PGI 234.7202

Procedures.
Source .docx attachment →
Effective Date
August 5, 2026
Class Deviation
DFARS Part

This text is not in eCFR or DITA. It is extracted from the .docx attachment for Class Deviation 2026-O0011, which directs contracting officers to use it in place of the codified PGI. The parsed text is a convenience layer; the .docx attachment is authoritative.

(b) Use of cost-reimbursement line items for production of major defense acquisition programs. (1) For additional contract type approval requirements for cost-reimbursement

contracts, see subpart 216.3.

(e) Development and demonstration of initial or additional prototype units.

(3) Upon request by Defense Pricing, Contracting, and Acquisition Policy (Contract Policy), contracting activities must provide the benefits derived from the use of contract line items or contract options for the development and demonstration or initial production of technology developed under the contract, or the delivery of initial or additional

items in accordance with DFARS 235.102.

Authoritative source

Issued as an attachment to the Office of the Secretary of Defense memorandum for Class Deviation 2026-O0011, signed August 5, 2026. Verify against the attachment before relying on this text.

Codified PGI

No codified counterpart is tracked for PGI 234.7202. This section exists only in the Class Deviation.