FAR Clause ACTIVE

52.232-13

Notice of Progress Payments.
View on acquisition.gov · View on eCFR.gov
Effective Date
APR 1984
Active Deviations
1
Versions
1 (since 2017-01-01)
RFO
RFO Version Available

The Revolutionary FAR Overhaul has published a revised version of this clause. The RFO version supersedes the eCFR text below for contracts using the RFO model; see the RFO deviation for applicability.

View RFO version
DEV
This clause is modified by 1 active class deviation
  • 2026-O0022 — DFARS RFO Implementation (Part 32)
    Substitute clause 52.232-13
View per-deviation details →
52.232-13 Notice of Progress Payments.

As prescribed in 32.502-3(a), insert the following provision in invitations for bids and requests for proposals that include a Progress Payments clause:

Notice of Progress Payments (APR 1984)

The need for customary progress payments conforming to the regulations in subpart 32.5 of the Federal Acquisition Regulation (FAR) will not be considered as a handicap or adverse factor in the award of the contract. The Progress Payments clause included in this solicitation will be included in any resulting contract, modified or altered if necessary in accordance with subsection 52.232-16 and its
Alternate I
of the FAR. Even though the clause is included in the contract, the clause shall be inoperative during any time the contractor's accounting system and controls are determined by the Government to be inadequate for segregation and accumulation of contract costs.

(End of provision)
RFO
Prescription superseded under the RFO

The prescription shown below is from the codified eCFR. Under the RFO, the prescribing section may have been revised, relocated or reserved. See the deviation memorandum for the current prescription authority.

View deviation: 2026-O0022 →
32.502-3(a)
(a) The contracting officer shall insert the provision at 52.232-13, Notice of Progress Payments, in invitations for bids and requests for proposals that include a Progress Payments clause.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC. Cross-references within the prescription are not resolved automatically.

Regulatory Stack

The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.

RFO RFO Version Overhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.

Search on acquisition.gov

R-DFARS R-DFARS Prescription Per Deviation 2026-O0022 (DFARS Part 232)
2026-O0022: DFARS RFO Implementation (Part 32) — DFARS Part 232

View Deviation 2026-O0022 →

FAR FAR Prescription ⚠ May be superseded by RFO 32.502-3(a)
(a) The contracting officer shall insert the provision at 52.232-13, Notice of Progress Payments, in invitations for bids and requests for proposals that include a Progress Payments clause.

View on acquisition.gov · View on eCFR.gov

Version History

Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.

No version history available from eCFR.

RFO Version

Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).

Clause Text

Substantive changes. The RFO version differs materially from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.232-13 Notice of Progress Payments.
eCFR (codified)
RFO (implemented)
1 added, 15 removed
As prescribed in 32.502-3(a), insert the following provision in invitations for bids and requests for proposals that include a Progress Payments clause:
As prescribed in 32.502-3(a), insert the following provision:
Applied to DoD contracts via Class Deviation 2026-O0022 (effective 2026-02-01) .

Prescription

Substantive changes. The RFO prescription differs materially from the eCFR prescription.
eCFR (codified)
RFO (implemented)
Unchanged
52.232-13 Notice of Progress Payments.: Prescription
eCFR (codified)
RFO (implemented)
4 removed
(a)
(a) The contracting officer shall insert the provision at 52.232-13, Notice of Progress Payments, in invitations for bids and requests for proposals that include a Progress Payments clause.
(a)
(a) Insert the provision at 52.232-13, Notice of Progress Payments, in invitations for bids and requests for proposals that include a Progress Payments clause.

Source: acquisition.gov RFO Part 52 · Prescribing Part 32

Active Class Deviations

DFARS RFO Implementation (Part 32) Substitute clause 52.232-13
MODIFIED

Related Clauses

References

52.232-16
Use with AI assistant
Copy a link and prompt for use with Gemini or another AI assistant.