A community resource for the acquisition workforce not a .gov website
part52.dev Federal Acquisition Clause Monitor
This PGI section supplements: DFARS 216.104-70 · FAR 16.104-70
The corresponding FAR Part 16 and DFARS Part 216 have been overhauled under the RFO. PGI replacement text is provided in the RFO deviation attachment. View FAR Part 16

Current Content

(1) General. There are several categories of research and development (R&D) contracts: research, exploratory development, advanced development, engineering development, and operational systems development (see DFARS 235.001 for definitions). Each category has a primary technical or functional objective. Different parts of a project may fit several categories. The contract type must fit the work required, not just the classification of the overall program.

(2) Research and exploratory development.

(i) Price is not necessarily the primary factor in determining the contract type.

(ii) The nature of the work to be performed will usually result in a cost-plus award fee, cost-plus fixed fee term, cost-no-fee, or cost-sharing contract.

(iii) If the Government and the contractor can identify and agree upon the level of contractor effort required, the contracting officer may select a firm fixed-price level-of-effort contract, except see DFARS 235.006.

(iv) If the Government and the contractor agree that an incentive arrangement is desirable and capable of being evaluated after completion of the work, the contracting officer may use an incentive type contract.

(3) Advanced development.

(i) The nature of the work to be performed often results in a cost-plus fixed fee completion type contract.

(ii) Contracting officers may select incentive contracts if—

(A) Realistic and measurable targets are identified; and

(B) Achievement of those targets is predictable with a reasonable degree of accuracy.

(iii) Contracting officers should not use contracts with only cost incentives where—

(A) There will be a large number of major technical changes; or

(B) Actions beyond the control of the contractor may influence the contractor's achievement of cost targets.

(4) Engineering development and operational systems development.

(i) When selecting contract types, also consider—

(A) The degree to which the project is clearly defined, which in turn affects the contractor's ability to provide accurate cost estimates;

(B) The need for effort that will overlap that of earlier stages;

(C) The need for firm technical direction by the Government; and

(D) The degree of configuration control the Government will exercise.

(ii) For development efforts, particularly for major defense systems, the preferred contract type is cost reimbursement.

(iii) Contracting officers should use fixed-price type contracts when risk has been reduced to the extent that realistic pricing can occur; e.g., when a program has reached the final stages of development and technical risks are minimal, except see DFARS 235.006.

Change History

Detected Type Summary
detected 2026-04-17 [PGI] PGI_MODIFIED PGI 216.104-70 updated: 14 lines added, 2 lines removed
View diff
--- previous
+++ current
@@ -1,2 +1,14 @@
-Follow the procedures at PGI 216.104-70 for selecting the appropriate research and development contract type, and see 235.006
-(b) for additional approval requirements.+(1) General. There are several categories of research and development (R&D) contracts: research, exploratory development, advanced development, engineering development, and operational systems development (see DFARS 235.001 for definitions). Each category has a primary technical or functional objective. Different parts of a project may fit several categories. The contract type must fit the work required, not just the classification of the overall program.
+(2) Research and exploratory development.
+(i) Price is not necessarily the primary factor in determining the contract type.
+(ii) The nature of the work to be performed will usually result in a cost-plus award fee, cost-plus fixed fee term, cost-no-fee, or cost-sharing contract.
+(iii) If the Government and the contractor can identify and agree upon the level of contractor effort required, the contracting officer may select a firm fixed-price level-of-effort contract, except see DFARS 235.006.
+(iv) If the Government and the contractor agree that an incentive arrangement is desirable and capable of being evaluated after completion of the work, the contracting officer may use an incentive type contract.
+(3) Advanced development.
+(i) The nature of the work to be performed often results in a cost-plus fixed fee completion type contract.
+(ii) Contracting officers may select incentive contracts if-- (A) Realistic and measurable targets are identified; and (B) Achievement of those targets is predictable with a reasonable degree of accuracy.
+(iii) Contracting officers should not use contracts with only cost incentives where-- (A) There will be a large number of major technical changes; or (B) Actions beyond the control of the contractor may influence the contractor's achievement of cost targets.
+(4) Engineering development and operational systems development.
+(i) When selecting contract types, also consider-- (A) The degree to which the project is clearly defined, which in turn affects the contractor's ability to provide accurate cost estimates; (B) The need for effort that will overlap that of earlier stages; (C) The need for firm technical direction by the Government; and (D) The degree of configuration control the Government will exercise.
+(ii) For development efforts, particularly for major defense systems, the preferred contract type is cost reimbursement.