This PGI section supplements: DFARS 232.704-70 · FAR 32.704-70
The corresponding FAR Part 32 and DFARS Part 232 have been overhauled under the RFO. PGI replacement text is provided in the RFO deviation attachment. View FAR Part 32

Current Content

(a) Upon receipt of the contractor’s notice under paragraph (c) of the clause at 252.232-7007 , Limitation of Government’s Obligation, the contracting officer shall promptly provide written notice to the contractor that the Government is—

(1) Allotting additional funds for continued performance and increasing the Government’s limitation of obligation in a specified amount;

(2) Terminating the contract; or

(3) Considering whether to allot additional funds; and

(i) The contractor is entitled by the contract terms to stop work when the Government’s limitation of obligation is reached; and

(ii) Any costs expended beyond the Government’s limitation of obligation are at the contractor’s risk.

(b) Upon learning that the contract will receive no further funds, the contracting officer shall promptly give the contractor written notice of the Government’s decision and terminate for the convenience of the Government.

(c) The contracting officer shall ensure that, in accordance with paragraph (b) of the clause at 252.232-7007 , Limitation of Government’s Obligation, sufficient funds are allotted to the contract to cover the total amount payable to the contractor in the event of termination for the convenience of the Government.

Sources: Search on acquisition.gov · View on acq.osd.mil