252.217-7007 Payments. As prescribed in 217.7104(a), use the following clause: Payments (DEC 1991) (a) Progress payments, as used in this clause, means payments made before completion of work in progress under a job order. (b) Upon submission by the Contractor of invoices in the form and number of copies directed by the Contracting Officer, and as approved by the Contracting Officer, the Government will make progress payments as work progresses under the job order. (1) Generally, the Contractor may submit invoices on a semi-monthly basis, unless expenditures justify a more frequent submission. (2) The Government need not make progress payments for invoices aggregating less than $5,000. (3) The Contracting Officer shall approve progress payments based on the value, computed on the price of the job order, of labor and materials incorporated in the work, materials suitably stored at the site of the work, and preparatory work completed, less the aggregate of any previous payments. (4) Upon request, the Contractor will furnish the Contracting Officer any reports concerning expenditures on the work to date that the Contracting Officer may require. (c) The Government will retain until final completion and acceptance of all work covered by the job order, an amount estimated or approved by the Contracting Officer under paragraph (b) of this clause. The amount retained will be in accordance with the rate authorized by Congress for Naval vessel repair contracts at the time of job order award. (d) The Contracting Officer may direct that progress payments be based on the price of the job order as adjusted as a result of change orders under the Changes clause of the Master Agreement. If the Contracting Officer does not so direct— (1) Payments of any increases shall be made from time to time after the amount of the increase is determined under the Changes clause of the Master Agreement; and (2) Reductions resulting from decreases shall be made for the purposes of subsequent progress payments as soon as the amounts are determined under the Changes clause of the Master Agreement. (e) Upon completion of the work under a job order and final inspection and acceptance, and upon submission of invoices in such form and with such copies as the Contracting Officer may prescribe, the Contractor shall be paid for the price of the job order, as adjusted pursuant to the Changes clause of the Master Agreement, less any performance reserves deemed necessary by the Contracting Officer, and less the amount of any previous payments. (f) All materials, equipment, or any other property or work in process covered by the progress payments made by the Government, upon the making of those progress payments, shall become the sole property of the Government, and are subject to the provisions of the Title clause of the Master Agreement. (End of clause)
The prescription shown below is from the codified eCFR. Under the RFO, the prescribing section may have been revised, relocated or reserved. See the deviation memorandum for the current prescription authority.
View deviation: 2026-O0043 → · View deviation: 2026-O0027 →R-DFARS Prescription Source
This clause is prescribed in the R-DFARS by the following deviation:
-
2026-O0027
— DFARS RFO Implementation (Part 17)
(DFARS Part 217)
Add clause 252.217-7007
217.7104(a)
(1) 252.217-7003, Changes.
(2) 252.217-7004, Job Orders and Compensation.
(3) 252.217-7005, Inspection and Manner of Doing Work.
(4) 252.217-7006, Title.
(5) 252.217-7007, Payments.
(6) 252.217-7008, Bonds.
(7) 252.217-7009, Default.
(8) 252.217-7010, Performance.
(9) 252.217-7011, Access to Vessel.
(10) 252.217-7012, Liability and Insurance.
(11) 252.217-7013, Guarantees.
(12) 252.217-7014, Discharge of Liens.
(13) 252.217-7015, Safety and Health.
(14) 252.217-7016, Plant Protection, as applicable. (b)(1) Incorporate in solicitations for, and in, job orders, the clauses in the master agreement, and any other clauses on subjects not covered by the master agreement, but applicable to the job order to be awarded.
(2) Use the clause at 252.217-7016, Plant Protection, in job orders where performance is to occur at the contractor's facility.
Regulatory Stack
The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.
R-DFARS
R-DFARS Prescription
Per Deviation 2026-O0027 (DFARS Part 217)
DFARS
DFARS Supplement (eCFR)
⚠ May be superseded by RFO
217.7104(a)
(1) 252.217-7003, Changes.
(2) 252.217-7004, Job Orders and Compensation.
(3) 252.217-7005, Inspection and Manner of Doing Work.
(4) 252.217-7006, Title.
(5) 252.217-7007, Payments.
(6) 252.217-7008, Bonds.
(7) 252.217-7009, Default.
(8) 252.217-7010, Performance.
(9) 252.217-7011, Access to Vessel.
(10) 252.217-7012, Liability and Insurance.
(11) 252.217-7013, Guarantees.
(12) 252.217-7014, Discharge of Liens.
(13) 252.217-7015, Safety and Health.
(14) 252.217-7016, Plant Protection, as applicable. (b)(1) Incorporate in solicitations for, and in, job orders, the clauses in the master agreement, and any other clauses on subjects not covered by the master agreement, but applicable to the job order to be awarded.
(2) Use the clause at 252.217-7016, Plant Protection, in job orders where performance is to occur at the contractor's facility.
Version History
Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.
No version history available from eCFR.