FAR Clause

52.242-1

Notice of Intent To Disallow Costs.
View on acquisition.gov · View on eCFR.gov
Effective Date
APR 1984
Active Deviations
Versions
1 (since 2017-01-01)
RFO
RFO Version Available

The Revolutionary FAR Overhaul has published a revised version of this clause. The RFO version supersedes the eCFR text below for contracts using the RFO model; see the RFO deviation for applicability.

View RFO version
52.242-1 Notice of Intent To Disallow Costs.

As prescribed in 42.802, insert the following clause in solicitations and contracts when a cost-reimbursement contract, a fixed-price incentive contract, or a contract providing for price redetermination is contemplated:

Notice of Intent To Disallow Costs (APR 1984)

(a) Notwithstanding any other clause of this contract—

(1) The Contracting Officer may at any time issue to the Contractor a written notice of intent to disallow specified costs incurred or planned for incurrence under this contract that have been determined not to be allowable under the contract terms; and

(2) The Contractor may, after receiving a notice under subparagraph (1) above, submit a written response to the Contracting Officer, with justification for allowance of the costs. If the Contractor does respond within 60 days, the Contracting Officer shall, within 60 days of receiving the response, either make a written withdrawal of the notice or issue a written decision.

(b) Failure to issue a notice under this Notice of Intent to Disallow Costs clause shall not affect the Government's rights to take exception to incurred costs.

(End of clause)
42.802
The contracting officer shall insert the clause at 52.242-1, Notice of Intent to Disallow Costs, in solicitations and contracts when a cost-reimbursement contract, a fixed-price incentive contract, or a contract providing for price redetermination is contemplated.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC. Cross-references within the prescription are not resolved automatically.

Regulatory Stack

The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.

RFO RFO Version Overhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.

Search on acquisition.gov

FAR FAR Prescription 42.802
The contracting officer shall insert the clause at 52.242-1, Notice of Intent to Disallow Costs, in solicitations and contracts when a cost-reimbursement contract, a fixed-price incentive contract, or a contract providing for price redetermination is contemplated.

View on acquisition.gov · View on eCFR.gov

Version History

Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.

No version history available from eCFR.

RFO Version

Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).

Clause Text

Substantive changes. The RFO version differs materially from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.242-1 Notice of Intent to Disallow Costs.
eCFR (codified)
RFO (implemented)
2 added, 23 removed
As prescribed in 42.802, insert the following clause in solicitations and contracts when a cost-reimbursement contract, a fixed-price incentive contract, or a contract providing for price redetermination is contemplated:
As prescribed in 42.602, insert the following clause:
6 added, 4 removed
(2)
(2) The Contractor may, after receiving a notice under subparagraph (1) above, submit a written response to the Contracting Officer, with justification for allowance of the costs. If the Contractor does respond within 60 days, the Contracting Officer shall, within 60 days of receiving the response, either make a written withdrawal of the notice or issue a written decision.
(2)
(2) The Contractor may, after receiving a notice under paragraph (a)(1) of this clause, submit a written response to the Contracting Officer, with justification for allowance of the costs. If the Contractor does respond within 60 days, the Contracting Officer will, within 60 days of receiving the response, either make a written withdrawal of the notice or issue a written decision.
2 added, 2 removed
(b)
(b) Failure to issue a notice under this Notice of Intent to Disallow Costs clause shall not affect the Government's rights to take exception to incurred costs.
(b)
(b) Failure to issue a notice under this Notice of Intent to Disallow Costs clause does not affect the Government’s rights to take exception to incurred costs.

Prescription

Minor revisions. The RFO prescription has formatting or editorial changes from the eCFR prescription.
eCFR (codified)
RFO (implemented)
Unchanged
52.242-1 Notice of Intent to Disallow Costs.: Prescription
eCFR (codified)
RFO (implemented)
1 added, 1 removed
The contracting officer shall insert the clause at 52.242-1, Notice of Intent to Disallow Costs, in solicitations and contracts when a cost-reimbursement contract, a fixed-price incentive contract, or a contract providing for price redetermination is contemplated.
The contracting officer must insert the clause at 52.242-1, Notice of Intent to Disallow Costs, in solicitations and contracts when a cost-reimbursement contract, a fixed-price incentive contract, or a contract providing for price redetermination is contemplated.

Source: acquisition.gov RFO Part 52 · Prescribing Part 42