This PGI section supplements: DFARS 225.270 · FAR 25.270
The corresponding FAR Part 25 and DFARS Part 225 have been overhauled under the RFO. PGI replacement text is provided in the RFO deviation attachment. View FAR Part 25

Current Content

(a) For DoD energy savings service contracts, the requirements documents from the requiring activity are required to specify if construction and construction materials will be used during the performance of the contract. If specified, the contracting officer shall—

(1) Include the FAR provisions and clauses regarding construction materials that implement the Buy American statute; and

(2) Enforce them based on the associated terms and conditions of the contract.

(b) See FAR subpart 23.2, Energy Savings Performance Contracts.

Change History

Detected Type Summary
detected 2026-04-17 [PGI] PGI_MODIFIED PGI 225.270 updated: 4 lines added, 1 lines removed
View diff
--- previous
+++ current
@@ -1 +1,4 @@
-If construction and construction materials will be used during the performance of a contract for DoD energy savings service requirements, see PGI 225.270 Energy savings service contracts. for additional guidance.+(a) For DoD energy savings service contracts, the requirements documents from the requiring activity are required to specify if construction and construction materials will be used during the performance of the contract. If specified, the contracting officer shall--
+(1) Include the FAR provisions and clauses regarding construction materials that implement the Buy American statute; and
+(2) Enforce them based on the associated terms and conditions of the contract.
+(b) See FAR subpart 23.2, Energy Savings Performance Contracts.
Sources: Search on acquisition.gov · View on acq.osd.mil