A community resource for the acquisition workforce not a .gov website
part52.dev Federal Acquisition Clause Monitor
This PGI section supplements: DFARS 252.217-7013 · FAR 52.217-7013
The corresponding FAR Part 52 and DFARS Part 252 have been overhauled under the RFO. PGI replacement text is provided in the RFO deviation attachment. View FAR Part 52

Current Content

As prescribed in 217.7104 (a), use the following clause:

GUARANTEES (DEC 1991)

(a) In the event any work performed or materials furnished by the contractor under the Master Agreement prove defective or deficient within 90 days from the date of redelivery of the vessel(s), the Contractor, as directed by the Contracting Officer and at its own expense, shall correct and repair the deficiency to the satisfaction of the Contracting Officer.

(b) If the Contractor or any subcontractor has a guarantee for work performed or materials furnished that exceeds the 90 day period, the Government shall be entitled to rely upon the longer guarantee until its expiration.

(c) With respect to any individual work item identified as incomplete at the time of redelivery of the vessel(s), the guarantee period shall run from the date the item is completed.

(d) If practicable, the Government shall give the Contractor an opportunity to correct the deficiency.

(1) If the Contracting Officer determines it is not practicable or is otherwise not advisable to return the vessel(s) to the Contractor, or the Contractor fails to proceed with the repairs promptly, the Contracting Officer may direct that the repairs be performed elsewhere, at the Contractor's expense.

(2) If correction and repairs are performed by other than the Contractor, the Contracting Officer may discharge the Contractor's liability by making an equitable deduction in the price of the job order.

(e) The Contractor's liability shall extend for an additional 90 day guarantee period on those defects or deficiencies that the Contractor corrected.

(f) At the option of the Contracting Officer, defects and deficiencies may be left uncorrected. In that event, the Contractor and Contracting Officer shall negotiate an equitable reduction in the job price. Failure to agree upon an equitable reduction shall constitute a dispute under the Disputes clause of this agreement.

(End of clause)

Sources: Search on acquisition.gov · View on acq.osd.mil