(a) General.
(i) The objective of proposal analysis is to ensure that the final agreed-to price is fair and reasonable.
(A) When the contracting officer needs data to determine price reasonableness and the offeror will not furnish that data, use the following sequence of steps to resolve the issue:
(i) The contracting officer should make it clear what data is required and why it is needed to determine fair and reasonable prices, and should be flexible in requesting data in existing formats with appropriate explanations from the offeror.
(ii) If the offeror refuses to provide the data, the contracting officer should elevate the issue within the contracting activity.
(iii) Contracting activity management shall, with support from the contracting officer, discuss the issue with appropriate levels of the offeror’s management.
(iv) If the offeror continues to refuse to provide the data, contracting activity management shall elevate the issue to the head of the contracting activity for a decision in accordance with FAR 15.403-3(a)(4).
(v) The contracting officer shall document the contract file to describe—
(a) The data requested and the contracting officer’s need for that data;
(b) Why there is currently no other alternative but to procure the item from this particular source; and
(c) A written plan for avoiding this situation in the future (e.g., develop a second source by...; bring the procurement in house to the Government by...).
(vi) Consistent with the requirements at FAR 15.304 and 42.1502 and the DoD Guide to Collection and Use of Past Performance Information, Version 3, dated May 2003, the contracting officer shall, unless exempted by the HCA, provide input into the past performance system, noting the offeror’s refusal to provide the requested information.
(B) In some cases, supplies or services that are not subject to TINA may require a cost analysis (see paragraph (c) of this section). This will occur when a price analysis is not sufficient for determining prices to be fair and reasonable. In such cases, the contracting officer should consider the need for a Defense Contract Audit Agency audit of the cost data.
(C) Particular attention should be paid to sole source commercial products or commercial services. While the order of preference at FAR 15.402 must be followed, if the contracting officer cannot determine price reasonableness without obtaining data other than cost or pricing data from the offeror, at a minimum, the contracting officer must obtain appropriate data on the prices at which the same or similar items have been sold previously (often previous sales data was the basis of the commercial item determination and must be requested during price analysis of the data provided by the offeror). If previous sales data is not sufficient to determine price reasonableness, the contracting officer must obtain “data other than certified cost or pricing data” and, if necessary, perform a cost analysis.
(D) Analysis of termination proposals, including termination of any contract scope, should not rely solely on earned value management budgets or estimates for estimating the costs of all work deleted, or the cost of deleted work already performed (reference FAR Subpart 15.4, Table 15-2—Instructions for Submitting Cost/Price Proposals When Certified Cost or Pricing Data are Required, columns (2) and (3) of section III.B., Change Orders, Modifications, and Claims).
(b) Price analysis .
(i) See the Department of Defense Guidebook for Acquiring Commercial Items, Part B: Pricing Commercial Items, for detailed guidance about techniques and approaches to pricing commercial products and commercial services.
(v) Contracting officers must obtain and document sufficient data to confirm that previous prices paid by the Government were based on a thorough price and/or cost analysis. For example, it would not be sufficient to use price(s) from a database paid by another contracting officer without understanding the type of analysis that was performed to determine the reasonableness of the price(s), and without verifying that the quantities were similar for pricing purposes. This does not necessarily need to be another analysis, but there should be coordination with the other office that acknowledges an analysis was performed previously.
(vii) See the Department of Defense Guidebook for Acquiring Commercial Items, Part B: Pricing Commercial Items, for information about how to obtain advisory assistance from the DoD cadre of experts in the Defense Contract Management Agency (DCMA) Commercial Item Group (CIG) via email at dcma.boston-ma.eastern-rc.mbx.Commercial@mail.mil or at .
(c) Cost analysis.
(i) When the contracting officer cannot obtain sufficient data to perform a price analysis in accordance with the pricing steps in FAR 15.404-1(b), a cost analysis is required.
(ii) When a solicitation is not subject to TINA and a cost analysis is required, the contracting officer must clearly communicate to the offeror the cost data that will be needed to determine if the proposed price is fair and reasonable.
(iii) To the extent possible, when cost or pricing data are not required to be submitted in accordance with Table 15-2 of FAR 15.408, the contracting officer should accept the cost data in a format consistent with the offeror’s records.
(iv) The contracting officer must always consider the need for field pricing support from the Defense Contract Management Agency, the Defense Contract Audit Agency, and/or other agencies.
(e) Technical analysis. Requesting technical assistance is particularly important when evaluating pricing related to items that are “similar to” items being purchased or commercial products or commercial services that are “of a type” or require “minor modifications.” Technical analysis can assist in pricing these types of items by identifying any differences between the item being acquired and the “similar to” item. In particular, the technical review can assist in evaluating the changes that are required to get from the “similar to” item, to the item being solicited, so the contracting officer can determine sufficient price/cost analysis techniques when evaluating that the price for the item being solicited is fair and reasonable. See the Department of Defense Guidebook for Acquiring Commercial Items, Part B: Pricing Commercial Items, for information about how to obtain advisory assistance from the DoD cadre of experts in the (DCMA) (CIG) via email at dcma.boston-ma.eastern-rc.mbx.Commercial@mail.mil or at http://www.dcma.mil/commercial-item-group/.
(h) Review and justification of pass-through contracts.
(2)(A) This requirement applies to acquisitions that include the clause at FAR 52.215-23, Limitations on Pass-Through Charges, as prescribed at FAR 15.408(n)(2)(i)(B). When considering alternative approaches or making the determination that the contracting approach selected is in the best interest of the Government as required by FAR 15.404-1(h)(2), consider the following elements:
(1) The requirement, proposed prime contractor, and overall proposed contract value.
(2) The information provided in response to the provision at FAR 52.215-22, Limitations on Pass-Through Charges—Identification of Subcontract Effort, regarding the subcontracts, and the estimated value of the proposed subcontracts.
(3) The availability of alternative existing contracts that would allow direct access to the subcontractor, such as existing indefinite delivery/indefinite quantity contracts, Federal Supply Schedule contracts, or Governmentwide agency contracts. Perform market research as appropriate.
(4) Potential cost savings of directly contracting with the subcontractor.
(5) Feasibility of competition for the subcontracted effort or justification for single source procurement.
(6) Potential impacts to the contracting and program schedule for implementing a direct contract with the subcontractors or conducting a competition for the subcontracted effort.
(7) Changes in performance risk as result of eliminating prime contractor oversight and substituting direct government oversight. Risks may include loss of prime contractor knowledge of integration and program requirements, availability of government contracting and contract administration personnel, reduced system or program accountability of the prime contractor who is no longer responsible for the entire effort, impact on warranties.
(8) Subcontractor past performance and experience directly managing programs of this size.
(B) DoD components shall include reviews of compliance in routine procurement management reviews or other inspections.
Change History
| Detected | Type | Summary |
|---|---|---|
| detected 2026-04-17 | PGI_MODIFIED | PGI 215.404-1 updated: 30 lines added, 14 lines removed |
View diff--- previous +++ current @@ -1,15 +1,31 @@ (a) General. -(i) Follow the procedures at PGI 215.404-1 for proposal analysis. -(ii) For spare parts or support equipment, perform an analysis of-- (A) Those line items where the proposed price exceeds by 25 percent or more the lowest price the Government has paid within the most recent 12-month period based on reasonably available data; (B) Those line items where a comparison of the item description and the proposed price indicates a potential for overpricing; (C) Significant high-dollar-value items. If there are no obvious high-dollar-value items, include an analysis of a random sample of items; and (D) A random sample of the remaining low-dollar value items. Sample size may be determined by subjective judgment, e.g., experience with the offeror and the reliability of its estimating and accounting systems. -(b) Price analysis for commercial and noncommercial items. -(i) In the absence of adequate price competition in response to the solicitation, pricing based on market prices is the preferred method to establish a fair and reasonable price (see PGI 215.404-1 (b)(i)). -(ii) If the contracting officer determines that the information obtained through market research is insufficient to determine the reasonableness of price, the contracting officer shall consider information submitted by the offeror of recent purchase prices paid by the Government and commercial customers for the same or similar commercial products or commercial services under comparable terms and conditions in establishing price reasonableness on a subsequent purchase if the contracting officer is satisfied that the prices previously paid remain a valid reference for comparison. Price reasonableness shall not be based solely on historical prices paid by the Government (see 215.403-3(a)(1)). The contracting officer shall consider the totality of other relevant factors such as the time elapsed since the prior purchase and any differences in the quantities purchased ( 10 U.S.C. 3703(e) ). -(iii) If the contracting officer determines that the offeror cannot provide sufficient information as described in paragraph (b)(ii) of this section to determine the reasonableness of price, the contracting officer should request the offeror to submit information on-- (A) Prices paid for the same or similar items sold under different terms and conditions; (B) Prices paid for similar levels of work or effort on related products or services; (C) Prices paid for alternative solutions or approaches; and (D) Other relevant information that can serve as the basis for determining the reasonableness of price. -(iv) If the contracting officer determines that the pricing information submitted is not sufficient to determine the reasonableness of price, the contracting officer shall request other relevant information, to include cost data. However, no cost data may be required in any case in which there are sufficient non-Government sales of the same item to establish reasonableness of price (section 831 of the National Defense Authorization Act for Fiscal Year 2013 (Pub. L. 112-239)). -(v) When evaluating pricing data, the contracting officer shall consider materially differing terms and conditions, quantities, and market and economic factors (see PGI 215.404-1 Proposal analysis techniques.(b)(v)). For similar items, the contracting officer shall also consider material differences between the similar item and the item being procured (see FAR 15.404-1(b)(2)(ii)(B)). Material differences are those that could reasonably be expected to influence the contracting officer's determination of price reasonableness. The contracting officer shall consider the following factors when evaluating the relevance of the information available: (A) Market prices. (B) Age of data. -(1) Whether data is too old to be relevant depends on the industry (e.g., rapidly evolving technologies), product maturity (e.g., stable), economic factors (e.g., new sellers in the marketplace), and various other considerations. -(2) A pending sale may be relevant if, in the judgement of the contracting officer, it is probable at the anticipated price, and the sale could reasonably be expected to materially influence the contracting officer's determination of price reasonableness. The contracting officer may consult with the cognizant administrative contracting officers (ACOs) as they may have information about pending sales. (C) Volume and completeness of transaction data. Data must include a sufficient number of transactions to represent the range of relevant sales to all types of customers. The data must also include key information, such as date, quantity sold, part number, part nomenclature, sales price, and customer. If the number of transactions is insufficient or the data is incomplete, the contracting officer shall request additional sales data to evaluate price reasonableness. If the contractor cannot provide sufficient sales data, the contracting officer shall request other relevant information. (D) Nature of transactions. The nature of a sales transaction includes the information necessary to understand the transaction, such as terms and conditions, date, quantity sold, sale price, unique requirements, the type of customer (government, distributor, retail end-user, etc.), and related agreements. It also includes warranties, key product technical specifications, maintenance agreements, and preferred customer rewards. -(vi) The contracting officer shall consider catalog prices to be reliable when they are regularly maintained and supported by relevant sales data (including any related discounts, refunds, rebates, offsets, or other adjustments). The contracting officer may request that the offeror support differences between the proposed price(s), catalog price(s), and relevant sales data. -(vii) The contracting officer may consult with the DoD cadre of experts who are available to provide expert advice to the acquisition workforce in assisting with commercial product or commercial service determinations and price reasonableness determinations. The DoD cadre of experts is identified at PGI 215.404-1 (b)(vii). -(viii) When procuring a service or an end product identified by a material identifier that is available as described at 204.7603, the contracting officer shall consider the Supplier Performance Risk System price risk assessments in determining if a proposed price is consistent with historical prices paid for an item or otherwise creates a risk to the Government. See also 215.403-3(a)(1). -(h) Review and justification of pass-through contracts. Follow the procedures at PGI 215.404-1 (h)(2) when considering alternative approaches or making the determination that the contracting approach selected is in the best interest of the Government, as required by FAR 15.404-1(h)(2).+(i) The objective of proposal analysis is to ensure that the final agreed-to price is fair and reasonable. (A) When the contracting officer needs data to determine price reasonableness and the offeror will not furnish that data, use the following sequence of steps to resolve the issue: +(i) The contracting officer should make it clear what data is required and why it is needed to determine fair and reasonable prices, and should be flexible in requesting data in existing formats with appropriate explanations from the offeror. +(ii) If the offeror refuses to provide the data, the contracting officer should elevate the issue within the contracting activity. +(iii) Contracting activity management shall, with support from the contracting officer, discuss the issue with appropriate levels of the offeror's management. +(iv) If the offeror continues to refuse to provide the data, contracting activity management shall elevate the issue to the head of the contracting activity for a decision in accordance with FAR 15.403-3(a)(4). +(v) The contracting officer shall document the contract file to describe-- +(a) The data requested and the contracting officer's need for that data; +(b) Why there is currently no other alternative but to procure the item from this particular source; and +(c) A written plan for avoiding this situation in the future (e.g., develop a second source by...; bring the procurement in house to the Government by...). +(vi) Consistent with the requirements at FAR 15.304 and 42.1502 and the DoD Guide to Collection and Use of Past Performance Information, Version 3, dated May 2003, the contracting officer shall, unless exempted by the HCA, provide input into the past performance system, noting the offeror's refusal to provide the requested information. (B) In some cases, supplies or services that are not subject to TINA may require a cost analysis (see paragraph (c) of this section). This will occur when a price analysis is not sufficient for determining prices to be fair and reasonable. In such cases, the contracting officer should consider the need for a Defense Contract Audit Agency audit of the cost data. (C) Particular attention should be paid to sole source commercial products or commercial services. While the order of preference at FAR 15.402 must be followed, if the contracting officer cannot determine price reasonableness without obtaining data other than cost or pricing data from the offeror, at a minimum, the contracting officer must obtain appropriate data on the prices at which the same or similar items have been sold previously (often previous sales data was the basis of the commercial item determination and must be requested during price analysis of the data provided by the offeror). If previous sales data is not sufficient to determine price reasonableness, the contracting officer must obtain "data other than certified cost or pricing data" and, if necessary, perform a cost analysis. (D) Analysis of termination proposals, including termination of any contract scope, should not rely solely on earned value management budgets or estimates for estimating the costs of all work deleted, or the cost of deleted work already performed (reference FAR Subpart 15.4, Table 15-2--Instructions for Submitting Cost/Price Proposals When Certified Cost or Pricing Data are Required, columns (2) and (3) of section III.B., Change Orders, Modifications, and Claims). +(b) Price analysis . + +(i) See the Department of Defense Guidebook for Acquiring Commercial Items, Part B: Pricing Commercial Items, for detailed guidance about techniques and approaches to pricing commercial products and commercial services. +(v) Contracting officers must obtain and document sufficient data to confirm that previous prices paid by the Government were based on a thorough price and/or cost analysis. For example, it would not be sufficient to use price(s) from a database paid by another contracting officer without understanding the type of analysis that was performed to determine the reasonableness of the price(s), and without verifying that the quantities were similar for pricing purposes. This does not necessarily need to be another analysis, but there should be coordination with the other office that acknowledges an analysis was performed previously. +(vii) See the Department of Defense Guidebook for Acquiring Commercial Items, Part B: Pricing Commercial Items, for information about how to obtain advisory assistance from the DoD cadre of experts in the Defense Contract Management Agency (DCMA) Commercial Item Group (CIG) via email at dcma.boston-ma.eastern-rc.mbx.Commercial@mail.mil or at . +(c) Cost analysis. +(i) When the contracting officer cannot obtain sufficient data to perform a price analysis in accordance with the pricing steps in FAR 15.404-1(b), a cost analysis is required. +(ii) When a solicitation is not subject to TINA and a cost analysis is required, the contracting officer must clearly communicate to the offeror the cost data that will be needed to determine if the proposed price is fair and reasonable. +(iii) To the extent possible, when cost or pricing data are not required to be submitted in accordance with Table 15-2 of FAR 15.408, the contracting officer should accept the cost data in a format consistent with the offeror's records. +(iv) The contracting officer must always consider the need for field pricing support from the Defense Contract Management Agency, the Defense Contract Audit Agency, and/or other agencies. +(e) Technical analysis. Requesting technical assistance is particularly important when evaluating pricing related to items that are "similar to" items being purchased or commercial products or commercial services that are "of a type" or require "minor modifications." Technical analysis can assist in pricing these types of items by identifying any differences between the item being acquired and the "similar to" item. In particular, the technical review can assist in evaluating the changes that are required to get from the "similar to" item, to the item being solicited, so the contracting officer can determine sufficient price/cost analysis techniques when evaluating that the price for the item being solicited is fair and reasonable. See the Department of Defense Guidebook for Acquiring Commercial Items, Part B: Pricing Commercial Items, for information about how to obtain advisory assistance from the DoD cadre of experts in the (DCMA) (CIG) via email at dcma.boston-ma.eastern-rc.mbx.Commercial@mail.mil or at http://www.dcma.mil/commercial-item-group/. +(h) Review and justification of pass-through contracts. (2)(A) This requirement applies to acquisitions that include the clause at FAR 52.215-23, Limitations on Pass-Through Charges, as prescribed at FAR 15.408(n)(2)(i)(B). When considering alternative approaches or making the determination that the contracting approach selected is in the best interest of the Government as required by FAR 15.404-1(h)(2), consider the following elements: +(1) The requirement, proposed prime contractor, and overall proposed contract value. +(2) The information provided in response to the provision at FAR 52.215-22, Limitations on Pass-Through Charges--Identification of Subcontract Effort, regarding the subcontracts, and the estimated value of the proposed subcontracts. +(3) The availability of alternative existing contracts that would allow direct access to the subcontractor, such as existing indefinite delivery/indefinite quantity contracts, Federal Supply Schedule contracts, or Governmentwide agency contracts. Perform market research as appropriate. +(4) Potential cost savings of directly contracting with the subcontractor. +(5) Feasibility of competition for the subcontracted effort or justification for single source procurement. +(6) Potential impacts to the contracting and program schedule for implementing a direct contract with the subcontractors or conducting a competition for the subcontracted effort. +(7) Changes in performance risk as result of eliminating prime contractor oversight and substituting direct government oversight. Risks may include loss of prime contractor knowledge of integration and program requirements, availability of government contracting and contract administration personnel, reduced system or program accountability of the prime contractor who is no longer responsible for the entire effort, impact on warranties. +(8) Subcontractor past performance and experience directly managing programs of this size. (B) DoD components shall include reviews of compliance in routine procurement management reviews or other inspections. |
||