A community resource for the acquisition workforce not a .gov website
part52.dev Federal Acquisition Clause Monitor
R-DFARS PGI Section Revision 1

PGI 243.304

Administration.
Source .docx attachment →
Effective Date
August 5, 2026
Class Deviation
DFARS Part

This text is not in eCFR or DITA. It is extracted from the .docx attachment for Class Deviation 2026-O0034, which directs contracting officers to use it in place of the codified PGI. The parsed text is a convenience layer; the .docx attachment is authoritative.

(1) Whenever practicable, provide advance notice of a proposed change order to the administrative contracting officer (ACO).

(i) The ACO must review the proposed change order to ensure compatibility with the status of performance.

(ii) If the contractor has progressed beyond the effective point specified in the proposed change order, the ACO must determine the earliest practical point at which the change order could be made effective and must advise the contracting officer.

(2) If a change order has been issued and the effective date has been determined to be impracticable, the contracting officer must—

(i) Issue another change order to correct, revise, or supersede the first change order; then

(ii) Definitize by supplemental agreement citing both change orders.

Authoritative source

Issued as an attachment to the Office of the Secretary of Defense memorandum for Class Deviation 2026-O0034, signed August 5, 2026. Verify against the attachment before relying on this text.

Codified PGI

No codified counterpart is tracked for PGI 243.304. This section exists only in the Class Deviation.