52.232-15 Progress Payments Not Included.
Revolutionary FAR Overhaul (RFO) Version
A revised version of this clause has been published under the Revolutionary FAR Overhaul (EO 14275). The RFO version supersedes the eCFR text below for contracts using the RFO FAR model. The RFO text is not duplicated here; see the clause page for a side-by-side comparison: https://part52.dev/clause/52-232-15/#rfo
Prescription and Applicability
FAR Prescription, 32.502-3(c)
(c) The contracting officer shall insert the provision at 52.232-15, Progress Payments Not Included, in invitations for bids if the solicitation will not contain one of the provisions prescribed in paragraphs (a) and (b) of this section.
Current Text
52.232-15 Progress Payments Not Included.
As prescribed in 32.502-3(c), insert the following provision in invitations for bids if the solicitation will not contain one of the provisions prescribed in 32.502-3 (a) and (b):
Progress Payments Not Included (APR 1984)
A progress payments clause is not included in this solicitation, and will not be added to the resulting contract at the time of award. Bids conditioned upon inclusion of a progress payment clause in the resulting contract will be rejected as nonresponsive.
(End of provision)
Suggested Questions
You can ask your AI assistant:
- Should I include this provision in my solicitation?
- Does this clause apply to commercial acquisitions?
- Does this clause apply to R&D contracts under Part 35?
- Which alternate should I use for a multiple-award contract?
- Are there any active Class Deviations that modify this clause?
- What changed in the most recent amendment?