This PGI section supplements: DFARS 242.1106 · FAR 42.1106
The corresponding FAR Part 42 and DFARS Part 242 have been overhauled under the RFO. PGI replacement text is provided in the RFO deviation attachment. View FAR Part 42

Current Content

(a) See DoDI 5000.2, Operation of the Defense Acquisition System, for reporting requirements for defense technology projects and acquisition programs.

(b)(i) Within four working days after receipt of the contractor's report, the CAO must provide the report and any required comments to the contracting officer and, unless otherwise specified in the contract, the inventory control manager.

(ii) If the contractor's report indicates that the contract is on schedule and the CAO agrees, the CAO does not need to add further comments. In all other cases, the CAO must add comments and recommend a course of action.