ______________ [insert specific type of contract] definitive contract is contemplated. The Contractor agrees to begin promptly negotiating with the Contracting Officer the terms of a definitive contract that will include (1) all clauses required by the Federal Acquisition Regulation (FAR) on the date of execution of the letter contract, (2) all clauses required by law on the date of execution of the definitive contract, and (3) any other mutually agreeable clauses, terms, and conditions. The Contractor agrees to submit a ______ [insert specific type of proposal (e.g., fixed-price or cost-and-fee)] proposal, including data other than certified cost or pricing data, and certified cost or pricing data, in accordance with FAR 15.408, Table 15-1, supporting its proposal.
2 added
(b)
(b) The schedule for definitizing this contract is [insert target date for definitization of the contract and dates for submission of proposal, beginning of negotiations, and, if appropriate, submission of make-or-buy and subcontracting plans and certified cost or pricing data]:
(b)
(b) The schedule for definitizing this contract is [insert target date for definitization of the contract and dates for submission of proposal, beginning of negotiations, and, if appropriate, submission of make-or-buy and subcontracting plans and certified cost or pricing data]: ___________________________________________________________________________________________ ___________________________________________________________________________________________
3 added, 1 removed
(c)
(c) If agreement on a definitive contract to supersede this letter contract is not reached by the target date in paragraph (b) above, or within any extension of it granted by the Contracting Officer, the Contracting Officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with subpart 15.4 and part 31 of the FAR, subject to Contractor appeal as provided in the Disputes clause. In any event, the Contractor shall proceed with completion of the contract, subject only to the Limitation of Government Liability clause.
(c)
(c) If agreement on a definitive contract to supersede this letter contract is not reached by the target date in paragraph (b) of this section, or within any extension of it granted by the Contracting Officer, the Contracting Officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with subpart 15.4 and part 31 of the FAR, subject to Contractor appeal as provided in the Disputes clause. In any event, the Contractor shall proceed with completion of the contract, subject only to the Limitation of Government Liability clause.
(1)
(1) After the Contracting Officer's determination of price or fee, the contract shall be governed by—
(1)
(1) After the Contracting Officer’s determination of price or fee, the contract shall be governed by-
(i)
(i) All clauses required by the FAR on the date of execution of this letter contract for either fixed-price or cost-reimbursement contracts, as determined by the Contracting Officer under this paragraph (c);
(i)
(i) All clauses required by the FAR on the date of execution of this letter contract for either fixed-price or cost-reimbursement contracts, as determined by the Contracting Officer under this paragraph (c);
(ii)
(ii) All clauses required by law as of the date of the Contracting Officer's determination; and
(ii)
(ii) All clauses required by law as of the date of the Contracting Officer’s determination; and
(iii)
(iii) Any other clauses, terms, and conditions mutually agreed upon.
(iii)
(iii) Any other clauses, terms, and conditions mutually agreed upon.
4 added, 2 removed
(2)
(2) To the extent consistent with subparagraph (c)(1) above, all clauses, terms, and conditions included in this letter contract shall continue in effect, except those that by their nature apply only to a letter contract.
(2)
(2) To the extent consistent with paragraph (c)(1) of this section, all clauses, terms, and conditions included in this letter contract shall continue in effect, except those that by their nature apply only to a letter contract.
(End of clause)
(End of clause)
3 added, 9 removed
Alternate I (APR 1984). In letter contracts awarded on the basis of price competition, add the following paragraph (d) to the basic clause:
Alternate I (Apr 1984). As prescribed in 16.603-4(b)(3), add the following paragraph (d) to the basic clause:
6 added, 6 removed
(d)
(d) The definitive contract resulting from this letter contract will include a negotiated ___ [insert price ceiling or firm fixed price] in no event to exceed ___ [insert the proposed price upon which the award was based].
(d)
(d) The definitive contract resulting from this letter contract will include a negotiated _____________ [insert "price ceiling" or "firm fixed price"] in no event to exceed ___________________ [insert the proposed price upon which the award was based].
27 removed
[48 FR 42478, Sept. 19, 1983, as amended at 60 FR 48221, Sept. 18, 1995; 62 FR 51271, Sept. 30, 1997; 75 FR 53152, Aug. 30, 2010]
Substantive changes. The RFO prescription differs materially from the eCFR prescription.
eCFR (codified)
RFO (implemented)
Unchanged
52.216-25 Contract Definitization.: Prescription
eCFR (codified)
RFO (implemented)
201 added, 16 removed
(b)
(b) In addition, the contracting officer shall insert the following clauses in solicitations and contracts when a letter contract is contemplated:
(b)
(c) Each letter contract must, as required by the clause at 52.216-25, Contract Definitization, contain a negotiated definitization schedule including (1) dates for submission of the contractor's price proposal, required certified cost or pricing data and data other than certified cost or pricing data; and, if required, make-or-buy and subcontracting plans, (2) a date for the start of negotiations, and (3) a target date for definitization, which must be the earliest practicable date for definitization. The schedule will provide for definitization of the contract within 180 days after the date of the letter contract or before completion of 40 percent of the work to be performed, whichever occurs first. However, the contracting officer may, in extreme cases and according to agency procedures, authorize an additional period. If, after exhausting all reasonable efforts, the contracting officer and the contractor cannot negotiate a definitive contract because of failure to reach agreement as to price or fee, the clause at 52.216-25 requires the contractor to proceed with the work and provides that the contracting officer may, with the approval of the head of the contracting activity, determine a reasonable price or fee in accordance with subpart 15.4 and part 31, subject to appeal as provided in the Disputes clause.
24 removed
(1)
(1) The clause at 52.216-23, Execution and Commencement of Work, except that this clause may be omitted from letter contracts awarded on SF 26;
(1)
20 removed
(2)
(2) The clause at 52.216-24, Limitation of Government Liability, with dollar amounts completed in a manner consistent with 16.603-2(d); and
(2)
112 removed
(3)
(3) The clause at 52.216-25, Contract Definitization, with its paragraph (b) completed in a manner consistent with 16.603-2(c). If at the time of entering into the letter contract, the contracting officer knows that the definitive contract will be based on adequate price competition or will otherwise meet the criteria of 15.403-1 for not requiring submission of certified cost or pricing data, the words "and certified cost or pricing data in accordance with FAR 15.408, Table 15-1 supporting its proposal" may be deleted from paragraph (a) of the clause. If the letter contract is being awarded on the basis of price competition, the contracting officer shall use the clause with its Alternate I.