This clause was rescinded effective March 18, 2026 by Contract Policy Memo 26-C-13. Do not include this clause in new solicitations or contracts. Essential requirements previously covered by this clause should be included in the Statement of Work or Performance Work Statement.

For current DAF acquisition guidance, refer to the DAF Contracting Compass.

(a) See the Price Negotiation Memorandum (PNM) Checklist that may be used to ensure PNMs contain all required information. For contract actions valued below the Truthful Cost or Pricing Data threshold, the DAF Streamlined PNM Format for supplies or services is available for use. If the value of the contract action exceeds the Truthful Cost or Pricing Data threshold and no exception to the Truthful Cost or Pricing Data threshold applies, pricing documentation is expected to address the cost element composition of the proposed, objective, and negotiated positions at an appropriate level of detail based on the value and complexity of the pricing action. The final PNM template and streamlined PNM templates for supplies or services may be tailored for use.

Prescription data is being collected. Check back after the next data refresh.

Regulatory Stack

No supplementary regulatory layers found for this clause.

Version History

Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.

No version history available from eCFR.

Use with AI assistant
Copy a link and prompt for use with Gemini or another AI assistant.