A community resource for the acquisition workforce
—not a .gov website
Community-maintained
part52.dev is built and maintained by members of the federal acquisition community to help with navigating DoD acquisition regulation.
Not affiliated with the U.S. Government
This site is not operated, endorsed or sanctioned by the U.S. Government. Data is sourced from public regulatory sources including eCFR.gov and acquisition.gov. Always verify against official sources.
The Revolutionary FAR Overhaul has published a revised version of this clause. The RFO version supersedes the eCFR text below for contracts using the RFO model; see the RFO deviation for applicability.
52.236-11 Use and Possession Prior to Completion.
As prescribed in 36.511, insert the following clause:
Use and Possession Prior to Completion (APR 1984)
(a) The Government shall have the right to take possession of or use any completed or partially completed part of the work. Before taking possession of or using any work, the Contracting Officer shall furnish the Contractor a list of items of work remaining to be performed or corrected on those portions of the work that the Government intends to take possession of or use. However, failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract. The Government's possession or use shall not be deemed an acceptance of any work under the contract.
(b) While the Government has such possession or use, the Contractor shall be relieved of the responsibility for the loss of or damage to the work resulting from the Government's possession or use, notwithstanding the terms of the clause in this contract entitled
Permits and Responsibilities.
If prior possession or use by the Government delays the progress of the work or causes additional expense to the Contractor, an equitable adjustment shall be made in the contract price or the time of completion, and the contract shall be modified in writing accordingly.
(End of clause)
[48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34761, July 3, 1995]
36.511
The contracting officer shall insert the clause at 52.236-11, Use and Possession Prior to Completion, in solicitations and contracts when a fixed-price construction contract is contemplated and the contract award amount is expected to exceed the simplified acquisition threshold. This clause may be inserted in solicitations and contracts when the contract amount is expected to be at or below the simplified acquisition threshold.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC.
Cross-references within the prescription are not resolved automatically.
Regulatory Stack
The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.
RFORFO VersionOverhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.
The contracting officer shall insert the clause at 52.236-11, Use and Possession Prior to Completion, in solicitations and contracts when a fixed-price construction contract is contemplated and the contract award amount is expected to exceed the simplified acquisition threshold. This clause may be inserted in solicitations and contracts when the contract amount is expected to be at or below the simplified acquisition threshold.
Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.
No version history available from eCFR.
RFO Version
Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).
Clause Text
Substantive changes. The RFO version differs materially from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.236-11 Use and Possession Prior to Completion.
eCFR (codified)
RFO (implemented)
1 added, 1 removed
As prescribed in 36.511, insert the following clause:
As prescribed in 36.101-7(d), insert the following clause:
2 added, 2 removed
Use and Possession Prior to Completion (APR 1984)
Use and Possession Prior to Completion (Deviation Date)
1 added, 89 removed
(a)
(a) The Government shall have the right to take possession of or use any completed or partially completed part of the work. Before taking possession of or using any work, the Contracting Officer shall furnish the Contractor a list of items of work remaining to be performed or corrected on those portions of the work that the Government intends to take possession of or use. However, failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract. The Government's possession or use shall not be deemed an acceptance of any work under the contract.
(a)
(a) The Government has the right to take possession of or use any completed or partially completed part of the work.
35 added, 82 removed
(b)
(b) While the Government has such possession or use, the Contractor shall be relieved of the responsibility for the loss of or damage to the work resulting from the Government's possession or use, notwithstanding the terms of the clause in this contract entitled Permits and Responsibilities. If prior possession or use by the Government delays the progress of the work or causes additional expense to the Contractor, an equitable adjustment shall be made in the contract price or the time of completion, and the contract shall be modified in writing accordingly.
(b)
(1) Before taking possession of or using any work, the Contracting Officer will furnish the Contractor a list of items of work remaining to be performed or corrected on those portions of the work that the Government intends to take possession of or use.
27 added
(2)
(2)
(2) Failure of the Contracting Officer to list any item of work shall not relieve the Contractor of responsibility for complying with the terms of the contract.
18 added
(3)
(3)
(3) The Government's possession or use shall not be deemed an acceptance of any work under the contract.
1 added
(b)
(b)
(b)
45 added
(1)
(1)
(1) While the Government has such possession or use, the Contractor is relieved of the responsibility for the loss of or damage to the work resulting from the Government’s possession or use, notwithstanding the terms of the clause in this contract entitled “Permits and Responsibilities”.
46 added
(2)
(2)
(2) If prior possession or use by the Government delays the progress of the work or causes additional expense to the Contractor, an equitable adjustment shall be made in the contract price or the time of completion, and the contract shall be modified in writing accordingly.
(End of clause)
(End of clause)
15 removed
[48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34761, July 3, 1995]
Prescription
Substantive changes. The RFO prescription differs materially from the eCFR prescription.
eCFR (codified)
RFO (implemented)
Unchanged
52.236-11 Use and Possession Prior to Completion.: Prescription
eCFR (codified)
RFO (implemented)
3 added, 26 removed
(1)
The contracting officer shall insert the clause at 52.236-11, Use and Possession Prior to Completion, in solicitations and contracts when a fixed-price construction contract is contemplated and the contract award amount is expected to exceed the simplified acquisition threshold. This clause may be inserted in solicitations and contracts when the contract amount is expected to be at or below the simplified acquisition threshold.
(1)
(1) The contracting officer must insert the clause at 52.236-11, Use and Possession Prior to Completion, in solicitations and contracts when a fixed-price construction contract is contemplated, and the contract award amount is expected to exceed the simplified acquisition threshold.