FAR Clause ACTIVE

52.211-12

Liquidated Damages—Construction.
View on acquisition.gov · View on eCFR.gov
Effective Date
SEP 2000
Active Deviations
1
Versions
1 (since 2017-01-01)
RFO
RFO Version Available

The Revolutionary FAR Overhaul has published a revised version of this clause. The RFO version supersedes the eCFR text below for contracts using the RFO model; see the RFO deviation for applicability.

View RFO version
DEV
This clause is modified by 1 active class deviation
  • 2026-O0013 — DFARS RFO Implementation (Part 11)
    Add clause 52.211-12
View per-deviation details →
52.211-12 Liquidated Damages—Construction.

As prescribed in 11.503(b), insert the following clause in solicitations and contracts:

Liquidated Damages—Construction (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of __ [
Contracting Officer insert amount
] for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

[65 FR 46067, July 26, 2000]
RFO
Prescription superseded under the RFO

The prescription shown below is from the codified eCFR. The Revolutionary FAR Overhaul relocates this clause's prescription as follows:

  • 11.50311.403 (prescriptive text also revised)
  • 211.503211.403 (prescriptive text also revised)

See the deviation memorandum for the current prescription authority.

View deviation: 2026-O0013 →

R-DFARS Prescription Source

This clause is prescribed in the R-DFARS by the following deviation:

  • 2026-O0013 — DFARS RFO Implementation (Part 11) (DFARS Part 211)
    Add clause 52.211-12
11.503(b)
(b) Use the clause at 52.211-12, Liquidated Damages-Construction, in solicitations and contracts for construction, other than cost-plus-fixed-fee, when the contracting officer determines that liquidated damages are appropriate (see 11.501(a)). If the contract specifies more than one completion date for separate parts or stages of the work, revise paragraph (a) of the clause to state the amount of liquidated damages for delay of each separate part or stage of the work.

DFARS Supplementary Guidance

211.503
(b) Use the clause at FAR 52.211-12, Liquidated Damages--Construction, in all construction contracts exceeding $900,000, except cost-plus-fixed-fee contracts or contracts where the contractor cannot control the pace of the work. Use of the clause in contracts of $900,000 or less is optional.
Prescription data sourced from eCFR as of 2026-06-10 03:16 UTC. Cross-references within the prescription are not resolved automatically.

Regulatory Stack

The layers of regulation that govern this clause, from the FAR prescription through agency-specific supplements and any active deviations.

RFO RFO Version Overhauled clause text
The Revolutionary FAR Overhaul publishes a revised version of this clause. See the RFO Version tab for the controlling authority under the RFO model.

Search on acquisition.gov

R-DFARS R-DFARS Prescription Per Deviation 2026-O0013 (DFARS Part 211)
2026-O0013: DFARS RFO Implementation (Part 11) — DFARS Part 211

View Deviation 2026-O0013 →

FAR FAR Prescription ⚠ May be superseded by RFO 11.503(b)
(b) Use the clause at 52.211-12, Liquidated Damages-Construction, in solicitations and contracts for construction, other than cost-plus-fixed-fee, when the contracting officer determines that liquidated damages are appropriate (see 11.501(a)). If the contract specifies more than one completion date for separate parts or stages of the work, revise paragraph (a) of the clause to state the amount of liquidated damages for delay of each separate part or stage of the work.

View on acquisition.gov · View on eCFR.gov

DFARS DFARS Supplement (eCFR) ⚠ May be superseded by RFO 211.503
(b) Use the clause at FAR 52.211-12, Liquidated Damages--Construction, in all construction contracts exceeding $900,000, except cost-plus-fixed-fee contracts or contracts where the contractor cannot control the pace of the work. Use of the clause in contracts of $900,000 or less is optional.

Search on acquisition.gov · View on eCFR.gov

Version History

Version history is sourced from the codified eCFR. Changes published only as class deviations or by the Revolutionary FAR Overhaul do not appear here until they are incorporated into the eCFR. For RFO-driven changes see the RFO Version tab and any active deviations cited above.

No version history available from eCFR.

RFO Version

Comparison of the codified eCFR text against the Revolutionary FAR Overhaul revision. Highlights show additions (green) and deletions (red, struck through).

Clause Text

Substantive changes. The RFO version differs materially from the eCFR text.
eCFR (codified)
RFO (implemented)
Unchanged
52.211-12 Liquidated Damages-Construction.
eCFR (codified)
RFO (implemented)
1 added, 1 removed
As prescribed in 11.503(b), insert the following clause in solicitations and contracts:
As prescribed in 11.403(b), insert the following clause in solicitations and contracts:
2 added, 2 removed
Liquidated Damages—Construction (SEP 2000)
Liquidated Damages-Construction (Sept 2000)
1 added, 1 removed
(a)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of __ [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.
(a)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of ____________ [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.
6 removed
[65 FR 46067, July 26, 2000]
Applied to DoD contracts via Class Deviation 2026-O0013 (effective 2026-02-01) .

Prescription

Minor revisions. The RFO prescription has formatting or editorial changes from the eCFR prescription.
eCFR (codified)
RFO (implemented)
Unchanged
52.211-12 Liquidated Damages-Construction.: Prescription
eCFR (codified)
RFO (implemented)
1 added, 3 removed
(b)
(b) Use the clause at 52.211-12, Liquidated Damages-Construction, in solicitations and contracts for construction, other than cost-plus-fixed-fee, when the contracting officer determines that liquidated damages are appropriate (see 11.501(a)). If the contract specifies more than one completion date for separate parts or stages of the work, revise paragraph (a) of the clause to state the amount of liquidated damages for delay of each separate part or stage of the work.
(b)
(b) Use the clause at 52.211-12, Liquidated Damages-Construction, in solicitations and contracts for construction, other than cost-plus-fixed-fee, when the contracting officer determines that liquidated damages are appropriate. If the contract specifies more than one completion date for separate parts or stages of the work, revise paragraph (a) of the clause to state the amount of liquidated damages for delay of each separate part or stage of the work.

Source: acquisition.gov RFO Part 52 · Prescribing Part 11