View RFO version52.222-30 Construction Wage Rate Requirements—Price Adjustment (None or Separately Specified Method). As prescribed in 22.407(e), insert the following clause: Construction Wage Rate Requirements—Price Adjustment (None or Separately Specified Method) (AUG 2018) (a) The wage determination issued under the Construction Wage Rate Requirements statute by the Administrator, Wage and Hour Division, U.S. Department of Labor, that is effective for an option to extend the term of the contract, will apply to that option period. (b) The Contracting Officer will make no adjustment in contract price, other than provided for elsewhere in this contract, to cover any increases or decreases in wages and benefits as a result of— (1) Incorporation of the Department of Labor's wage determination applicable at the exercise of the option to extend the term of the contract; (2) Incorporation of a wage determination otherwise applied to the contract by operation of law; or (3) An increase in wages and benefits resulting from any other requirement applicable to workers subject to the Construction Wage Rate Requirements statute. (End of clause) [66 FR 53482, Oct. 22, 2001, as amended at 79 FR 24218, Apr. 29, 2014; 83 FR 42575, Aug. 22, 2018]
22.407(e)
(1) A fixed-price contract subject to the Construction Wage Rate Requirements statute that will contain option provisions by which the contracting officer may extend the term of the contract, and the contracting officer determines the most appropriate contract price adjustment method is the method at 22.404-12(c)(1) or (2); or
(2) A cost-reimbursable type contract subject to the Construction Wage Rate Requirements statute that will contain option provisions by which the contracting officer may extend the term of the contract.
Regulatory Stack
The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.
RFO
RFO Version
Overhauled clause text
FAR
FAR Prescription
22.407(e)
(1) A fixed-price contract subject to the Construction Wage Rate Requirements statute that will contain option provisions by which the contracting officer may extend the term of the contract, and the contracting officer determines the most appropriate contract price adjustment method is the method at 22.404-12(c)(1) or (2); or
(2) A cost-reimbursable type contract subject to the Construction Wage Rate Requirements statute that will contain option provisions by which the contracting officer may extend the term of the contract.
Version History
Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.
RFO Version
Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).