This text comes from the Word attachment to class deviation 2026-O0043, not from acquisition.gov. The deviation memo directs contracting officers to use it in place of the codified PGI. The source attachment linked below is authoritative.

Text

(a) There may be situations where the numeric order of the modifications to a contract does not reflect the order in which those changes to the contract take effect.

(b) To establish the sequence of modifications to a contract or order, the modifications will be applied in the following order—

(1) Modifications will be applied in order of the effective date on the modification;

(2) In the event of two or more modifications with the same effective date, modifications will be applied in signature date order; and

(3) In the event of two or more modifications with the same effective date and the same signature date, procuring contracting office modifications will be applied in numeric order, followed by contract administration office modifications in numeric order.