(b) Authorization. For commercial interim payments and commercial advance payments authorized by FAR 32.202-1(b) that does not require OUSD(A&S)/DPCAP approval of an individual or class deviation from FAR Part 32 requirements (see DFARS 201.402(1)(vi)), the contracting officer shall submit all commercial interim payment requests and commercial advance payment requests through the SCO to local FM for review and approval. Prior to submitting to the local FM for approval, the SCO must determine the package is adequate, complete, and justified. The request must include the following: a determination that the applicable circumstances outlined in FAR 32.202-1(b) have been met to include the contracting officer’s determination in accordance with FAR 32.202-1(b)(3) and preliminary payment office concurrence with liquidation provisions per FAR
32.202-1(b)(8) when required by FAR 32.206(e), legal review, J&A (if applicable), background paper such as a Milestone Payment Plan that outlines the reason(s) for the request, and the proposed payment schedule. Submit a copy of the approved package to the cognizant HCA Workflow.
(d) Unusual contract financing. See
5332.114 Unusual Contract Financing.
.
Unusual contract financing arrangements must be approved by DPCAP.
Change History
| Date | Authority | Type | Summary |
|---|---|---|---|
| 2026-03-20 | CLAUSE_MODIFIED | Modified: (b) updated | |
View diff--- 2026-03-20 10:27:43
+++ 2026-03-20 13:16:18
@@ -1,4 +1,4 @@
-(b) Authorization. For commercial interim payments and commercial advance payments authorized by FAR 32.202-1(b) that does not require OUSD(A&S)/DPCAP approval of an individual or class deviation from FAR Part 32 requirements (see DFARS 201.402(1)(vi)), the contracting officer shall submit all commercial interim payment requests and commercial advance payment requests through the SCO to local FM for review and approval. Prior to submitting to the local FM for approval, the SCO must determine the package is adequate, complete, and justified. The request must include the following: a determination that the applicable circumstances outlined in FAR 32.202-1(b) have been met to include the contracting officer's determination in accordance with FAR 32.202-1(b)(3) and preliminary payment office concurrence with liquidation provisions per FAR
+(b) Authorization. For commercial interim payments and commercial advance payments authorized by FAR 32.202-1(b) that does not require OUSD(A&S)/DPCAP approval of an individual or class deviation from FAR Part 32 requirements (see DFARS 201.402(1)(vi)), the contracting officer shall submit all commercial interim payment requests and commercial advance payment requests through the SCO to local FM for review and approval. Prior to submitting to the local FM for approval, the SCO must determine the package is adequate, complete, and justified. The request must include the following: a determination that the applicable circumstances outlined in FAR 32.202-1(b) have been met to include the contracting officer’s determination in accordance with FAR 32.202-1(b)(3) and preliminary payment office concurrence with liquidation provisions per FAR
32.202-1(b)(8) when required by FAR 32.206(e), legal review, J&A (if applicable), background paper such as a Milestone Payment Plan that outlines the reason(s) for the request, and the proposed payment schedule. Submit a copy of the approved package to the cognizant HCA Workflow.
(d) Unusual contract financing. See
5332.114 Unusual Contract Financing.
|
|||
Prescription data is being collected. Check back after the next data refresh.
Regulatory Stack
No supplementary regulatory layers found for this clause.
Version History
Version history data is being collected.
Active Class Deviations
No active class deviations affect this clause.
Use with AI assistant
Copy a link and prompt for use with Gemini or another AI assistant.