52.232-33

Payment by Electronic Funds Transfer—System for Award Management.
View on acquisition.gov · View on eCFR.gov
Effective Date
OCT 2018
Active Deviations
1
Versions
3 (since 2018-09-26)
RFO
RFO Version Available

The Revolutionary FAR Overhaul has published a revised version of this clause. The RFO version supersedes the eCFR text below for contracts using the RFO model; see the RFO deviation for applicability.

View RFO version
DEV
This clause is modified by 1 active class deviation
  • 2026-O0022 — DFARS RFO Implementation (Part 32)
View per-deviation details →
52.232-33 Payment by Electronic Funds Transfer—System for Award Management.

As prescribed in 32.1110(a)(1), insert the following clause:

Payment by Electronic Funds Transfer—System for Award Management (OCT 2018)

(a)
Method of payment.
(1) All payments by the Government under this contract shall be made by electronic funds transfer (EFT), except as provided in paragraph (a)(2) of this clause. As used in this clause, the term "EFT" refers to the funds transfer and may also include the payment information transfer.

(2) In the event the Government is unable to release one or more payments by EFT, the Contractor agrees to either—

(i) Accept payment by check or some other mutually agreeable method of payment; or

(ii) Request the Government to extend the payment due date until such time as the Government can make payment by EFT (but see paragraph (d) of this clause).

(b)
Contractor's EFT information.
The Government shall make payment to the Contractor using the EFT information contained in the System for Award Management (SAM). In the event that the EFT information changes, the Contractor shall be responsible for providing the updated information to SAM.

(c)
Mechanisms for EFT payment.
The Government may make payment by EFT through either the Automated Clearing House (ACH) network, subject to the rules of the National Automated Clearing House Association, or the Fedwire Transfer System. The rules governing Federal payments through the ACH are contained in 31 CFR part 210.

(d)
Suspension of payment.
If the Contractor's EFT information in SAM is incorrect, then the Government need not make payment to the Contractor under this contract until correct EFT information is entered into SAM; and any invoice or contract financing request shall be deemed not to be a proper invoice for the purpose of prompt payment under this contract. The prompt payment terms of the contract regarding notice of an improper invoice and delays in accrual of interest penalties apply.

(e)
Liability for uncompleted or erroneous transfers.
(1) If an uncompleted or erroneous transfer occurs because the Government used the Contractor's EFT information incorrectly, the Government remains responsible for—

(i) Making a correct payment;

(ii) Paying any prompt payment penalty due; and

(iii) Recovering any erroneously directed funds.

(2) If an uncompleted or erroneous transfer occurs because the Contractor's EFT information was incorrect, or was revised within 30 days of Government release of the EFT payment transaction instruction to the Federal Reserve System, and—

(i) If the funds are no longer under the control of the payment office, the Government is deemed to have made payment and the Contractor is responsible for recovery of any erroneously directed funds; or

(ii) If the funds remain under the control of the payment office, the Government shall not make payment, and the provisions of paragraph (d) of this clause shall apply.

(f)
EFT and prompt payment.
A payment shall be deemed to have been made in a timely manner in accordance with the prompt payment terms of this contract if, in the EFT payment transaction instruction released to the Federal Reserve System, the date specified for settlement of the payment is on or before the prompt payment due date, provided the specified payment date is a valid date under the rules of the Federal Reserve System.

(g)
EFT and assignment of claims.
If the Contractor assigns the proceeds of this contract as provided for in the assignment of claims terms of this contract, the Contractor shall require as a condition of any such assignment, that the assignee shall register separately in SAM and shall be paid by EFT in accordance with the terms of this clause. Notwithstanding any other requirement of this contract, payment to an ultimate recipient other than the Contractor, or a financial institution properly recognized under an assignment of claims pursuant to subpart 32.8, is not permitted. In all respects, the requirements of this clause shall apply to the assignee as if it were the Contractor. EFT information that shows the ultimate recipient of the transfer to be other than the Contractor, in the absence of a proper assignment of claims acceptable to the Government, is incorrect EFT information within the meaning of paragraph (d) of this clause.

(h)
Liability for change of EFT information by financial agent.
The Government is not liable for errors resulting from changes to EFT information made by the Contractor's financial agent.

(i)
Payment information.
The payment or disbursing office shall forward to the Contractor available payment information that is suitable for transmission as of the date of release of the EFT instruction to the Federal Reserve System. The Government may request the Contractor to designate a desired format and method(s) for delivery of payment information from a list of formats and methods the payment office is capable of executing. However, the Government does not guarantee that any particular format or method of delivery is available at any particular payment office and retains the latitude to use the format and delivery method most convenient to the Government. If the Government makes payment by check in accordance with paragraph (a) of this clause, the Government shall mail the payment information to the remittance address contained in SAM.

(End of clause)

[64 FR 10542, Mar. 4, 1999, as amended at 68 FR 56675, Oct. 1, 2003; 78 FR 37683, June 21, 2013; 83 FR 48700, Sept. 26, 2018]
RFO
Prescription superseded under the RFO

The prescription shown below is from the codified eCFR. Under the RFO, the prescribing section may have been revised, relocated or reserved. See the deviation memorandum for the current prescription authority.

View deviation: 2026-O0022 →
32.1110(a)
(a) The contracting officer shall insert the clause at-

(1) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management, in solicitations and contracts that include the provision at 52.204-7 System for Award Management, or an agency clause that requires a contractor to be registered in SAM and maintain registration until final payment, unless-

(i) Payment will be made through a third party arrangement (see 13.301 and paragraph (d) of this section); or

(ii) An exception listed in 32.1103(a) through (i) applies.

(2)
(i) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management, in solicitations and contracts that require EFT as the method for payment but do not include the provision at 52.204-7, System for Award Management, or a similar agency clause that requires the contractor to be registered in the SAM.

(ii) (A) If permitted by agency procedures, the contracting officer may insert in paragraph (b)(1) of the clause, a particular time after award, such as a fixed number of days, or event such as the submission of the first request for payment.

(B) If no agency procedures are prescribed, the time period inserted in paragraph (b)(1) of the clause shall be "no later than 15 days prior to submission of the first request for payment."

DFARS Supplementary Guidance

232.1110
Use the clause at 252.232-7009 , Mandatory Payment by Governmentwide Commercial Purchase Card, in solicitations, contracts, and agreements, including solicitations, contracts, and agreements using FAR part 12 procedures for the acquisition of commercial products and commercial services, when--
(1) Placement of orders or calls valued at or below the micro-purchase threshold is anticipated; and
(2) Payment by Governmentwide commercial purchase card is required for orders or calls valued at or below the micro-purchase threshold under the contract or agreement.
Prescription data sourced from eCFR as of 2026-06-10 20:31 UTC. Cross-references within the prescription are not resolved automatically.

Regulatory Stack

The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.

RFO RFO Version Overhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.

Search on acquisition.gov

R-DFARS R-DFARS Prescription Per Deviation 2026-O0022 (DFARS Part 232)
2026-O0022: DFARS RFO Implementation (Part 32) — DFARS Part 232

View Deviation 2026-O0022 →

FAR FAR Prescription ⚠ May be superseded by RFO 32.1110(a)
(a) The contracting officer shall insert the clause at-

(1) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management, in solicitations and contracts that include the provision at 52.204-7 System for Award Management, or an agency clause that requires a contractor to be registered in SAM and maintain registration until final payment, unless-

(i) Payment will be made through a third party arrangement (see 13.301 and paragraph (d) of this section); or

(ii) An exception listed in 32.1103(a) through (i) applies.

(2)
(i) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management, in solicitations and contracts that require EFT as the method for payment but do not include the provision at 52.204-7, System for Award Management, or a similar agency clause that requires the contractor to be registered in the SAM.

(ii) (A) If permitted by agency procedures, the contracting officer may insert in paragraph (b)(1) of the clause, a particular time after award, such as a fixed number of days, or event such as the submission of the first request for payment.

(B) If no agency procedures are prescribed, the time period inserted in paragraph (b)(1) of the clause shall be "no later than 15 days prior to submission of the first request for payment."

View on acquisition.gov · View on eCFR.gov

DFARS DFARS Supplement (eCFR) ⚠ May be superseded by RFO 232.1110
Use the clause at 252.232-7009 , Mandatory Payment by Governmentwide Commercial Purchase Card, in solicitations, contracts, and agreements, including solicitations, contracts, and agreements using FAR part 12 procedures for the acquisition of commercial products and commercial services, when--
(1) Placement of orders or calls valued at or below the micro-purchase threshold is anticipated; and
(2) Payment by Governmentwide commercial purchase card is required for orders or calls valued at or below the micro-purchase threshold under the contract or agreement.

Search on acquisition.gov · View on eCFR.gov

Version History

Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.

3 versions tracked from 2018-09-26 to 2019-05-06.
MAY 2019 May 6, 2019 CURRENT
OCT 2018 October 26, 2018 SUBSTANTIVE
Removed in this version
Added in this version
Unchanged
SEP 2018 (previous)
OCT 2018 (current)
1 added, 3 removed
(i)
However, the Government does not guarantee that any particular format or method of delivery is available at any particular payment office and retains the latitude to use the format and delivery method most convenient to the Government. If the Government makes payment by check in accordance with paragraph (a) of this clause, the Government shall mail the payment information to the remittance address contained in the SAM database. (End of clause)
(i)
However, the Government does not guarantee that any particular format or method of delivery is available at any particular payment office and retains the latitude to use the format and delivery method most convenient to the Government. If the Government makes payment by check in accordance with paragraph (a) of this clause, the Government shall mail the payment information to the remittance address contained in SAM. (End of clause)
2 added, 5 removed
(b)
(b) Contractor's EFT information. The Government shall make payment to the Contractor using the EFT information contained in the System for Award Management (SAM) database. In the event that the EFT information changes, the Contractor shall be responsible for providing the updated information to the SAM database.
(b)
(b) Contractor's EFT information. The Government shall make payment to the Contractor using the EFT information contained in the System for Award Management (SAM). In the event that the EFT information changes, the Contractor shall be responsible for providing the updated information to SAM.
1 added, 5 removed
(d)
(d) Suspension of payment. If the Contractor's EFT information in the SAM database is incorrect, then the Government need not make payment to the Contractor under this contract until correct EFT information is entered into the SAM database; and any invoice or contract financing request shall be deemed not to be a proper invoice for the purpose of prompt payment under this contract. The prompt payment terms of the contract regarding notice of an improper invoice and delays in accrual of interest penalties apply.
(d)
(d) Suspension of payment. If the Contractor's EFT information in SAM is incorrect, then the Government need not make payment to the Contractor under this contract until correct EFT information is entered into SAM; and any invoice or contract financing request shall be deemed not to be a proper invoice for the purpose of prompt payment under this contract. The prompt payment terms of the contract regarding notice of an improper invoice and delays in accrual of interest penalties apply.
2 removed
(g)
(g) EFT and assignment of claims. If the Contractor assigns the proceeds of this contract as provided for in the assignment of claims terms of this contract, the Contractor shall require as a condition of any such assignment, that the assignee shall register separately in the SAM database and shall be paid by EFT in accordance with the terms of this clause. Notwithstanding any other requirement of this contract, payment to an ultimate recipient other than the Contractor, or a financial institution properly recognized under an assignment of claims pursuant to subpart 32.8, is not permitted.
(g)
(g) EFT and assignment of claims. If the Contractor assigns the proceeds of this contract as provided for in the assignment of claims terms of this contract, the Contractor shall require as a condition of any such assignment, that the assignee shall register separately in SAM and shall be paid by EFT in accordance with the terms of this clause. Notwithstanding any other requirement of this contract, payment to an ultimate recipient other than the Contractor, or a financial institution properly recognized under an assignment of claims pursuant to subpart 32.8, is not permitted.
SEP 2018 September 26, 2018 SUBSTANTIVE
Earliest version available from the eCFR

RFO Version

Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).

Clause Text

Minor revisions. The RFO version has formatting or editorial changes from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.232-33 Payment by Electronic Funds Transfer-System for Award Management.
eCFR (codified)
RFO (implemented)
47 removed
(a)
(a) Method of payment. (1) All payments by the Government under this contract shall be made by electronic funds transfer (EFT), except as provided in paragraph (a)(2) of this clause. As used in this clause, the term "EFT" refers to the funds transfer and may also include the payment information transfer.
(a)
(a) Method of payment.
47 added
(1)
(1)
(1) All payments by the Government under this contract shall be made by electronic funds transfer (EFT), except as provided in paragraph (a)(2) of this clause. As used in this clause, the term "EFT" refers to the funds transfer and may also include the payment information transfer.
22 removed
(e)
(e) Liability for uncompleted or erroneous transfers. (1) If an uncompleted or erroneous transfer occurs because the Government used the Contractor's EFT information incorrectly, the Government remains responsible for—
(e)
(e) Liability for uncompleted or erroneous transfers.
22 added
(1)
(1)
(1) If an uncompleted or erroneous transfer occurs because the Government used the Contractor’s EFT information incorrectly, the Government remains responsible for-
2 added, 1 removed
(f)
(f) EFT and prompt payment. A payment shall be deemed to have been made in a timely manner in accordance with the prompt payment terms of this contract if, in the EFT payment transaction instruction released to the Federal Reserve System, the date specified for settlement of the payment is on or before the prompt payment due date, provided the specified payment date is a valid date under the rules of the Federal Reserve System.
(f)
(f) EFT and prompt paymen t. A payment shall be deemed to have been made in a timely manner in accordance with the prompt payment terms of this contract if, in the EFT payment transaction instruction released to the Federal Reserve System, the date specified for settlement of the payment is on or before the prompt payment due date, provided the specified payment date is a valid date under the rules of the Federal Reserve System.
27 removed
[64 FR 10542, Mar. 4, 1999, as amended at 68 FR 56675, Oct. 1, 2003; 78 FR 37683, June 21, 2013; 83 FR 48700, Sept. 26, 2018]
Applied to DoD contracts via Class Deviation 2026-O0022 (effective 2026-02-01) .

Prescription

Substantive changes. The RFO prescription differs materially from the eCFR prescription.
eCFR (codified)
RFO (implemented)
Unchanged
52.232-33 Payment by Electronic Funds Transfer-System for Award Management.: Prescription
eCFR (codified)
RFO (implemented)
74 added, 6 removed
(a)
(a) The contracting officer shall insert the clause at-
(a)
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the contractor must have submitted correct EFT banking information in accordance with the applicable solicitation provision (e.g., 52.232-38, Submission of Electronic Funds Transfer Information with Offer), contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—System for Award Management, or 52.232-34, Payment by Electronic Funds Transfer—Other Than System for Award Management), or applicable agency procedures.
44 removed
(1)
(1) 52.232-33, Payment by Electronic Funds Transfer-System for Award Management, in solicitations and contracts that include the provision at 52.204-7 System for Award Management, or an agency clause that requires a contractor to be registered in SAM and maintain registration until final payment, unless-
(1)
19 removed
(i)
(i) Payment will be made through a third party arrangement (see 13.301 and paragraph (d) of this section); or
(i)
9 removed
(ii)
(ii) An exception listed in 32.1103(a) through (i) applies.
(ii)
52 removed
(2)
(2) (i) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award Management, in solicitations and contracts that require EFT as the method for payment but do not include the provision at 52.204-7, System for Award Management, or a similar agency clause that requires the contractor to be registered in the SAM.
(2)
42 removed
(ii)
(ii) (A) If permitted by agency procedures, the contracting officer may insert in paragraph (b)(1) of the clause, a particular time after award, such as a fixed number of days, or event such as the submission of the first request for payment.
(ii)
33 removed
(B)
(B) If no agency procedures are prescribed, the time period inserted in paragraph (b)(1) of the clause shall be "no later than 15 days prior to submission of the first request for payment."
(B)

Source: acquisition.gov RFO Part 52 · Prescribing Part 32

Active Class Deviations

DFARS RFO Implementation (Part 32) Modify clause 52.232-33
MODIFIED

Related Clauses

Referenced by

52.212-4 52.212-5 52.213-4 52.232-25 52.232-26 52.232-27
Use with AI assistant
Copy a link and prompt for use with Gemini or another AI assistant.