52.226-5

Restrictions on Subcontracting Outside Disaster or Emergency Area.
View on acquisition.gov · View on eCFR.gov
Effective Date
NOV 2007
Active Deviations
Versions
1 (since 2017-01-01)
RFO
RFO Version Available

The Revolutionary FAR Overhaul has published a revised version of this clause. The RFO version supersedes the eCFR text below for contracts using the RFO model; see the RFO deviation for applicability.

View RFO version
52.226-5 Restrictions on Subcontracting Outside Disaster or Emergency Area.

As prescribed in 26.206(c), insert the following clause:

Restrictions on Subcontracting Outside Disaster or Emergency Area (NOV 2007)

(a)
Definitions.
The definitions of the following terms used in this clause are found in the Small Business Administration regulations at 13 CFR 125.6(e): cost of the contract, cost of contract performance incurred for personnel, cost of manufacturing, cost of materials, personnel, and subcontracting.

(b) The Contractor agrees that in performance of the contract in the case of a contract for—

(1)
Services (except construction).
At least 50 percent of the cost of contract performance incurred for personnel shall be expended for employees of the Contractor or employees of other businesses residing or primarily doing business in the clause at FAR 52.226—4, Notice of Disaster or Emergency Area Set-Aside;

(2)
Supplies (other than procurement from a nonmanufacturer of such supplies).
The Contractor or employees of other businesses residing or primarily doing business in the set-aside area shall perform work for at least 50 percent of the cost of manufacturing the supplies, not including the cost of materials;

(3)
General construction.
The Contractor will perform at least 15 percent of the cost of the contract, not including the cost of materials, with its own employees or employees of other businesses residing or primarily doing business in the set-aside area; or

(4)
Construction by special trade Contractors.
The Contractor will perform at least 25 percent of the cost of the contract, not including the cost of materials, with its own employees or employees of other businesses residing or primarily doing business in the set-aside area.

(End of clause)

[72 FR 63088, Nov. 7, 2007, as amended at 74 FR 52849, Oct. 14, 2009]
26.206(c)
(c) The contracting officer shall insert the clause at 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area, in all solicitations and contracts that involve local area set-asides.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC. Cross-references within the prescription are not resolved automatically.

Regulatory Stack

The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.

RFO RFO Version Overhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.

Search on acquisition.gov

FAR FAR Prescription 26.206(c)
(c) The contracting officer shall insert the clause at 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area, in all solicitations and contracts that involve local area set-asides.

View on acquisition.gov · View on eCFR.gov

Version History

Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.

No version history available from eCFR.

RFO Version

Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).

Clause Text

Substantive changes. The RFO version differs materially from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.226-5 Restrictions on Subcontracting Outside Disaster or Emergency Area.
eCFR (codified)
RFO (implemented)
1 added, 1 removed
As prescribed in 26.206(c), insert the following clause:
As prescribed in 26.202-3(c), insert the following clause:
2 added, 2 removed
Restrictions on Subcontracting Outside Disaster or Emergency Area (NOV 2007)
Restrictions on Subcontracting Outside Disaster or Emergency Area (DEVIATION DATE)
4 added
(1)
(1) Services (except construction). At least 50 percent of the cost of contract performance incurred for personnel shall be expended for employees of the Contractor or employees of other businesses residing or primarily doing business in the clause at FAR 52.226—4, Notice of Disaster or Emergency Area Set-Aside;
(1)
(1) Services (except construction). At least 50 percent of the cost of contract performance incurred for personnel shall be expended for employees of the Contractor or employees of other businesses residing or primarily doing business in the area designated in the clause at FAR 52.226—4, Notice of Disaster or Emergency Area Set-Aside;
15 removed
[72 FR 63088, Nov. 7, 2007, as amended at 74 FR 52849, Oct. 14, 2009]

Prescription

Substantive changes. The RFO prescription differs materially from the eCFR prescription.
eCFR (codified)
RFO (implemented)
Unchanged
52.226-5 Restrictions on Subcontracting Outside Disaster or Emergency Area.: Prescription
eCFR (codified)
RFO (implemented)
1 added, 7 removed
(c)
(c) The contracting officer shall insert the clause at 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area, in all solicitations and contracts that involve local area set-asides.
(c)
(c) Insert the clause at 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area, in solicitations and contracts involving local area set-asides.

Source: acquisition.gov RFO Part 52 · Prescribing Part 26

Related Clauses

Referenced by

52.212-5

References

52.226-4
Use with AI assistant
Copy a link and prompt for use with Gemini or another AI assistant.