A community resource for the acquisition workforce
—not a .gov website
Community-maintained
part52.dev is built and maintained by members of the federal acquisition community to help with navigating DoD acquisition regulation.
Not affiliated with the U.S. Government
This site is not operated, endorsed or sanctioned by the U.S. Government. Data is sourced from public regulatory sources including eCFR.gov and acquisition.gov. Always verify against official sources.
The Revolutionary FAR Overhaul has published a revised version of this clause. The RFO version supersedes the eCFR text below for contracts using the RFO model; see the RFO deviation for applicability.
52.243-6 Change Order Accounting.
As prescribed in 43.205(f), the contracting officer may insert a clause, substantially the same as follows:
Change Order Accounting (APR 1984)
The Contracting Officer may require change order accounting whenever the estimated cost of a change or series of related changes exceeds $100,000. The Contractor, for each change or series of related changes, shall maintain separate accounts, by job order or other suitable accounting procedure, of all incurred segregable, direct costs (less allocable credits) of work, both changed and not changed, allocable to the change. The Contractor shall maintain such accounts until the parties agree to an equitable adjustment for the changes ordered by the Contracting Officer or the matter is conclusively disposed of in accordance with the Disputes clause.
(End of clause)
[48 FR 42478, Sept. 19, 1983, as amended at 54 FR 29297, July 11, 1989; 56 FR 15156, Apr. 15, 1991]
43.205(f)
(f) The contracting officer may insert a clause, substantially the same as the clause at 52.243-6, Change Order Accounting, in solicitations and contracts for supply and research and development contracts of significant technical complexity, if numerous changes are anticipated. The clause may be included in solicitations and contracts for construction if deemed appropriate by the contracting officer.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC.
Cross-references within the prescription are not resolved automatically.
Regulatory Stack
The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.
RFORFO VersionOverhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.
(f) The contracting officer may insert a clause, substantially the same as the clause at 52.243-6, Change Order Accounting, in solicitations and contracts for supply and research and development contracts of significant technical complexity, if numerous changes are anticipated. The clause may be included in solicitations and contracts for construction if deemed appropriate by the contracting officer.
Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.
No version history available from eCFR.
RFO Version
Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).
Clause Text
Substantive changes. The RFO version differs materially from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.243-6 Change Order Accounting.
eCFR (codified)
RFO (implemented)
1 added, 1 removed
As prescribed in 43.205(f), the contracting officer may insert a clause, substantially the same as follows:
As prescribed in 43.305(f), the contracting officer may insert a clause, substantially the same as follows:
2 added, 2 removed
Change Order Accounting (APR 1984)
Change Order Accounting (Deviation Date)
1 added, 1 removed
The Contracting Officer may require change order accounting whenever the estimated cost of a change or series of related changes exceeds $100,000. The Contractor, for each change or series of related changes, shall maintain separate accounts, by job order or other suitable accounting procedure, of all incurred segregable, direct costs (less allocable credits) of work, both changed and not changed, allocable to the change. The Contractor shall maintain such accounts until the parties agree to an equitable adjustment for the changes ordered by the Contracting Officer or the matter is conclusively disposed of in accordance with the Disputes clause.
The Contracting Officer may require change order accounting whenever the estimated cost of a change or series of related changes exceeds $100,000. The Contractor, for each change or series of related changes, shall maintain separate accounts, by job order or other suitable accounting procedure, of all incurred segregable, direct costs (less allocable credits) of work, both changed and not changed, allocable to the change. The Contractor shall maintain the accounts until the parties agree to an equitable adjustment for the changes ordered by the Contracting Officer or the matter is conclusively disposed of in accordance with the Disputes clause.
(End of clause)
(End of clause)
21 removed
[48 FR 42478, Sept. 19, 1983, as amended at 54 FR 29297, July 11, 1989; 56 FR 15156, Apr. 15, 1991]
Prescription
Substantive changes. The RFO prescription differs materially from the eCFR prescription.
eCFR (codified)
RFO (implemented)
Unchanged
52.243-6 Change Order Accounting.: Prescription
eCFR (codified)
RFO (implemented)
17 added, 52 removed
(f)
(f) The contracting officer may insert a clause, substantially the same as the clause at 52.243-6, Change Order Accounting, in solicitations and contracts for supply and research and development contracts of significant technical complexity, if numerous changes are anticipated. The clause may be included in solicitations and contracts for construction if deemed appropriate by the contracting officer.
(f)
The following categories of direct costs normally are segregable and accountable under the terms of the Change Order Accounting clause at 52.243-6: