52.246-18 Warranty of Supplies of a Complex Nature.
Prescription and Applicability
FAR Prescription, 46.710(b)
(b)
(1) The contracting officer may insert a clause substantially the same as the clause at 52.246-18, Warranty of Supplies of a Complex Nature, in solicitations and contracts for deliverable complex items when a fixed-price supply or research and development contract is contemplated and the use of a warranty clause has been approved under agency procedures. If the contractor's design rather than the Government's design will be used, insert the word "design" before "material" in paragraph (b)(1).
(2) If it is desirable to specify that necessary transportation incident to correction or replacement will be at the Government's expense (as might be the case if, for example, the cost of a warranty would otherwise be prohibitive), the contracting officer may use the clause with its Alternate II.
(3) If a fixed-price incentive contract is contemplated, the contracting officer may use the clause with its Alternate III.
(4) If it is anticipated that recovery of the warranted item will involve considerable Government expense for disassembly and/or reassembly of larger items, the contracting officer may use the clause with its Alternate IV.
DFARS Supplementary Guidance, 246.710
(1) Use a clause substantially the same as the basic or one of the alternates of the clause at 252.246-7001 , Warranty of Data, in solicitations and contracts that include the clause at 252.227-7013 , Rights in Technical Data and Computer Software, when there is a need for greater protection or period of liability than provided by the inspection and warranty clauses prescribed in FAR part 46.
(i) Use the basic clause in solicitations and contracts that are not firm-fixed price or fixed-price incentive.
(ii) Use alternate I in fixed-price-incentive solicitations and contracts.
(iii) Use alternate II in firm-fixed-price solicitations and contracts.
(2) Use the clause at 252.246-7002 , Warranty of Construction (Germany), instead of the clause at FAR 52.246-21, Warranty of Construction, in solicitations and contracts for construction when a fixed-price contract will be awarded and contract performance will be in Germany.
(3) When the solicitation includes the clause at 252.211-7003, Item Unique Identification and Valuation, which is prescribed in 211.274-5(a), and it is anticipated that the resulting contract will include a warranty for serialized items--
(i) Use the provision at 252.246-7005 , Notice of Warranty Tracking of Serialized Items, in the solicitation if the Government does not specify a warranty and offerors will be required to enter data with the offer;
(ii) Use the clause at 252.246-7006 , Warranty Tracking of Serialized Items, in the solicitation and contract; and
(iii) Include the following warranty attachments, available at https://www.pdrep.csd.disa.mil/pdrep_files/other/wsr.htm, in the solicitation and contract and see 246.710-70 : (A) Warranty Tracking Information. (B) Source of Repair Instructions.
Current Text
52.246-18 Warranty of Supplies of a Complex Nature.
As prescribed in 46.710(b)(1), insert a clause substantially as follows:
Warranty of Supplies of a Complex Nature (MAY 2001)
(a) Definitions. As used in this clause—
Acceptance means the act of an authorized representative of the Government by which the Government assumes for itself, or as an agent of another, ownership of existing and identified supplies, or approves specific services rendered, as partial or complete performance of the contract.
Supplies means the end items furnished by the Contractor and related services required under this contract. The word does not include "data."
(b) Contractor's obligations.
(1) The Contractor warrants that for ____ [ Contracting Officer shall state the specific warranty period after delivery, or the specified event whose occurrence will terminate the warranty period; e.g., the number of miles or hours of use, or combinations of any applicable events or periods of time ] all supplies furnished under this contract will be free from defects in material and workmanship and will conform with all requirements of this contract; provided, however, that with respect to Government-furnished property, the Contractor's warranty shall extend only to its proper installation, unless the Contractor performs some modification or other work on the property, in which case the Contractor's warranty shall extend to the modification or other work.
(2) Any supplies or parts thereof corrected or furnished in replacement shall be subject to the conditions of this clause to the same extent as supplies initially delivered. This warranty shall be equal in duration to that set forth in paragraph (b)(1) of this clause and shall run from the date of delivery of the corrected or replaced supplies.
(3) The Contractor shall not be obligated to correct or replace supplies if the facilities, tooling, drawings, or other equipment or supplies necessary to accomplish the correction or replacement have been made unavailable to the Contractor by action of the Government. In the event that correction or replacement has been directed, the Contractor shall promptly notify the Contracting Officer, in writing, of the nonavailability.
(4) The Contractor shall also prepare and furnish to the Government data and reports applicable to any correction required (including revision and updating of all affected data called for under this contract) at no increase in the contract price.
(5) When supplies are returned to the Contractor, the Contractor shall bear the transportation costs from the place of delivery specified in the contract (irrespective of the f.o.b. point or the point of acceptance) to the Contractor's plant and return.
(6) All implied warranties of merchantability and fitness for a particular purpose are excluded from any obligation contained in this contract.
(c) Remedies available to the Government.
(1) In the event of a breach of the Contractor's warranty in paragraph (b)(1) of this clause, the Government may, at no increase in contract price—
(i) Require the Contractor, at the place of delivery specified in the contract (irrespective of the f.o.b. point or the point of acceptance) or at the Contractor's plant, to repair or replace, at the Contractor's election, defective or nonconforming supplies; or
(ii) Require the Contractor to furnish at the Contractor's plant the materials or parts and installation instructions required to successfully accomplish the correction.
(2) If the Contracting Officer does not require correction or replacement of defective or nonconforming supplies or the Contractor is not obligated to correct or replace under paragraph (b)(3) of this clause, the Government shall be entitled to an equitable reduction in the contract price.
(3) The Contracting Officer shall notify the Contractor in writing of any breach of the warranty in paragraph (b) of this clause within ____ [ Contracting Officer shall insert specific period of time in which notice shall be given to the Contractor; e.g., 45 days after delivery of the nonconforming supplies.; 45 days of the last delivery under this contract.; or 45 days after discovery of the defect. ] The Contractor shall submit to the Contracting Officer a written recommendation within ____ [ Contracting Officer shall insert period of time ] as to the corrective action required to remedy the breach. After the notice of breach, but not later than ____ [ Contracting Officer shall insert period within which the warranty remedies should be exercised ] after receipt of the Contractor's recommendation for corrective action, the Contracting Officer may, in writing, direct correction or replacement as in paragraph (c)(1) of this clause, and the Contractor shall, notwithstanding any disagreement regarding the existence of a breach of warranty, comply with this direction. If it is later determined that the Contractor did not breach the warranty in paragraph (b)(1) of this clause, the contract price will be equitably adjusted.
(4) If supplies are corrected or replaced, the period for notification of a breach of the Contractor's warranty in paragraph (c)(3) of this clause shall be ____ [ Contracting Officer shall insert period within which the Contractor must be notified of a breach as to corrected or replaced supplies ] from the furnishing or return by the Contractor to the Government of the corrected or replaced supplies or parts thereof, or, if correction or replacement is effected by the Contractor at a Government or other activity, for ____ [ Contracting Officer shall insert period within which the Contractor must be notified of a breach of warranty as to corrected or replaced supplies ] thereafter.
(5) The rights and remedies of the Government provided in this clause are in addition to and do not limit any rights afforded to the Government by any other clause of the contract.
(End of clause)
Alternate I [Reserved]
Alternate II (APR 1984). If it is desirable to specify that necessary transportation incident to correction or replacement will be at the Government's expense (as might be the case if, for example, the cost of a warranty would otherwise be prohibitive), substitute a paragraph substantially the same as the following paragraph (b)(5) for paragraph (b)(5) of the basic clause:
(5) If correction or replacement is required and transportation of supplies in connection with correction or replacement is necessary, transportation charges and responsibility for the supplies while in transit shall be borne by the Government.
Alternate III (APR 1984). If a fixed-price incentive contract is contemplated, add a paragraph substantially the same as the following paragraph (c)(6) to the basic clause:
(6) All costs incurred or estimated to be incurred by the Contractor in complying with this clause shall be considered when negotiating the total final price under the Incentive Price Revision clause of this contract. After establishment of the total final price, Contractor compliance with this clause shall be at no increase in the total final price. Any equitable adjustments made under paragraph (c)(2) of this clause shall be governed by the paragraph entitled Equitable Adjustments Under Other Clauses in the Incentive Price Revision clause of this contract.
Alternate IV (APR 1984). If it is anticipated that recovery of the warranted item will involve considerable Government expense for disassembly and/or reassembly of larger items, add a paragraph substantially the same as the following paragraph (c)(6) to the basic clause. Redesignate the additional paragraph as ( c )( 7 ) if
Alternate III is also used:
(6) The Contractor shall be liable for the reasonable costs of disassembly and/or reassembly of larger items when it is necessary to remove the supplies to be inspected and/or returned for correction or replacement.
[48 FR 42478, Sept. 19, 1983, as amended at 60 FR 48256, Sept. 18, 1995; 66 FR 2136, Jan. 10, 2001]
Suggested Questions
You can ask your AI assistant:
- Should I include this provision in my solicitation?
- Does this clause apply to commercial acquisitions?
- Does this clause apply to R&D contracts under Part 35?
- Which alternate should I use for a multiple-award contract?
- Are there any active Class Deviations that modify this clause?
- What changed in the most recent amendment?