This PGI section supplements: DFARS 236.270 · FAR 36.270
The corresponding FAR Part 36 and DFARS Part 236 have been overhauled under the RFO. PGI replacement text is provided in the RFO deviation attachment. View FAR Part 36

Current Content

(a) 10 U.S.C. 2858 requires agency head approval to expedite the completion date of a contract funded by a Military Construction Appropriations Act, if additional costs are involved. This approval authority may not be redelegated. The approval authority must—

(1) Certify that the additional expenditures are necessary to protect the National interest; and

(2) Establish a reasonable completion date for the project.

(b) The contracting officer may approve an expedited completion date if no additional costs are involved.