This PGI section supplements: DFARS 208.7004-4 · FAR 8.7004-4
The corresponding FAR Part 8 and DFARS Part 208 have been overhauled under the RFO. PGI replacement text is provided in the RFO deviation attachment. View FAR Part 8

Current Content

(1) Unless otherwise agreed between the departments, May 31 is the cutoff date for the receipt of MIPRs citing expiring appropriations which must be obligated by September 30 of that fiscal year. If circumstances arise that require the submission of MIPRs citing expiring appropriations after the cutoff date, the requiring department will communicate with the acquiring department before submission to find out whether the acquiring department can execute a contract or otherwise obligate the funds by the end of the fiscal year. Acquiring departments will make every effort to obligate funds for all such MIPRs accepted after the cutoff date. However, acceptance of a late MIPR does not constitute assurance by the acquiring department that all such funds will be obligated.

(2) Nothing in these instructions is intended to restrict the processing of MIPRs when the acquiring department is capable of executing contracts or otherwise obligating funds before the end of the fiscal year.

(3) The May 31 cutoff date does not apply to MIPRs citing continuing appropriations.