The contracting officer shall insert the clause at 52.236-6, Superintendence by the Contractor, in solicitations and contracts when a fixed-price construction contract or a fixed-price dismantling, demolition, or removal of improvements contract is contemplated and the contract amount is expected to exceed the simplified acquisition threshold. The contracting officer may insert the clause in solicitations and contracts when a fixed-price construction or a fixed-price contract for dismantling, demolition, or removal of improvements is contemplated and the contract amount is expected to be at or below the simplified acquisition threshold.
Current Text
52.236-6 Superintendence by the Contractor.
As prescribed in 36.506, insert the following clause:
Superintendence by the Contractor (APR 1984)
At all times during performance of this contract and until the work is completed and accepted, the Contractor shall directly superintend the work or assign and have on the work a competent superintendent who is satisfactory to the Contracting Officer and has authority to act for the Contractor.
(End of clause)
[48 FR 42478, Sept. 19, 1983, as amended at 60 FR 34761, July 3, 1995]
Suggested Questions
You can ask your AI assistant:
- Should I include this provision in my solicitation?
- Does this clause apply to commercial acquisitions?
- Does this clause apply to R&D contracts under Part 35?
- Which alternate should I use for a multiple-award contract?
- Are there any active Class Deviations that modify this clause?
- What changed in the most recent amendment?