This PGI section supplements: DFARS 225.202 · FAR 25.202
The corresponding FAR Part 25 and DFARS Part 225 have been overhauled under the RFO. PGI replacement text is provided in the RFO deviation attachment. View FAR Part 25

Current Content

(a)(2) A nonavailability determination is not required for construction materials listed in FAR 25.104(a). For other materials, a nonavailability determination shall be approved at the levels specified in (b)(ii). Use the estimated value of the construction materials to determine the approval level. A nonavailability determination is not required before January 1, 2030, if there is an offer for foreign construction material that exceeds 55 percent domestic content (also see FAR 25.204(b)(1)(ii) and (b)(2)(ii)).