Authority
Section 814 of the William M. (Mac) Thornberry National Defense Authorization Act for Fiscal Year 2021 (Pub. L. 116-283), which modifies 10 U.S.C. 2306a
Summary
This deviation raises the certified cost or pricing data threshold for subcontract awards and contract modifications from $750,000 to $2 million. Contracting Officers must use deviation versions of five Federal Acquisition Regulation (FAR) clauses in lieu of the standard FAR text. The deviation implements section 814 of the FY2021 NDAA.
Contracting Officer Actions
1
Use $2 million in lieu of $750,000 as the threshold at FAR 15.403-4(a)(1) for obtaining certified cost or pricing data for subcontract awards and contract or subcontract modifications at any tier.
2
Use the deviation clauses in Attachment 1 in lieu of FAR 52.214-27, 52.214-28, 52.215-11, 52.215-12 and 52.215-13.
3
Do not use Alternate I of FAR 52.214-28, Alternate I of FAR 52.215-12 or Alternate I of FAR 52.215-13. These alternates conflict with the deviation clauses.
4
Upon contractor request, modify existing contracts as soon as practicable, without requiring consideration, to incorporate applicable deviation clauses.
Supersession
This revision supersedes Class Deviation 2022-O0001 issued October 5, 2021. The revision corrects the TINA threshold in 52.214-27 (DEVIATION) paragraph (a).
Duration
This deviation remains in effect until incorporated into the DFARS or otherwise rescinded.
Inflation adjustment
If the $2 million threshold is adjusted for inflation under FAR 1.109(a), the changed threshold applies for the remaining contract term unless a subsequent adjustment occurs.
Affected Provisions and Clauses
Clause Text Changes
Original (removed)
Deviation (added)
Unchanged
52.214-27 Price Reduction for Defective Certified Cost or Pricing Data—Modifications—Sealed Bidding: Paragraph (a)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
2 added, 18 removed
(a)
(a) This clause shall become operative only for any modification to this contract involving aggregate increases and/or decreases in costs, plus applicable profits, expected to exceed the threshold for the submission of certified cost or pricing data in Federal Acquisition Regulation (FAR) 15.403-4(a)(1) on the date of execution of the modification, except that this clause does not apply to a modification if an exception under FAR 15.403-1(b) applies.
(a)
This clause shall become operative only for any modification to this contract involving aggregate increases and/or decreases in costs, plus applicable profits, expected to exceed $2 million on the date of execution of the modification, except that this clause does not apply to a modification if an exception under FAR 15.403-1(b) applies.
Original (removed)
Deviation (added)
Unchanged
52.214-27 Price Reduction for Defective Certified Cost or Pricing Data—Modifications—Sealed Bidding: Paragraph (b)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
1 removed
(b)
(b) If any price, including profit, negotiated in connection with any modification under this clause, was increased by any significant amount because (1) the Contractor or a subcontractor furnished certified cost or pricing data that were not complete, accurate, and current as certified in its Certificate of Current Cost or Pricing Data, (2) a subcontractor or prospective subcontractor furnished the Contractor certified cost or pricing data that were not complete, accurate, and current as certified in the Contractor's Certificate of Current Cost or Pricing Data, or (3) any of these parties furnished data of any description that were not accurate, the price shall be reduced accordingly and the contract shall be modified to reflect the reduction. This right to a price reduction is limited to that resulting from defects in data relating to modifications for which this clause becomes operative under paragraph (a) of this clause.
(b)
If any price, including profit, negotiated in connection with any modification under this clause, was increased by any significant amount because (1) the Contractor or a subcontractor furnished certified cost or pricing data that were not complete, accurate, and current as certified in its Certificate of Current Cost or Pricing Data, (2) a subcontractor or prospective subcontractor furnished the Contractor certified cost or pricing data that were not complete, accurate, and current as certified in the Contractor's Certificate of Current Cost or Pricing Data, or (3) any of these parties furnished data of any description that were not accurate, the price shall be reduced accordingly and the contract shall be modified to reflect the reduction. This right to a price reduction is limited to that resulting from defects in data relating to modifications for which this clause becomes operative under paragraph (a) of this clause.
Original (removed)
Deviation (added)
Unchanged
52.214-27 Price Reduction for Defective Certified Cost or Pricing Data—Modifications—Sealed Bidding: Paragraph (c)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
1 removed
(c)
(c) Any reduction in the contract price under paragraph (b) of this clause due to defective data from a prospective subcontractor that was not subsequently awarded the subcontract shall be limited to the amount, plus applicable overhead and profit markup, by which (1) the actual subcontract or (2) the actual cost to the Contractor, if there was no subcontract, was less than the prospective subcontract cost estimate submitted by the Contractor; provided, that the actual subcontract price was not itself affected by defective certified cost or pricing data.
(c)
Any reduction in the contract price under paragraph (b) of this clause due to defective data from a prospective subcontractor that was not subsequently awarded the subcontract shall be limited to the amount, plus applicable overhead and profit markup, by which (1) the actual subcontract or (2) the actual cost to the Contractor, if there was no subcontract, was less than the prospective subcontract cost estimate submitted by the Contractor; provided, that the actual subcontract price was not itself affected by defective certified cost or pricing data.
Original (removed)
Deviation (added)
Unchanged
52.214-27 Price Reduction for Defective Certified Cost or Pricing Data—Modifications—Sealed Bidding: Paragraph (d)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
Original (removed)
Deviation (added)
Unchanged
52.214-27 Price Reduction for Defective Certified Cost or Pricing Data—Modifications—Sealed Bidding: Paragraph (e)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
86 added, 1 removed
(e)
(e) If any reduction in the contract price under this clause reduces the price of items for which payment was made prior to the date of the modification reflecting the price reduction, the Contractor shall be liable to and shall pay the United States at the time such overpayment is repaid—
(e)
If any reduction in the contract price under this clause reduces the price of items for which payment was made prior to the date of the modification reflecting the price reduction, the Contractor shall be liable to and shall pay the United States at the time such overpayment is repaid— (1) Interest compounded daily, as required by 26 U.S.C. 6622, on the amount of such overpayment to be computed from the date(s) of overpayment to the Contractor to the date the Government is repaid by the Contractor at the applicable underpayment rate effective for each quarter prescribed by the Secretary of the Treasury under 26 U.S.C. 6621(a)(2); and (2) A penalty equal to the amount of the overpayment, if the Contractor or subcontractor knowingly submitted certified cost or pricing data which were incomplete, inaccurate, or noncurrent.
Original (removed)
Deviation (added)
Unchanged
52.214-28 Subcontractor Certified Cost or Pricing Data—Modifications—Sealed Bidding: Paragraph (a)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
41 added, 2 removed
(a)
(a) The requirements of paragraphs (b) and (c) of this clause shall
(a)
The requirements of paragraphs (b) and (c) of this clause shall— (1) Become operative only for any modification to this contract involving aggregate increases and/or decreases in costs, plus applicable profits, expected to exceed $2 million on the date of execution of the modification, and (2) Be limited to such modifications.
Original (removed)
Deviation (added)
Unchanged
52.214-28 Subcontractor Certified Cost or Pricing Data—Modifications—Sealed Bidding: Paragraph (b)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
10 added, 31 removed
(b)
(b) Before awarding any subcontract expected to exceed the threshold for submission of certified cost or pricing data in FAR 15.403-4(a)(1), on the date of agreement on price or the date of award, whichever is later, or before pricing any subcontract modifications involving aggregate increases and/or decreases in costs, plus applicable profits, expected to exceed the threshold for submission of certified cost or pricing data in FAR 15.403-4(a)(1), the Contractor shall require the subcontractor to submit certified cost or pricing data (actually or by specific identification in writing), as part of the subcontractor's proposal in accordance with FAR 15.408, Table 15-2 (to include any information reasonably required to explain the subcontractor's estimating process such as the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data, and the nature and amount of any contingencies included in the price), unless an exception under FAR 15.403-1(b) applies. If the threshold for submission of certified cost or pricing data specified in FAR 15.403-4(a)(1) is adjusted for inflation as set forth in FAR 1.109(a), then pursuant to FAR 1.109(d) the changed threshold applies throughout the remaining term of the contract, unless there is a subsequent threshold adjustment.
(b)
Before awarding any subcontract expected to exceed $2 million, on the date of agreement on price or the date of award, whichever is later, or before pricing any subcontract modifications involving aggregate increases and/or decreases in costs, plus applicable profits, expected to exceed $2 million, the Contractor shall require the subcontractor to submit certified cost or pricing data (actually or by specific identification in writing), as part of the subcontractor's proposal in accordance with Federal Acquisition Regulation (FAR) 15.408, Table 15-2 (to include any information reasonably required to explain the subcontractor's estimating process such as the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data, and the nature and amount of any contingencies included in the price), unless an exception under FAR 15.403-1(b) applies. If the $2 million threshold for submission of certified cost or pricing data specified is adjusted for inflation as set forth in FAR 1.109(a), then pursuant to FAR 1.109(d) the changed threshold applies throughout the remaining term of the contract, unless there is a subsequent threshold adjustment.
Original (removed)
Deviation (added)
Unchanged
52.214-28 Subcontractor Certified Cost or Pricing Data—Modifications—Sealed Bidding: Paragraph (c)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
1 removed
(c)
(c) The Contractor shall require the subcontractor to certify in substantially the form prescribed in subsection 15.406-2 of the Federal Acquisition Regulation that, to the best of its knowledge and belief, the data submitted under paragraph (b) above were accurate, complete, and current as of the date of agreement on the negotiated price of the subcontract or subcontract modification.
(c)
The Contractor shall require the subcontractor to certify in substantially the form prescribed in subsection 15.406-2 of the Federal Acquisition Regulation that, to the best of its knowledge and belief, the data submitted under paragraph (b) above were accurate, complete, and current as of the date of agreement on the negotiated price of the subcontract or subcontract modification.
Original (removed)
Deviation (added)
Unchanged
52.214-28 Subcontractor Certified Cost or Pricing Data—Modifications—Sealed Bidding: Paragraph (d)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
2 added, 39 removed
(d)
(d) The Contractor shall insert the substance of this clause, including this paragraph (d), in each subcontract that, when entered into, exceeds the threshold for submission of certified cost or pricing data in FAR 15.403-4(a)(1). (End of clause) Alternate I (OCT 2025). As prescribed in 14.201-7(c)(1)(ii), substitute the following paragraph (b) in place of paragraph (b) of the basic clause:
(d)
The Contractor shall insert the substance of this clause, including this paragraph (d), in each subcontract that, when entered into, exceeds $2 million.
Original (removed)
Deviation (added)
Unchanged
52.215-11 Price Reduction for Defective Certified Cost or Pricing Data—Modifications: Paragraph (a)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
6 added, 18 removed
(a)
(a) This clause shall become operative only for any modification to this contract involving a pricing adjustment expected to exceed the threshold for submission of certified cost or pricing data in Federal Acquisition Regulation (FAR) 15.403-4(a)(1) on the date of execution of the modification, except that this clause does not apply to any modification if an exception under FAR 15.403-1(b) applies.
(a)
This clause shall become operative only for any modification to this contract involving a pricing adjustment expected to exceed $2 million on the date of execution of the modification, except that this clause does not apply to any modification if an exception under Federal Acquisition Regulation (FAR) 15.403-1(b) applies.
Original (removed)
Deviation (added)
Unchanged
52.215-11 Price Reduction for Defective Certified Cost or Pricing Data—Modifications: Paragraph (b)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
3 added, 4 removed
(b)
(b) If any price, including profit or fee, negotiated in connection with any modification under this clause, or any cost reimbursable under this contract, was increased by any significant amount because (1) the Contractor or a subcontractor furnished certified cost or pricing data that were not complete, accurate, and current as certified in its Certificate of Current Cost or Pricing Data, (2) a subcontractor or prospective subcontractor furnished the Contractor certified cost or pricing data that were not complete, accurate, and current as certified in the Contractor's Certificate of Current Cost or Pricing Data, or (3) any of these parties furnished data of any description that were not accurate, the price or cost shall be reduced accordingly and the contract shall be modified to reflect the reduction. This right to a price reduction is limited to that resulting from defects in data relating to modifications for which this clause becomes operative under paragraph (a) of this clause.
(b)
If any price, including profit or fee, negotiated in connection with any modification under this clause, or any cost reimbursable under this contract, was increased by any significant amount because— (1) The Contractor or a subcontractor furnished certified cost or pricing data that were not complete, accurate, and current as certified in its Certificate of Current Cost or Pricing Data; (2) A subcontractor or prospective subcontractor furnished the Contractor certified cost or pricing data that were not complete, accurate, and current as certified in the Contractor's Certificate of Current Cost or Pricing Data; or (3) Any of these parties furnished data of any description that were not accurate, the price or cost shall be reduced accordingly and the contract shall be modified to reflect the reduction. This right to a price reduction is limited to that resulting from defects in data relating to modifications for which this clause becomes operative under paragraph (a) of this clause.
Original (removed)
Deviation (added)
Unchanged
52.215-11 Price Reduction for Defective Certified Cost or Pricing Data—Modifications: Paragraph (c)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
4 added, 3 removed
(c)
(c) Any reduction in the contract price under paragraph (b) of this clause due to defective data from a prospective subcontractor that was not subsequently awarded the subcontract shall be limited to the amount, plus applicable overhead and profit markup, by which (1) the actual subcontract or (2) the actual cost to the Contractor, if there was no subcontract, was less than the prospective subcontract cost estimate submitted by the Contractor; provided, that the actual subcontract price was not itself affected by defective certified cost or pricing data.
(c)
Any reduction in the contract price under paragraph (b) of this clause due to defective data from a prospective subcontractor that was not subsequently awarded the subcontract shall be limited to the amount, plus applicable overhead and profit markup, by which— (1) The actual subcontract price; or (2) The actual cost to the Contractor, if there was no subcontract awarded, was less than the prospective subcontract cost estimate submitted by the Contractor; provided, that the actual subcontract price was not itself affected by defective certified cost or pricing data.
Original (removed)
Deviation (added)
Unchanged
52.215-11 Price Reduction for Defective Certified Cost or Pricing Data—Modifications: Paragraph (d)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
Original (removed)
Deviation (added)
Unchanged
52.215-11 Price Reduction for Defective Certified Cost or Pricing Data—Modifications: Paragraph (e)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
86 added, 1 removed
(e)
(e) If any reduction in the contract price under this clause reduces the price of items for which payment was made prior to the date of the modification reflecting the price reduction, the Contractor shall be liable to and shall pay the United States at the time such overpayment is repaid—
(e)
If any reduction in the contract price under this clause reduces the price of items for which payment was made prior to the date of the modification reflecting the price reduction, the Contractor shall be liable to and shall pay the United States at the time such overpayment is repaid— (1) Interest compounded daily, as required by 26 U.S.C. 6622, on the amount of such overpayment to be computed from the date(s) of overpayment to the Contractor to the date the Government is repaid by the Contractor at the applicable underpayment rate effective for each quarter prescribed by the Secretary of the Treasury under 26 U.S.C. 6621(a)(2); and (2) A penalty equal to the amount of the overpayment, if the Contractor or subcontractor knowingly submitted certified cost or pricing data that were incomplete, inaccurate, or noncurrent.
Original (removed)
Deviation (added)
Unchanged
52.215-12 Subcontractor Certified Cost or Pricing Data: Paragraph (a)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
10 added, 35 removed
(a)
(a) Before awarding any subcontract expected to exceed the threshold for submission of certified cost or pricing data in Federal Acquisition Regulation (FAR) 15.403-4(a)(1), on the date of agreement on price or the date of award, whichever is later; or before pricing any subcontract modification involving a pricing adjustment expected to exceed the threshold for submission of certified cost or pricing data in FAR 15.403-4(a)(1), the Contractor shall require the subcontractor to submit certified cost or pricing data (actually or by specific identification in writing), in accordance with FAR 15.408, Table 15-2 (to include any information reasonably required to explain the subcontractor's estimating process such as the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data, and the nature and amount of any contingencies included in the price), unless an exception under FAR 15.403-1(b) applies. If the threshold for submission of certified cost or pricing data specified in FAR 15.403-4(a)(1) is adjusted for inflation as set forth in FAR 1.109(a), then pursuant to FAR 1.109(d) the changed threshold applies throughout the remaining term of the contract, unless there is a subsequent threshold adjustment.
(a)
Before awarding any subcontract expected to exceed $2 million, on the date of agreement on price or the date of award, whichever is later; or before pricing any subcontract modification involving a pricing adjustment expected to exceed $2 million, the Contractor shall require the subcontractor to submit certified cost or pricing data (actually or by specific identification in writing), in accordance with Federal Acquisition Regulation (FAR) 15.408, Table 15-2 (to include any information reasonably required to explain the subcontractor's estimating process such as the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data, and the nature and amount of any contingencies included in the price), unless an exception under FAR 15.403-1(b) applies. If the $2 million threshold for submission of certified cost or pricing data is adjusted for inflation as set forth in FAR 1.109(a), then pursuant to FAR 1.109(d) the changed threshold applies throughout the remaining term of the contract, unless there is a subsequent threshold adjustment.
Original (removed)
Deviation (added)
Unchanged
52.215-12 Subcontractor Certified Cost or Pricing Data: Paragraph (b)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
1 removed
(b)
(b) The Contractor shall require the subcontractor to certify in substantially the form prescribed in FAR 15.406-2 that, to the best of its knowledge and belief, the data submitted under paragraph (a) of this clause were accurate, complete, and current as of the date of agreement on the negotiated price of the subcontract or subcontract modification.
(b)
The Contractor shall require the subcontractor to certify in substantially the form prescribed in FAR 15.406-2 that, to the best of its knowledge and belief, the data submitted under paragraph (a) of this clause were accurate, complete, and current as of the date of agreement on the negotiated price of the subcontract or subcontract modification.
Original (removed)
Deviation (added)
Unchanged
52.215-12 Subcontractor Certified Cost or Pricing Data: Paragraph (c)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
42 added, 10 removed
(c)
(c) In each subcontract that, when entered into, exceeds the threshold for submission of certified cost or pricing data in FAR 15.403-4(a)(1), the Contractor shall insert either—
(c)
In each subcontract that, when entered into, exceeds $2 million, the Contractor shall insert either— (1) The substance of this clause, including this paragraph (c), if paragraph (a) of this clause requires submission of certified cost or pricing data for the subcontract; or (2) The substance of the clause at 52.215-13, Subcontractor Certified Cost or Pricing Data—Modifications (DEVIATION 2022-O0001).
Original (removed)
Deviation (added)
Unchanged
52.215-13 Subcontractor Certified Cost or Pricing Data—Modifications: Paragraph (a)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
34 added, 1 removed
(a)
(a) The requirements of paragraphs (b) and (c) of this clause shall—
(a)
The requirements of paragraphs (b) and (c) of this clause shall— (1) Become operative only for any modification to this contract involving a pricing adjustment expected to exceed $2 million on the date of execution of the modification; and (2) Be limited to such modifications.
Original (removed)
Deviation (added)
Unchanged
52.215-13 Subcontractor Certified Cost or Pricing Data—Modifications: Paragraph (b)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
10 added, 32 removed
(b)
(b) Before awarding any subcontract expected to exceed the threshold for submission of certified cost or pricing data in FAR 15.403-4(a)(1), on the date of agreement on price or the date of award, whichever is later; or before pricing any subcontract modification involving a pricing adjustment expected to exceed the threshold for submission of certified cost or pricing data in FAR 15.403-4(a)(1), the Contractor shall require the subcontractor to submit certified cost or pricing data (actually or by specific identification in writing), in accordance with FAR 15.408, Table 15-2 (to include any information reasonably required to explain the subcontractor's estimating process such as the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data, and the nature and amount of any contingencies included in the price), unless an exception under FAR 15.403-1(b) applies. If the threshold for submission of certified cost or pricing data specified in FAR 15.403-4(a)(1) is adjusted for inflation as set forth in FAR 1.109(a), then pursuant to FAR 1.109(d) the changed threshold applies throughout the remaining term of the contract, unless there is a subsequent threshold adjustment.
(b)
Before awarding any subcontract expected to exceed $2 million, on the date of agreement on price or the date of award, whichever is later; or before pricing any subcontract modification involving a pricing adjustment expected to exceed $2 million, the Contractor shall require the subcontractor to submit certified cost or pricing data (actually or by specific identification in writing), in accordance with Federal Acquisition Regulation (FAR) 15.408, Table 15-2 (to include any information reasonably required to explain the subcontractor's estimating process such as the judgmental factors applied and the mathematical or other methods used in the estimate, including those used in projecting from known data, and the nature and amount of any contingencies included in the price), unless an exception under FAR 15.403-1(b) applies. If the $2 million threshold for submission of certified cost or pricing data is adjusted for inflation as set forth in FAR 1.109(a), then pursuant to FAR 1.109(d) the changed threshold applies throughout the remaining term of the contract, unless there is a subsequent threshold adjustment.
Original (removed)
Deviation (added)
Unchanged
52.215-13 Subcontractor Certified Cost or Pricing Data—Modifications: Paragraph (c)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
1 removed
(c)
(c) The Contractor shall require the subcontractor to certify in substantially the form prescribed in FAR 15.406-2 that, to the best of its knowledge and belief, the data submitted under paragraph (b) of this clause were accurate, complete, and current as of the date of agreement on the negotiated price of the subcontract or subcontract modification.
(c)
The Contractor shall require the subcontractor to certify in substantially the form prescribed in FAR 15.406-2 that, to the best of its knowledge and belief, the data submitted under paragraph (b) of this clause were accurate, complete, and current as of the date of agreement on the negotiated price of the subcontract or subcontract modification.
Original (removed)
Deviation (added)
Unchanged
52.215-13 Subcontractor Certified Cost or Pricing Data—Modifications: Paragraph (d)
Original: JUN 2020
Deviation: JUN 2020 (DEVIATION 2022-O0001)
2 added, 43 removed
(d)
(d) The Contractor shall insert the substance of this clause, including this paragraph (d), in each subcontract that exceeds the threshold for submission of certified cost or pricing data in FAR 15.403-4(a)(1) on the date of agreement on price or the date of award, whichever is later. (End of clause) Alternate I (OCT 2025). As prescribed in 15.408(e)(2), substitute the following paragraphs (a), (b), and (d) for paragraphs (a), (b), and (d) of the basic clause:
(d)
The Contractor shall insert the substance of this clause, including this paragraph (d), in each subcontract that exceeds $2 million on the date of agreement on price or the date of award, whichever is later.