A community resource for the acquisition workforce not a .gov website
part52.dev Federal Acquisition Clause Monitor
This PGI section supplements: DFARS 217.7404-1 · FAR 17.7404-1
The corresponding FAR Part 17 and DFARS Part 217 have been overhauled under the RFO. PGI replacement text is provided in the RFO deviation attachment. View FAR Part 17

Current Content

(1) The requiring activity, in coordination with the contracting office, will prepare the request for approval package for an undefinitized contract action (UCA) requirement. The approval package shall—

(i) Document why a UCA is required (for letter contracts see DFARS 216.603);

(ii) Provide a detailed explanation for the need to begin performance before definitization;

(iii) Address the adverse impact on agency requirements that would result from delays in beginning performance;

(iv) Identify the risk of using a UCA and the means by which the Government will mitigate such risk;

(v) Identify and justify the specific contractual instrument to be used;

(vi) Establish limitations on the obligation of funds; and

(vii) Provide the definitization schedule of agreed-upon events that support timely definitization.

(2) A sample format with certain variations for letter contracts is provided at this website: http://www.acq.osd.mil/dpap/dars/pgi/docs/Template_for_UCA_Authorization_Requests.pdf.

Change History

Detected Type Summary
detected 2026-04-17 [PGI] PGI_MODIFIED PGI 217.7404-1 updated: 9 lines added, 4 lines removed
View diff
--- previous
+++ current
@@ -1,4 +1,9 @@
-The contracting officer shall obtain approval from the head of the contracting activity before--
-(a) Entering into a UCA. The request for approval must fully explain the need to begin performance before definitization, including the adverse impact on agency requirements resulting from delays in beginning performance.
-(b) Including requirements for non-urgent spare parts and support equipment in a UCA. The request should show that inclusion of the non-urgent items is consistent with good business practices and in the best interest of the United States.
-(c) Modifying the scope of a UCA when performance has already begun. The request should show that the modification is consistent with good business practices and in the best interests of the United States.+(1) The requiring activity, in coordination with the contracting office, will prepare the request for approval package for an undefinitized contract action (UCA) requirement. The approval package shall--
+(i) Document why a UCA is required (for letter contracts see DFARS 216.603);
+(ii) Provide a detailed explanation for the need to begin performance before definitization;
+(iii) Address the adverse impact on agency requirements that would result from delays in beginning performance;
+(iv) Identify the risk of using a UCA and the means by which the Government will mitigate such risk;
+(v) Identify and justify the specific contractual instrument to be used;
+(vi) Establish limitations on the obligation of funds; and
+(vii) Provide the definitization schedule of agreed-upon events that support timely definitization.
+(2) A sample format with certain variations for letter contracts is provided at this website: http://www.acq.osd.mil/dpap/dars/pgi/docs/Template_for_UCA_Authorization_Requests.pdf.
Sources: Search on acquisition.gov · View on acq.osd.mil