PGI 241.202

Procedures.
Source .docx attachment →
Effective Date
February 1, 2026
Class Deviation
DFARS Part

This text is not in eCFR or DITA. It is extracted from the .docx attachment for Class Deviation 2026-O0039, which directs contracting officers to use it in place of the codified PGI. The parsed text is a convenience layer; the .docx attachment is authoritative.

(1) Connection and service charges. The Government may pay a connection charge when required to cover the cost of the necessary connecting facilities. A connection charge based on the estimated labor cost of installing and removing the facility must not include salvage cost. A lump-sum connection charge must be no more than the agreed cost of the connecting facilities less net salvage. The order of precedence for contractual treatment of connection and service charges is—

(i) No connection charge.

(ii) Termination liability. Use when an obligation is necessary to secure the required services. The obligation must be not more than the agreed connection charge, less any net salvage material costs. Use of a termination liability instead of a connection charge requires the approval of the service power procurement officer or designee.

(iii) Connection charge, refundable. Use a refundable connection charge when the supplier refuses to provide the facilities based on lack of capital or published rules which prohibit providing up-front funding. The contract should provide for refund of the connection charge within five years unless a longer period or omission of the refund requirement is authorized by the service power procurement officer or designee.

(iv) Connection and service charges, nonrefundable. The Government may pay certain nonrefundable, nonrecurring charges including service initiation charges, a contribution in aid of construction, membership fees, and charges required by the supplier's rules and regulations to be paid by the customer. If possible, consider sharing with other than Government users the use of (and costs for) facilities when large nonrefundable charges are required.

(2)(A) Do not use the connection charge provisions for the installation of Government-owned distribution lines and facilities. The acquisition of such facilities must be authorized by legislation and accomplished in accordance with FAR Part 36. Also, do not use the connection charge provisions for the installation of new facilities related to the supplier's production and general “backbone” system unless authorized by legislation.

(B) Construction labor standards ordinarily do not apply to construction accomplished under the connection charge provisions of this part. However, if installation includes construction of a public building or public work per FAR 36.102, construction labor standards may apply.

Authoritative source

Issued as an attachment to the Office of the Secretary of Defense memorandum for Class Deviation 2026-O0039, signed February 1, 2026. Verify against the attachment before relying on this text.

Codified PGI

The codified text remains published on acquisition.gov but is superseded by this Class Deviation. View codified PGI 241.202.